Question

Cash-flow Problem Set You are the owner of a large data-services firm and are deciding on the purchase of a new hardware cool

use excel
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1. Profit at Face Value
Cost Saving p.a $2,33,300
Additional O&M expense p.a -$2,120
Net Cash saving p.a $2,31,180
*No. of years 15
Total Cash Saving $34,67,700
-Cost of cooling system -$30,00,000
Profit at Face value $4,67,700
Thus, the system seems profitable at face value.
2 (a) NPV
Net Cash saving p.a $2,31,180
PVAF @ 6% 9.7122
PV of Total Cash Saving $22,45,266
-PV of Cost of cooling system -$30,00,000
NPV -$7,54,734
Year (n) PVF @ 6% (1/1.06^n)
1 0.9434
2 0.8900
3 0.8396
4 0.7921
5 0.7473
6 0.7050
7 0.6651
8 0.6274
9 0.5919
10 0.5584
11 0.5268
12 0.4970
13 0.4688
14 0.4423
15 0.4173
PVAF 9.7122
2 (b)
As we assume a Higher discount rate, NPV will get lower as required rate of return is increasing but cashflow is same.
Eg: Taking discount rate as 7%, NPV will be -$894436
As we assume a Lower discount rate, NPV will get higher as required rate of return is decreasing but cashflow is same.
Eg: Taking discount rate as 5%, NPV will be -$600421
2 (c ) IRR
1.87%
(using IRR Function in Excel.)
2 (d) Yearly cost-saving to break-even
Net Cash saving p.a $3,08,890
PVAF @ 6% 9.7122
PV of Total Cash Saving $30,00,000
-PV of Cost of cooling system -$30,00,000
NPV $0
(Using Goal-seek function in Excel.)
3 (a) Debt-Equity= 70:30
Cost of cooling system $30,00,000
Debt @ 70% $21,00,000
Equity @ 30% $9,00,000
Yearly Payment for 8 years -$3,11,908 =PMT(4%,8,2100000,0,0)
Years Cashflows PVAF @ 6% PV
0 (Equity) -$9,00,000 1 -$9,00,000
1-8 (Loan Repayment) -$3,11,908 6.2098 -$19,36,886
1-15 (Net Cash Saving) $2,31,180 9.7122 $22,45,266
NPV -$5,91,620
Year (n) PVF @ 6% (1/1.06^n) PVAF
1 0.9434
2 0.8900
3 0.8396
4 0.7921
5 0.7473
6 0.7050
7 0.6651
8 0.6274 6.2098
9 0.5919
10 0.5584
11 0.5268
12 0.4970
13 0.4688
14 0.4423
15 0.4173 9.7122
3 (b) Debt-Equity= 60:40
If a larger portion is financed through equity, NPV will REDUCE as Cash Outflow at 0 year will increase, leading to decrease in NPV.
Cost of cooling system $30,00,000
Debt @ 60% $18,00,000
Equity @ 40% $12,00,000
Yearly Payment for 8 years -$2,67,350 =PMT(4%,8,1800000,0,0)
Years Cashflows PVAF @ 6% PV
0 (Equity) -$12,00,000 1 -$12,00,000
1-8 (Loan Repayment) -$2,67,350 6.2098 -$16,60,190
1-15 (Net Cash Saving) $2,31,180 9.7122 $22,45,266
NPV -$6,14,924
Add a comment
Know the answer?
Add Answer to:
use excel Cash-flow Problem Set You are the owner of a large data-services firm and are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • please show step by step and where you got the info please no excel Section: Name:...

    please show step by step and where you got the info please no excel Section: Name: Q5. Project Cost of Capital (25 points) SAIPA Corp. is a publicly traded company that specializes in car manufacturing. The company's debt-to-equity ratio is 1/4 and it plans to maintain the same debt-to-equity ratio indefinitely. SAIPA's cost of debt is 7%, and its equity beta is 1.5. Risk free rate is 5%, market risk premium is also 5 % , and corporate tax rate...

  • Finance NPV Problem

    Your firm is contemplating the purchase of a new $500,000 computer-based order entry system. the system will be depreciated straight-line to zero over its 5-year life. It will be worth $44,000 at the end of that time. You will be able to reduce working capital by $69,000 at the beginning of the project. Working capital will revert back to normal at the end of the project. The tax rate is 23% and the required return on the project is 11%a)...

  • ZYZ Inc. is considering a project with the following cash flows: Year Cash Flow (CF) 0...

    ZYZ Inc. is considering a project with the following cash flows: Year Cash Flow (CF) 0 -$200,000 1 $30.000 2 $40,000 3 $50,000 4 $60,000 5 $70.000 If the discount rate is 5%, what is the NPV of the proposed project? $12.253.47 O $21,009.43 $10,572.99 $11,572.99 Question 22 (2 points) The primary idea behind the net present value rule is that an investment: O is worthwhile if it creates value for the owners. must have total cash flows that equal...

  • Your firm is contemplating the purchase of a new $1,831,500 computer-based order entry system. The system...

    Your firm is contemplating the purchase of a new $1,831,500 computer-based order entry system. The system will be depreciated straight-line to zero over its 5-year life. It will be worth $178,200 at the end of that time. You will be able to reduce working capital by $247,500 (this is a one-time reduction). The tax rate is 22 percent and your required return on the project is 18 percent and your pretax cost savings are $706,900 per year. a. What is...

  • Your firm is contemplating the purchase of a new $2,164,500 computer-based order entry system. The system...

    Your firm is contemplating the purchase of a new $2,164,500 computer-based order entry system. The system will be depreciated straight-line to zero over its 5-year life. It will be worth $210,600 at the end of that time. You will be able to reduce working capital by $292,500 (this is a one-time reduction). The tax rate is 25 percent and your required return on the project is 18 percent and your pretax cost savings are $848,700 per year. a. What is...

  • Use Excel For example.. I want it looks like that 7.21 From the following data, calculate...

    Use Excel For example.. I want it looks like that 7.21 From the following data, calculate the (a) conven tional and (b) modified benefit/cost ratios using a discount rate of 6% per year and a very long (in nite) project life. To the People To the Government Benefits:$300,000 now Costs: $1.5 million novw and $100,000 per year thereafter $40,000 per year and $200,000 three years from now Disbenefits: Savings: $70,000 per year 0 1 2 3 4 cf 150000 -1000...

  • Problem 9-17 Project Evaluation [LO 2] Your firm is contemplating the purchase of a new $395,000...

    Problem 9-17 Project Evaluation [LO 2] Your firm is contemplating the purchase of a new $395,000 computer-based order entry system. The system will be depreciated straight-line to zero over its five-year life. It will be worth $30,000 at the end of that time. You will be able to reduce working capital by $35,000 at the beginning of the project. Working capital will revert back to normal at the end of the project. Assume the tax rate is 21 percent. a.Suppose...

  • Use the following information for the next three problems, Year Cash Flow 1 $12,500 2 $14,000...

    Use the following information for the next three problems, Year Cash Flow 1 $12,500 2 $14,000 3 $10,000 4 $11,000 5 $16,000 5. What is the NPV of above project if the initial investment was $35,000? Assume a cost of capital of 11% 6. Calculate the IRR assuming a cost of capital of 11%. 7. Calculate the MIRR of the project assuming a cost of capital of 11%. ___________________________________________________________________________ 8. Suppose that you are approached with an offer to purchase...

  • Supppose a firm has decided to invest in a project which has the following cash flow...

    Supppose a firm has decided to invest in a project which has the following cash flow structure. The project has annual costs of $10 starting today and growing by 3% each subsequent year. The project also generates revenues of X starting 10 years from today, and these cash flows grow by 2% each year after that. Both revenue and costs are perpetuities. a. Suppose X=$30 and the discount rate is 6%. i. What is the NPV of the project? (Note...

  • Problem 10-17 Project Evaluation [LO2] Your firm is contemplating the purchase of a new $570,000 computer-based...

    Problem 10-17 Project Evaluation [LO2] Your firm is contemplating the purchase of a new $570,000 computer-based order entry system. The system will be depreciated straight-line to zero over its five-year life. It will be worth $86,000 at the end of that time. You will be able to reduce working capital by $111,000 (this is a one-time reduction). The tax rate is 22 percent and the required return on the project is 10 percent. If the pretax cost savings are $150,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT