ANSWER
As per the given question,
Maximum numbers per workstation in 30 days =
Exterior construction = 104,000 x 30 = 3,120,000
Pulp filter = 26,000 x 24/6 x 30 = 3,120,000
Painting = 3,020 x 24/0.5 x 30 = 4,348,800
Packaging = 5,020 x 24 x 30 = 3,614,400
Lowest of the above numbers is 3,120,000 which means Bryan inc. can manufacture 3,120,000 juicers.
THANK YOU FOR THE QUESTION....KINDLY RATE.....IT HELPS ME A LOT
Bryan Inc. produces a specialty top-quality juice machine. The product, the JM50, requires four processes to...
Bryan Inc. produces a specialty top-quality juice machine. The product, the JM50, requires four processes to be completed. Specifically, these processes are exterior construction, pulp filter insertion, painting, and packaging. Each process is performed at separate workstations with different completion rates: Exterior construction can manufacture 112,000 juicer exteriors per day. Pulp filter insertion can install 28,000 filters every 6 hours. Painting can decorate 3,060 juicers every half hour. Packaging can package 5,060 juicers per hour. The plant operates 24/7, 24...
Bryan Inc. produces a specialty top-quality juice machine. The product, the JM50, requires four processes to be completed. Specifically, these processes are exterior construction, pulp filter insertion, painting, and packaging. Each process is performed at separate workstations with different completion rates: Exterior construction can manufacture 100,000 juicer exteriors per day. Pulp filter insertion can install 25,000 filters every 6 hours. Painting can decorate 3,000 juicers every half hour. Packaging can package 5,000 juicers per hour. The plant operates 24/7, 24...
Bryan Inc. produces a specialty top-quality juice machine. The product, the JM50, requires four proce packaging. Each process is performed at separate workstations with different completion rates: Exterior construction can manufacture 100,560 juicer exteriors per day Pulp filter insertion can install 25,140 filters every 6 hours. Painting can decorate 3.140 juicers every half hour. Packaging can package 5,140 juicers per hour. The plant operates 2417, 24 hours a day every day of the week. Which function(s) isfare the bottleneck(s)? (Assume...
Bryan Inc. produces a specialty top-quality juice machine. The product, the JM50, requires four proce packaging. Each process is performed at separate workstations with different completion rates: Exterior construction can manufacture 100,560 juicer exteriors per day Pulp filter insertion can install 25,140 filters every 6 hours. Painting can decorate 3.140 juicers every half hour. Packaging can package 5,140 juicers per hour. The plant operates 2417, 24 hours a day every day of the week. Which function(s) isfare the bottleneck(s)? (Assume...
Bryan Inc. produces a specialty top quality juice machine. The product, the JM50, requires four processes to be completed. Specifically, these processes packaging. Each process is performed at separate workstations with different completion rates: Exterior construction can manufacture 100,560 juicer exteriors per day Pulp filter insertion can install 25,140 filters every 6 hours. Painting can decorate 3,140 juicers every half hour. Packaging can package 5,140 juicers per hour. The plant operates 24/7, 24 hours a day every day of the...