1a
Material price variance 1580 favourable
Material quantity variance. -$3234. unfavorable
1b
Labour rate variance. -$4296. Unfavorable
Labour efficiency variance -$2130 unfavorable
Explanation;
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.32 per micron Direct labor: 1.4 hours per toy at $7.10 per hour During July, the company produced 4,700 Maze toys. The toy's production data for the month are as follows: Direct materials: 73,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.35 per micron Direct labor: 1.5 hours per toy at $7.10 per hour During July, the company produced 4,500 Maze toys. The toy's production data for the month are as follows: Direct materials: 70,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.34 per micron Direct labor: 1.1 hours per toy at $7.10 per hour During July, the company produced 5,200 Maze toys. The toy's production data for the month are as follows: Direct materials: 74,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $1.50 per micron Direct labor: 1.3 hours per toy at $21 per hour During July, the company produced 3,000 Maze toys. The toy's production data for the month are as follows: Direct materials. 25,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.32 per micron Direct labor: 1.5 hours per toy at $7.10 per hour During July, the company produced 5,500 Maze toys. The toy's production data for the month are as follows: Direct materials: 79,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.31 per micron Direct labor: 1.4 hours per toy at $7.20 per hour During July, the company produced 5,100 Maze toys. The toy's production data for the month are as follows: Direct materials. 75,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy Direct materials: 6 microns per toy at $0.34 per micron Direct labor: 12 hours per toy at $710 per hour During July, the company produced 4,800 Maze toys. The toy's production data for the month are as follows: Direct materials: 74,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.33 per micron Direct labor: 1.4 hours per toy at $7.30 per hour During July, the company produced 5,200 Maze toys. The toy's production data for the month are as follows: Direct materials: 76,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.34 per micron Direct labor: 1.3 hours per toy at $7.50 per hour During July, the company produced 4,700 Maze toys. The toy's production data for the month are as follows: Direct materials: 72,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.31 per micron Direct labor: 1.1 hours per toy at $6.80 per hour During July, the company produced 5,500 Maze toys. The toy's production data for the month are as follows: Direct materials: 77,000 microns were purchased at a cost of...