Question

The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has...

The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions:

Project A Project B
Probability Cash Flows Probability Cash Flows
0.2 $6,250 0.2 $0  
0.6 $6,500 0.6 $6,500  
0.2 $6,750 0.2 $19,000  

BPC has decided to evaluate the riskier project at 13% and the less-risky project at 9%. The data has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below.

Open spreadsheet

  1. What is each project's expected annual cash flow? Round your answers to two decimal places.

    Project A: $  

    Project B: $  

    Project B's standard deviation (σB) is $6,185.47 and its coefficient of variation (CVB) is 0.80. What are the values of (σA) and (CVA)? Round your answers to two decimal places.

    σA = $  

    CVA =

  2. Based on the risk-adjusted NPVs, which project should BPC choose?

    _________Project AProject B

  3. If you knew that Project B's cash flows were negatively correlated with the firm's other cash flow, but Project A's cash flows were positively correlated, how might this affect the decision?

    _________This would make Project B more appealing.This would make Project B less appealing.

    If Project B's cash flows were negatively correlated with gross domestic product (GDP), while A's cash flows were positively correlated, would that influence your risk assessment?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a). Expected annual cash flow = sum of {probability*annual cash flow}

Expected annual cash flow for Project A = (0.2*6,250) + (0.6*6,500) + (0.2*6,750) = 6,500.00

Expected annual cash flow for Project B = (0.2*0) + (0.6*6,500) + (0.2*19,000) = 7,700.00

b). Standard deviation = {sum of [probability*(Cash flow - expected annual cash flow)^2]}^0.5

Coefficient of variation = standard deviation/expected annual cash flow

Project A: standard deviation = 158.11; CV = 0.02

Cash flow (CF) Probability (P) (CF-Expected CF)^2*P CF P 6250 0.20 1250 12500 0.60 6500 3900 0 6750 0.20 1350 12500 Total 650

c). NPV = sum of present values of all future cash flows - initial investment

Project A NPV = 9.953.42

Using NPV function with cash flows & 9% discount| NPV P Formula rate NPV Prob Probability (P) Time T 0 1 NPV 0.20 -6500 6250

Project B NPV = 11,680.88

Using NPV function with cash flows & 13% Formula discount rate NPV Prob -1300.00 Probability (P) 0.20 Time T 0 1 2 NPV -6500

Based on risk-adjusted NPVs, Project B should be chosen as it has higher NPV.

d). If project B's cash flows are negatively correlated with the firm's other cash flow, then it will make project B more appealing as it would mean that the project has positive cash flows when the firm's other cash flows are negative.

Similarly, if project B's cash flows are negatively correlated with the GDP, it would make it more appealing.

Add a comment
Know the answer?
Add Answer to:
The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $7,000 and has...

    The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $7,000 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,250 0.2 $0   0.6 $7,000 0.6 $7,000   0.2 $7,750 0.2 $19,000   BPC has decided to evaluate the riskier project at 11% and the less-risky project at 10%. What...

  • The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has...

    The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,000 0.2 $0   0.6 $6,500 0.6 $6,500   0.2 $7,000 0.2 $18,000   BPC has decided to evaluate the riskier project at 13% and the less-risky project at 8%. The...

  • The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $7,000 and has...

    The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $7,000 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,250 0.2 $0   0.6 $7,000 0.6 $7,000   0.2 $7,750 0.2 $19,000   BPC has decided to evaluate the riskier project at 13% and the less-risky project at 10%. The...

  • The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial...

    The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial outflow of $6,500 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,000 0.2 $ 0   0.6   6,500 0.6 6,500   0.2   7,000 0.2 17,000   BPC has decided to evaluate the riskier project at 13% and...

  • Excel Online Structured Activity: Project risk analysis The Butler-Perkins Company (BPC) must decide between two mutually...

    Excel Online Structured Activity: Project risk analysis The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,750 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,000 0.2 $0   0.6 $6,750 0.6 $6,750   0.2 $7,500 0.2 $18,000   BPC has decided to evaluate the riskier project at 12%...

  • The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has...

    The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $5,750 0.2 $0 0.6 $6,500 0.6 $6,500 0.2 $7,250 0.2 $19,000 BPC has decided to evaluate the riskier project at 11% and the less-risky project at 9%. The...

  • The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial...

    The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each project has an initial outflow of $6,500 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Cash Flows Probability Cash Flows Probability $5,750 $ 0.2 0.2 0 6,500 0.6 0.6 6,500 19,000 0.2 7,250 0.2 BPC has decided to evaluate the riskier project at 13% and...

  • The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $7,000 and has...

    The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $7,000 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,250 0.2 $0 0.6 $7,000 0.6 $7,000 02 $7,750 0.2 $19,000 BPC has decided to evaluate the riskier project at 13% and the less-risky project at 10%. a....

  • The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has...

    The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $6,000 0.2 $0 0.6 $6,500 0.6 $6,500 0.2 $7,000 0.2 $18,000 BPC has decided to evaluate the riskier project at 11% and the less-risky project at 9%. The...

  • CVA = The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,750...

    CVA = The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,750 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions Project A Probability Cash Flows Probability Cash Flows Project EB 0.2 0.6 0.2 $6,000 $6,750 $7,500 0.2 0.6 0.2 $0 $6,750 $18,000 BPC has decided to evaluate the riskier project at 12% and the less-risky project at...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT