Use the information in the table and assume that a worker is
expected to devote half-time (four hours per day) to this project
with work taking place on a 5-day-per-week basis. What is the total
resource requirement for the project?
Activity | Predecessor | Hours per Day | Time (Days) |
A | -- | 4 | 6 |
B | A | 4 | 11 |
C | A | 5 | 5 |
D | B | 4 | 6 |
E | B | 4 | 6 |
F | B | 6 | 3 |
G | C, D | 8 | 11 |
H | E, F | 8 | 8 |
J | G, H | 3 | 10 |
K | J | 6 | 4 |
365 hours |
||
320 hours |
||
310 hours |
||
335 hours |
total resource requirement for the project = Hours per day * Time (days)
Total resource requirement for the project = 4*6+4*11+5*5+4*6+4*6+6*3+8*11+8*8+3*10+6*4
total resource requirement for the project = 365 hours. (OPTION A)
Please leave a like. thank you.
Use the information in the table and assume that a worker is expected to devote half-time...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) A minus− 5 B A 4 C A 6 D B 6 E B 4 F C 4 G D 6 H E, F 7 Carl's team should be able to complete the project in nothing days. Critical path activities for Carl's project are .
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...
Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A C 9 B D 5 B E 7 C, D F 6 D G 4 C H 7 E, F, G Activity Duration ES EF LS LF Float A 5 0 5 0 5 B 7 5 12 5 12 C 9 12 21 12 21 D 5 12 17 16 21 E 7 21 28 21 28 F 6 17 23 22 28...
1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task. b) Find the critical path and expected project competition time? c) What is the probability of...
I need help Software Project Management question Q1. For the following table of information: a) Draw a network diagram (Activity on Arrow) b) List down all the network paths c) Determine the critical path(s) Activity Predecessor Duration A Start 5 days B A 2 days C A 3 days D B 4 days E C 6 days F C 3 days G D, E 4 days H F 2 days I G 3 days J H 1...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) - ITMO OWNono Ana E, F D GH a) The activities on the critical path are b) The project length is days. A-B-E-G-1 A-B-D-H-1 A-C-F-G-
Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H A, C, F, G A, C, E, H How much...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) S A Figure 1 C A 4 5 5 F 5 F G E, F D GH 2 3 H The correct AOA precedence diagram is shown in a Figure 2 Q Figure 3
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float Activity description immediate predecessor Expected time (Weeks) A - 5 B - 4 C A 7 D B 7 E B 8 F B 5 G C,D 8 H E,I 11 I F 2 J F 12 K H,I 11 2.convert the above into activity on the node