Ashton Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materiRequirement 1. Compute the (a) budgeted indirect-cost rate and (b) actual indirect-cost rate. Why do they differ? Identify thRequirement 2. What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and (b) actual costiCompany names may be different but the structure is the same! Please replace names with new company names if this applies! Thank you!

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Requirement 1
Budgeted indirect costs Budgeted direct labour hours Budgeted indirect cost rate
                 8,300,000                          166,000                               50 per DLH
Actual indirect costs Actual direct labour hours Actual indirect cost rate
                 6,642,000                          162,000                               41 per DLH
Requirement 2
a) Normal costing
Model Budgeted indirect cost rate Actual direct labour hours Indirect costs Direct costs Total costs
Laguna                                     50                            960               48,000         145,025       193,025
Mission                                     50                         1,060               53,000         169,205       222,205
b) Actual costing
Model Actual indirect cost rate Actual direct labour hours Indirect costs Direct costs Total costs
Laguna                                     41                            960               39,360         145,025       184,385
Mission                                     41                         1,060               43,460         169,205       212,665
Add a comment
Know the answer?
Add Answer to:
Company names may be different but the structure is the same! Please replace names with new...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Avery budgets 2017 assembly-support costs to be $8,100,000 and 2017 direct labor-hours to be 135,000. At the end of 2017, Avery is comparing the costs of several jobs that were started and completed in 2017. (Click the icon to view the data.)...

  • 1 Data Table Laguna Model Construction period Direct materials costs Direct labor costs Direct labor-hours Feb-June...

    1 Data Table Laguna Model Construction period Direct materials costs Direct labor costs Direct labor-hours Feb-June 2017 106,440 $ 36,625 $ Mission Model May-Oct 2017 127,250 41,130 1,090 $ 970 Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2017 actual assembly-support costs were $7,425,000, and the actual direct labor-hours were 165,000. Print Done X Requirements 1. Compute the...

  • Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166,000. At the end of 2017, Andrews is comparing the costs of several jobs that were started and completed in 2017 E (Click the icon to view the...

  • materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base...

    materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Anderson budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166.000. At the end of 2017, Anderson is comparing the costs of several jobs that were started and completed in 2017 (Click the icon to view the data) Read the requirements Requirement 1. Compute the (a) budgeted indirect.cost rate and (b) actual indirect.cost...

  • Help me calculate the total costs using normal costing for each model! Acre Construction assemblies residential...

    Help me calculate the total costs using normal costing for each model! Acre Construction assemblies residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor hours is the location base for assembly support costs in December 2016. Acre budgets 2017 by support costs to be $8.000.000 and 2017 direct labor hours to be 100,000. At the end of 201 Acre is comparing the costs of several...

  • Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $ 8,000,000 and 2017 direct labor-hours to be 160,000 . At the end of 2017 , Andrews is comparing the costs of several jobs that were started and completed in 2017 .Direct materials and direct...

  • Job costing, normal and actual costing. Atkinson Construction assembles residential houses

    Job costing, normal and actual costing. Atkinson Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Atkinson budgets 2017 assembly-support costs to be $ 8,800,000 and 2017 direct labor-hours to be 220,000.At the end of 2017, Atkinson is comparing the costs of several jobs that were started and completed in 2017 .Laguna...

  • E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with...

    E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Attleboro budgets 2017 assembly-support costs to be $8,600,000 and 2017 direct labor-hours to be 215,000. At the end of 2017, Attleboro is comparing the costs of several jobs that were started and completed in 2017. (Click the...

  • Craden Solutions designs Web pages for clients in the education sector. The company's job-costing system has...

    Craden Solutions designs Web pages for clients in the education sector. The company's job-costing system has a single direct cost category (Web-designing labor) and a single indirect cost pool composed of all overhead costs. Overhead costs are allocated to individual jobs based on direct labor-hours. The company employs six Web designers. Budgeted and actual information regarding Craden Solutions follows: (Click the icon to view the data.) Read the requirements. Requirement 1. Compute the direct-cost rate and the indirect-cost rate per...

  • 1. Compute the (a) budgeted Y UNI What are the job costs of the Laguna Model...

    1. Compute the (a) budgeted Y UNI What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and Why might Atkinson Construction prefer normal costing over actual costing? 4-24 Budgeted manufacturing overhead rate, allocated manufacturing overhead. Taylor Company uses bosting. It allocates manufacturing overhead costs using a budgeted rate per machine-hour. The following data are available for 2017: Budgeted manufacturing overhead costs $3,800,000 Budgeted machine-hours 200,000 Actual manufacturing overhead costs $3,660,000 Actual machine-hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT