Question

Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing p
Units completed Engineering hours Setups Machine hours Inspection hours Model C 300,000 1,000 80 20,000 1,500 Model D 200,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Correct answer is:

$2,640,000

Explanation:

Let us first calculate activity rates:

Activity Engineering Setups Machining Inspection Expected Cost Activity Driver (EC) Activity Driver Quantity (Q) $1,000,000 E

Overhead assigned to model C = 1000 * $200 + 80 * $4,500 + 20000 * $80 + 1500 * $320

= $2,640,000

Option B is correct and other options A, C and D are incorrect.

Add a comment
Know the answer?
Add Answer to:
Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 8.Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing...

    8.Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs...

  • Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers:...

    Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers: the deluxe and the regular. At the beginning of the year, the following data were prepared for this plant: Deluxe Regular Quantity 100,000 800,000 Selling price $900 $750 Unit prime cost $529 $483 In addition, the following information was provided so that overhead costs could be assigned to each product: Activity Name Activity Driver Deluxe Regular Activity Cost Setups Number of setups 300 200...

  • COVID 19 Co. produces two different products (Product Yand Product B) using two different activities Machining,...

    COVID 19 Co. produces two different products (Product Yand Product B) using two different activities Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The activity rate for Machining is $125 per machine hour, and the activity rate for Inspection is $500 per batch. The activity drivers are used as follows: Product Y Product B Total Machine hours 1,000 3.000 4,000 Number of batches 45 15 60 What is...

  • Adity a nd Activity and Product Casting Hammer Company produces a variety of ectronicament. One of...

    Adity a nd Activity and Product Casting Hammer Company produces a variety of ectronicament. One of its parts product the end there the beginning the year, the wing data were prepared for this Deluxe Regular Quantity 100.000 500.000 Selling price Unit grime cost 1900 $750 $529 r mation was provided In addition, the fo that had to b e d tech product: Activity Name Activity the De Regular Activity Cost Setups Number of setups $1,350,000 Machine Hours Machining 500.000 100,000...

  • Duration-Based Costing Gee Manufacturing produces two models of camshafts used in the production of automobile engines:...

    Duration-Based Costing Gee Manufacturing produces two models of camshafts used in the production of automobile engines: Regular and High Performance. Gee currently uses an ABC system to assign costs to the two products. For the coming year, the company has the following overhead activities, costs, and activity drivers: Activity Expected Cost Activity Driver Activity Capacity Setups $214,612            Setup hours 10,000             Machining $420,000            Machine hours 20,000             Moving $112,500            Move hours 5,000             Total OH $747,112            At practical capacity,...

  • Duration-Based Costing Gee Manufacturing produces two models of camshafts used in the production of automobile engines:...

    Duration-Based Costing Gee Manufacturing produces two models of camshafts used in the production of automobile engines: Regular and High Performance. Gee currently uses an ABC system to assign costs to the two products. For the coming year, the company has the following overhead activities, costs, and activity drivers: Activity Expected Cost Activity Driver Activity Capacity Setups Machining Moving Total OH $214,612 $420,000 $112,500 $747,112 Setup hours Machine hours Move hours 10,000 20,000 5,000 At practical capacity, the expected activity demands...

  • Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for...

    Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Maintenance. ... Materials handling Machine setups Inspections .. $ 20,000 30,000 70,000 $10,000 15,000 5,000 25,000 $55,000 Cost Driver Machine hours Material moves Machine setups Inspection hours $120,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours .. Materials moves.. Machine setups Inspection hours. 10,000 3,000 700 5,000...

  • Activity Rates and Activity-Based Product Costing Hammer Company produces a variety of electronic equipment. One of...

    Activity Rates and Activity-Based Product Costing Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers: the deluxe and the regular. At the beginning of the year, the following data were prepared for this plant: Deluxe Regular Quantity 100,000 800,000 Selling price $900 $750 Unit prime cost $529 $483 In addition, the following information was provided so that overhead costs could be assigned to each product: Activity Name Activity Driver Deluxe Regular Activity Cost...

  • Question 33 Vid-saver, Inc. has five activity cost pools and two products (a budget tape rewinder...

    Question 33 Vid-saver, Inc. has five activity cost pools and two products (a budget tape rewinder and a deluxe tape rewinder). Information is presented below Cost Drivers by Product Budget Deluxe Activity Cost Pool Ordering and Receiving Machine Setup Machining Assembly inspection Cost Driver Orders Setups Machine hours Parts Inspections Est. Overhead $ 110,000 297.000 1,000,000 1,200,000 300,000 500 150.000 1.200,000 550 100.000 800.000 450 Instructions Compute the overhead cost per unit for each product Production is 700,000 units of...

  • Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers:...

    Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers: the deluxe and the regular. At the beginning of the year, the following data were prepared for this plant: Deluxe Regular Quantity 100,000 $900 800,000 $750 Selling price Unit prime cost $529 $483 In addition, the following information was provided so that overhead costs could be assigned to each product: Activity Name Activity Driver Deluxe Regular Setups Number of setups 300 Machining Machine hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT