Camile owns Crunch Code, a company that provides quick programming solutions. Clients send Crunch projects via their webpage and Crunch bangs out the needed code as quickly as possible. Camile has five programmers who do all of the coding. On average, a project arrives once every 4.8 hours. Each project is assigned to one programmer and that programmer takes on average 19.2 hours to complete each project.
Camile wants to know what fraction (as a percent) of the time is each of her programmers busy coding?
Avg Utilzation= Arrival rate/(servers*service rate)
Arrival rate= 1/4.8=0.2083 per hr
service rate=1/19.2=0.0521 per hour
hence avg utilizarion of coders= 0.2083/(5*0.0521)=0.799=0.8 or 80%
Camile owns Crunch Code, a company that provides quick programming solutions. Clients send Crunch projects via...
Camille owns Crunch Code, a company that provides quick programming solutions. Clients send projects to Crunch via their web page and a programmer develops the needed code as quickly as possible. Camille has five programmers, who do all of the coding. On average, a project arrives once every 4.8 hours, with a standard deviation of 6.00 hours. Each project is assigned to one programmer and that programmer takes on average 19.2 hours to complete each project with a standard deviation...
UT PA 16-13 (Algo) Camile owns Crunch Code, a company... 10 points Camile owns Crunch Code, a company that provides quick programming solutions. Clients send Crunch projects via their web page and Crunch bangs out the needed code as quickly as possible. Camile has five programmers who do all of the coding. On average, a project arrives once every 4.1 hours, with a standard deviation of 4.2 hours. Each project is assigned to one programmer and that programmer takes on...
Please help & show a clear step by step, with the formulas. PA 16-12 Camile owns Crunch Code, a company.. Camile owns Crunch Code, a company that provides quick programming solutions. Clients send Crunch projects via their webpage and Crunch bangs out the needed code as quickly as possible. Camile has five programmers who do all of the coding. On average, a project arrives once every 4.8 hours, with a standard deviation of 6.00 hours. Each project is assigned to...