Question

8. (16 points) The CengageCompany makes Elmotovs. It has developed the following per nit standard costs for 2019 for each itection 14 points te SHOW ALL COMPUTATIONS OR NO CREDIT GIVEN The answer to this question could be submitted differently than w

8. (16 points) The CengageCompany makes Elmotovs. It has developed the following per nit standard costs for 2019 for each item: Direct Dixest Manufacturing Labor Materials Overhead Standard Quantity 4 pounds 3 hours 3 hours $3.00/db $8.00/b $4.00/DLH Standard Price $24.00 Unit Standard Cost $12.00 $12.00 In 2019, the company expected to produce 20,000 units of toys and planned a level of 60,000 hours of direct labor Actual results for 2019 are presented below: 1. Direct materials purchased and used were 84,000 pounds at a cost of $235,200. 2. Direct labor costs were $518,500 for 61,000 direct labor hours actually worked. 3. Actual manufacturing overhead was $240,000 4. Actual production was 20,500 units. INSTRUCTIONS Compute the following variances: 1. Direct materials: total, price and quantity 2. Direct labor: total, price and quantity 3. Total overhead variance
ction 14 points te SHOW ALL COMPUTATIONS OR NO CREDIT GIVEN The answer to this question could be submitted differently than what is presented here. For example-you could use the matrix approach Do not embed the formulas in the cells-you must write out the formulas. Place answer Show calculations here V 11(1) Total materials variance: 5 Materials price variance: 9Materials quantity variance: 71(3) total overhead variance
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Calculation

Answer

1

(1) Total material variance:

Actual total direct material cost – Total standard cost for actual quantity

2

=$ 235,200 - $ 12 x 20,500

($ 10,800)

F

3

=$ 235,200 - $ 246,000 = -$ 10,800

4

5

Material price variance:

(Actual price – Standard price) x Actual quantity

($ 16,800)

F

6

=($ 2.8 - $ 3) x 84,000

7

=- $ 0.2 x 84,000 = - $ 16,800

8

9

Material quantity variance:

(Actual quantity - Standard quantity) x Standard price per unit

$ 6,000

U

10

=(84,000 – 82,000) x $ 3

11

= 2,000 x $ 3 = $ 6,000

12

13

(2) Total labor variance:

Actual total labor cost – Total standard labor cost for actual quantity

$ 26,500

U

14

= $ 518,500 - $ 24 x 20,500

15

= $ 518,500 - $ 492,000 = $ 26,500

16

17

Labor price variance:

(Actual rate – Standard rate) x Actual labor hours

$ 30,500

U

18

= ($ 8.5 - $ 8) x 61,000

19

= $ 0.5 x 61,000 = $ 30,500

20

21

Labor quantity variance:

(Actual hours used - Standard hours allowed) x Standard rate

($ 4,000)       

F

22

= (61,000 – 61,500) x $ 8

23

= -500 x $ 8 = - $ 4,000       

24

25

26

27

Total overhead variance

Actual overhead – Total standard overhead allowed

($6,000)

F

= $ 240,000 - $ 12 x 20,500

= $ 240,000 - $ 246,000 = - $ 6,000    

Explanation:

Total material variance = Actual total direct material cost – Total standard cost for actual quantity

                                          = $ 235,200 - $ 12 x 20,500 = $ 235,200 - $ 246,000

                                                                                           = -$ 10,800          F

                Actual price of direct material = Total material cost/Total units purchased

                                                               = $ 235,200/84,000 = $ 2.8/lb

                                                                                                                                    

Direct material price variance = (Actual price – Standard price) x Actual quantity

                                                      = ($ 2.8 - $ 3) x 84,000 = - $ 0.2 x 84,000 = - $ 16,800     F

Standard quantity of material required for actual production = Unit standard quantity x actual unit

                                                                                               = 4 x 20,500 = 82,000 pounds

Direct material quantity variance = (Actual quantity - Standard quantity) x Standard price per unit

                                                           = (84,000 – 82,000) x $ 3 = 2,000 x $ 3 = $ 6,000        U

Total material variance = Actual total labor cost – Total standard labor cost for actual quantity

                                          = $ 518,500 - $ 24 x 20,500 = $ 518,500 - $ 492,000

                                                                                           = $ 26,500     U

Actual labor rate = Total labor cost/total hour worked = $ 518,500/61,000 = $ 8.5 PLH

Direct labor price variance = (Actual rate – Standard rate) x Actual quantity

                                          = ($ 8.5 - $ 8) x 61,000 = $ 0.5 x 61,000 = $ 30,500     U

Standard labor hours allowed = Unit standard labor hour x Actual unit produced

                                               = 3 x 20,500 = 61,500 Hrs

Direct labor quantity variance = (Actual hours used - Standard hours allowed) x Standard rate

                                               = (61,000 – 61,500) x $ 8 = -500 x $ 8 = - $ 4,000        F

Total overhead variance = Actual overhead – Total standard overhead

                                       = $ 240,000 - $ 12 x 20,500 = $ 240,000 - $ 246,000 = - $ 6,000     F

Add a comment
Know the answer?
Add Answer to:
8. (16 points) The CengageCompany makes Elmotovs. It has developed the following per nit standard costs for 2019 for ea...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hector Company has developed the following standard costs for its product for 2019: HECTOR COMPANY Standard Cost Card...

    Hector Company has developed the following standard costs for its product for 2019: HECTOR COMPANY Standard Cost Card Product A Cost Element Standard Quantity × Standard Price = Standard Cost Direct materials 4 pounds $3 $12 Direct labor 3 hours 8 24 Manufacturing overhead 3 hours 4 12 $48 The company expected to produce 30,000 units of Product A in 2020 and work 90,000 direct labor hours. Actual results for 2020 are as follows: • 31,000 units of Product A...

  • Unit 6 Lab-Principles of Accounting II Exercise 213 Dart Company developed the following standard costs for...

    Unit 6 Lab-Principles of Accounting II Exercise 213 Dart Company developed the following standard costs for its product for 2019: DART COMPANY Standard Cost Card Cost Element   Standard Quantity × Standard Price = Standard Cost Direct materials 4 pounds $ 5 $20 Direct labor 2 hours 10 20 Variable overhead 2 hours 4 8 Fixed overhead 2 hours 2 4 $52 The company expected to work at the 120,000 direct labor hours level of activity and produce 60,000 units of...

  • Q1. Dart Company developed the following standard costs for its product for 2016: DART COMPANY Standard...

    Q1. Dart Company developed the following standard costs for its product for 2016: DART COMPANY Standard Cost Card                                                      Cost Elements Standard Quantity   * Standard Price     = Standard Cost Direct materials      4 pounds $5 $20 Direct labor       2 hours 10 20 Variable overhead     2 hours 4 8 Fixed overhead   2 hours 2 4 $52                                                                                                                                                                                                               The company expected to work at the 120,000 direct labor hours level of activity and produce 60,000 units of product. Actual results for 2016 were as follows:...

  • Blumenthal Manufacturing makes a product with the following standard costs: Standard Quantity or Hours Standard Price...

    Blumenthal Manufacturing makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Direct materials 3.5 pounds $3.00 per pound Direct labor 0.8 hours $19.00 per hour Variable overhead 0.8 hours $8.00 per hour In July the company produced 3,500 units using 12,240 pounds of the direct material and 1,500 direct labor-hours. During the month, the company purchased 13,000 pounds of the direct material at a cost of $35,100. The actual direct labor cost was...

  • Chrisman Corporation makes a product with the following standard costs: Inputs Direct materials Direct labor Variable...

    Chrisman Corporation makes a product with the following standard costs: Inputs Direct materials Direct labor Variable overhead Standard Quantity or Hours 8.8 pounds 1.4 hours 1.4 hours Standard Price or Rate $2.00 per pound $20.00 per hour $10.00 per hour The company reported the following results concerning this product in August. Actual output Raw materials used in production Raw materials purchased Actual direct labor hours Actual cost of raw materials purchased Actual cost of direct labor Actual cost of variable...

  • VEGA COMPANY Standard Cost Card Product A Cost Element Standard Quantity Standard Price - Standard Cost...

    VEGA COMPANY Standard Cost Card Product A Cost Element Standard Quantity Standard Price - Standard Cost Direct materials 4 pounds Direct labor 3 hours Manufacturing overhead 3 hours Actual results for 2016 are as follows: • 25 000 units of Product A were produced • Actual direct labor costs were $630,800 for 76.000 direct labor hours worked • Actual direct materials purchased and used during the year cost $283 500 for 105,000 pounds • Actual variable overhead incurred was $130,000...

  • Mlar Corporation makes a product with the following standard costs: Direct materials Direct labor Variable overhead...

    Mlar Corporation makes a product with the following standard costs: Direct materials Direct labor Variable overhead Standard Quantity or Hours 12.5 pounds 0.8 hours 0.8 hours Standard Price or Rate $12.00 per pound $37.00 per hour $17.50 per hour In January the company produced 3.480 units using 13,920 pounds of the direct material and 2,904 direct labor hours. During the month, the company purchased 16,900 pounds of the direct material at a cost of $14,680. The actual direct labor cost...

  • Question 16 Blomdahl Corporation makes a product with the following standard costs: Inputs Standard Quantity/Hours Standard...

    Question 16 Blomdahl Corporation makes a product with the following standard costs: Inputs Standard Quantity/Hours Standard Price/Rate Direct Materials 5.5 kilos $8.00 per kilo Direct Labor 0.5 Hours $21.00 per hour Variable Overhead 0.5 Hour $5.00 per hour The company reported the following results concerning this product in October 7,500 units 41,100 kilos 2,800 hours Actual Output Purchase of raw materials Actual direct labor-hours Raw materials used in production Cost of raw materials Cost of direct labor Actual variable overhead...

  • Oddo Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price...

    Oddo Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit   Direct materials 2.0 ounces $6.00 per ounce $12.00   Direct labor 0.6 hours $12.00 per hour $7.20   Variable overhead 0.6 hours $4.50 per hour $2.70 The company reported the following results concerning this product in December.   Originally budgeted output 6,400 units   Actual output 6,200 units   Raw materials used in production 9,600 ounces   Actual direct labor-hours 3,920 hours   Purchases of...

  • Question 3 5.52 pts Kartman Corporation makes a product with the following standard costs: 7.00 Per...

    Question 3 5.52 pts Kartman Corporation makes a product with the following standard costs: 7.00 Per Standard Quantity or Standard Cost Hours Standard Price or Rate Per Unit Direct materials 6.5pounds $ $ 45.50 pound Direct labor 0.6hours $ 24.00per hour $ 14.40 Variable overhead 0.6hours $ 4.00per hour $ 2.40 In June the company's budgeted production was 3.400 units but the actual production was 3,500 units. The company used 22,150 pounds of the direct material and 2,290 direct labor-hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT