Question



Additional problems 1. Consider a plan to improve lighting on a dangerous section of highway. The improvements involve a one-time cost in year 1 of $5,000,000, would last 8 years, and are expected to reduce the annual number of accidents by 12. A recent report indicates that the average social cost of a motor vehicle crash is $77,000. a) b) Illustrate the timing of the benefits and costs using a timeline. Calculate the net present value of the project, assuming all benefits and costs accrue at the end of the year and a discount rate of 3%. Would you recommend this project? c) There is some uncertainty surrounding the accident reduction effects. Research suggests that there is a 75% chance that the number of crashes prevented is 12 and a 25% chance that only 9 crashes are prevented. To deal with the uncertainty you undertake (i) expected value analysis, and (ii) worst-case analysis. Briefly explain what you would do in each case. Does this additional analysis support your initial recommendation (from question (i) above) lot for londscane services is given by the following
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Timeline 0 Cash flow 5000000 924000 924000 924000 924000924000 924000 924000 924000 NPV @ 3% 1486195.58 Since NPV is positive, project is favorable c)Expected value Reduction in annual crashes 12 0 4 Cash flow 5000000 924000 924000 924000 924000924000 924000 924000 924000 NPV @ 3% 1486195.58 Reduction in annual crashes9 0 4 6 Cash flow 5000000 693000 693000 693000 693000693000 693000 693000 693000 NPV @ 3% 135353.31 Prob Reduction in crash 12 NPV 1486195.58 75% -135353.31 25% Expected value 1080808.4 Since Expected value is positive, we can go ahead Worst case NPV of 9 crash reduction is negative as shown above Expected value analysis supports our initial decision. Worst case analysis do not

Add a comment
Know the answer?
Add Answer to:
Additional problems 1. Consider a plan to improve lighting on a dangerous section of highway. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. The government is contemplating a project that protects a wilderness area. The project's initial costs...

    4. The government is contemplating a project that protects a wilderness area. The project's initial costs incurred at time t-0 equal S375,000. Starting in year 1, the project is expected to produce annual net benefits of S100,000 into perpetuity (a) Calculate the net present value assuming a discount rate of 8%. Do you recommend going forward with this project? (b)There is some uncertainty about the estimates of initial costs and annual net benefits Research suggests that there is a 75%...

  • Case 5 Twin Falls Community Hospital (Capital Investment Analysis) Twin Falls Community Hospital is a 250-bed,...

    Case 5 Twin Falls Community Hospital (Capital Investment Analysis) Twin Falls Community Hospital is a 250-bed, not-for-profit hospital located in the city of Twin Falls, the largest city in Idaho’s Magic Valley region and the seventh largest in the state. The hospital was founded in 1972 and today is acknowledged to be one of the leading healthcare providers in the area. Twin Falls’ management is currently evaluating a proposed ambulatory (outpatient) surgery center. Over 80 percent of all outpatient surgery...

  • Summary should briefly analyze the central problems and issues of the case and provide some analysis...

    Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • What happened on United flight 3411?What service expectations do customers have of airlines such ...

    What happened on United flight 3411?What service expectations do customers have of airlines such as United and How did these expectations develop over time? Thank You! In early April 2017, United Airlines (United), one of the largest airlines in the world, found itself yet again in the middle of a service disaster this time for forcibly dragging a passenger off an overbooked flight. The incident was to become a wake-up call for United, forcing it to ask itself what to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT