Predetermined overhead rate = $180,000 / 30,000 = $6 per direct labor hour

a. Work in process inventory, April 30 :

Direct material $2,600
Direct labor (150*$12) 1,800
Overhead applied (150*$6) 900
Work in process inventory, April 30 $5,300

b. Direct material purchased during April = Accounts payable, April 30 + Cash payments - Accounts payable, April 1

Direct material purchased during April = $8,000+40,000-6,000 = $42,000

c. Overhead applied to work in process = 2,600*$6 = $15,600

d. Cost of goods sold = Finished goods inventory, April 1 + Cost of goods manufactured - Finished goods inventory, April 30

Cost of goods sold = $11,000+89,000-16,000 = $84,000

e. Over or underapplied overhead for April = Actual overhead - Overhead applied

Overapplied overhead = $14,800 - 15,600 = $800

f. Direct material usage during april :

Total manufacturing cost = Work in process, April 30 + Cost of goods manufactured - Work in process, April 1

Total manufacturing cost = $5,300+89,000-4,500 = $89,800

Direct material usage = Total manufacturing cost - Direct labor cost - Overhead applied

Direct material usage = $89,800 - 31,200 (2,600*$12) - 15,600 = $43,000

g. Direct material inventory, April 30 = Direct material inventory, April 1 + Direct material purchases - Direct material usage

Direct material inventory, April 30 = $12,000+42,000-43,000 = $11,000

Add a comment
Know the answer?
Add Answer to:
44. Completing missing data (Appendix 2.2). After a dispute concerning wages, John Lyon destroyed all information...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A new computer virus (AcctBGone) destroyed most of the company records at BackupsRntUs. The computer experts...

    A new computer virus (AcctBGone) destroyed most of the company records at BackupsRntUs. The computer experts at the company could recover only a few fragments of the company's factory ledger for March as follows. Direct Materials Inventory BB (3/1) 90,600 | Finished Goods Inventory EB (3/31) 65,100 | Manufacturing Overhead Control Work-In-Process Inventory BB (3/1) 26,49€ Cost of Goods Sold Accounts Payable 53,200 EB (3/31) Further investigation and reconstruction from other sources yielded the following additional information: • The controller...

  • The following transactions occurred in April at Steve’s Cabinets, a custom cabinet firm: Purchased $21,500 of...

    The following transactions occurred in April at Steve’s Cabinets, a custom cabinet firm: Purchased $21,500 of materials on account. Issued $1,350 of supplies from the materials inventory. Purchased $12,300 of materials on account. Paid for the materials purchased in transaction (1) using cash. Issued $14,700 in direct materials to the production department. Incurred direct labor costs of $25,500, which were credited to Wages Payable. Paid $22,300 cash for utilities, power, equipment maintenance, and other miscellaneous items for the manufacturing plant....

  • A tornado struck the only manufacturing plant of Toledo Farm Implements (TFI) on June 1. All...

    A tornado struck the only manufacturing plant of Toledo Farm Implements (TFI) on June 1. All work-in-process inventory was destroyed, but a few records were salvaged from the wreckage and from the company's headquarters. If acceptable documentation is provided, the loss will be covered by insurance. The insurable value of work-in-process inventory consists of direct materials, direct labor, and applied overhead. The following information about the plant appears on the April financial statements at the company's downtown headquarters: Materials inventory,...

  • he charges to Work in Process—Assembly Department for a period, together with information concerning production, are...

    he charges to Work in Process—Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in process at the beginning of production. Work in Process—Assembly Department Bal., 9,000 units, 40% completed 72,360 To Finished Goods, 41,500 units ? Direct materials, 40,000 units @ $6.80 272,000 Direct labor 80,000 Factory overhead 40,450 Bal., ? units, 30% completed ? Cost per equivalent units of $6.80 for Direct Materials and $3.00 for Conversion Costs. a....

  • Required information [The following information applies to the questions displayed below) Marcelino Co.'s March 31 inventory...

    Required information [The following information applies to the questions displayed below) Marcelino Co.'s March 31 inventory of raw materials is $89,000. Raw materials purchases in April are $550,000, and factory payroll cost in April is $382,000. Overhead costs incurred in April are: indirect materials, $56,000: indirect labor $28,000; factory rent, $39.000; factory utilities, $20,000; and factory equipment depreciation. $59.000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $655,000 cash in April. Costs of...

  • Please show the explanations of how you've obtained the answers. Required information [The following information applies...

    Please show the explanations of how you've obtained the answers. Required information [The following information applies to the questions displayed below.] Marcelino Co.'s March 31 inventory of raw materials is $83,000. Raw materials purchases in April are $580,000, and factory payroll cost in April is $385,000. Overhead costs incurred in April are: indirect materials, $57,000; indirect labor, $26,000; factory rent, $40,000; factory utilities, $20,000; and factory equipment depreciation, $58,000. The predetermined overhead rate is 50% of direct labor cost. Job...

  • An expert commented need time, not sure what that means. This is all the info of...

    An expert commented need time, not sure what that means. This is all the info of the problem. Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: a. Materials purchased on account, $2,330. b. Materials requisitioned and factory labor used: Job No. Materials Factory Labor $2,300 $2,230 2,720 3,110 1,810 1,520 101 102 103 104 105...

  • The debts to Work in Processembly Deant for April, together with data concerning production are as...

    The debts to Work in Processembly Deant for April, together with data concerning production are as follows: $ 7,500 April 1. work in process Materials cost, 3.000 units Conversion costs, 3.000 units, 8096 completed Materials added during April 10,000 units Conversion costs during April Goods finished during April, 11.500 units April 30 work in process, 1.500 units, 60% completed 6.00 29,000 35,000 All direct materials are placed in process at the beginning of the process and the average cost method...

  • i completed the part a and all entries were correct i just now need part b...

    i completed the part a and all entries were correct i just now need part b which is puting the ending balances on the t accounts. please make answers readable and please explain. thank you please show work and make answers visble Check my work The following transactions occurred in April at Steve's Cabinets, a custom cabinet firm. 1. Purchased $25,500 of materials on account 2. Issued $1,750 of supplies from the materials inventory 3. Purchased $13,100 of materials on...

  • Please show the computation to obtain the answers. 12. Required information [The following information applies to...

    Please show the computation to obtain the answers. 12. Required information [The following information applies to the questions displayed below.) Part 1 of 2 0.58 points Sierra Company manufactures soccer balls in two sequential processes: Cutting and Stitching. All direct materials enter production at the beginning of the Cutting process. The following information is available regarding its May inventories: Beginning Ending Inventory Inventory $ 76,000 $ 91,750 183,500 130,500 Raw materials inventory Work in process inventory- Cutting Work in process...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT