Question

It took MegaTech, Inc. 200,000 labor-hours to produce the first of several oil drilling rigs for...

It took MegaTech, Inc. 200,000 labor-hours to produce the first of several oil drilling rigs for Antarctic exploration. Your company, Natural Resources, Inc. has agreed to purchase the fifth oil drilling rig from their manufacturing yard. Assume that MegaTech experiences a learning rate of 75%. At a labor rate of $38 per hour, what should you, as the purchasing agent expect to pay for the fifth unit? TN = T1C, Where TN = Time needed to produce the Nth unit

Rate, labor/hr

$38

learning rate

0.75

T1 = Time needed to produce the first unit

200,000

C5th =learning curve coefficient given, look for it in table.

TN

Total cost

a.

TN is $102,600

b.

Total cost is $3,898,800

c.

C5th =learning curve coefficient given, look for it in table is 0.513

alternative without table. It took MegaTech, Inc. 100,000 labor-hours to produce the first of several oil drilling rigs for Antarctic exploration. Your company, Natural Resources, Inc. has agreed to purchase the fifth oil drilling rig from their manufacturing yard. Assume that MegaTech experiences a learning rate of 80%. At a labor rate of $35 per hour, How long should all five oil-drilling rigs take to complete? TN = T1C, Where TN = Time needed to produce the Nth unit

labor hour

$35

learning rate

0.8

a = the time required for the initial unit of output

100,000

X, the Nth unit

1

2

3

4

5

a. b = the slope of the learning curve, represented as: log decimal learning rate/log 2

b. TNx, Time needed to produce the Nth unit

c. TN cumulative

d. total costs

a.

b = the slope of the learning curve, represented as: log decimal learning rate/log 2 is -0.3219

b.

TNx, Time needed to produce the third unit is less than 64,000

c.

TN cumulative time for all units is $373,774

d.

total costs is $13,082,094

*Multiple Answers May Be Selected For Each Question*

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1st question

learning curve coefficient given C = 0.513 for learning rate 75% and for 5th unit

So, Tn = 200000*0.513 = 102600

Total cost is 102600*38 = 3898800

all the statements a. b. and c. are correct


Alternative without table

Formula

Correct answers are a.

b = the slope of the learning curve, represented as: log decimal learning rate/log 2 is -0.3219 = LOG(0.8)/LOG(2) = -0.3219

c.TN cumulative time for all units is $373,774

d.total costs is $13,082,094

b. is incorrect as time taken to produce 3rd unit is 70120 hours

Add a comment
Know the answer?
Add Answer to:
It took MegaTech, Inc. 200,000 labor-hours to produce the first of several oil drilling rigs for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • If 200 labor hours were required to produce the first unit in a production run, and...

    If 200 labor hours were required to produce the first unit in a production run, and n labor hours were required to produce the seventh unit. Find the value of n if the learning curve rate during production is 80%.?

  • Harper Ltd is a manufacturer of rowing boats. It has designed a new boat called the...

    Harper Ltd is a manufacturer of rowing boats. It has designed a new boat called the Seafarer and expects to produce the Seafarer in a continuous operation over an 18 month period During this period, it is expected that a total of sixteen Seafarer's will be produced and sold. The production of the Seafarer is a labour intensive operation and units are produced one after another The costs of producing the first Seafarer are as follows Skilled Labour 1,000 hours...

  • From the last question.... You are an experienced machinist with a small tool shop. You have...

    From the last question.... You are an experienced machinist with a small tool shop. You have been asked to submit a bid to produce twelve (12) special clamps for a new die that is under construction. You estimate that the material costs (metal and fasteners) for each clamp are $150.00. You also estimate that 9.49 labor hours are needed to produce the first clamp. The value of your labor is $50/hour. Your potential customer is receptive to your bid from...

  • 40. The labour cost to construct the first unit of a special piece of equipment was...

    40. The labour cost to construct the first unit of a special piece of equipment was $126,000. If labour costs are subject to a 90% learning curve, what will be the cost to build the second unit? Use the following values as needed to respond In(95%) / ln(2)s-0074 In(90%) /ln(2) =-0.152 In(8596) / ln(2) =-0.234 In(80%) / In(2) =-0.322 n(75%)/In(2) =-0.415 In(70%)/In(2) -0.515 a) $126,000 b) $113,000 c) $100,800 d) $113,400 Answer: d 41 A firm will build 8 units...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT