Question

Wilmington Company has two manufacturing departments - Assembly and Fabrication It considers all of its manufacturing overhea
Job Bravo Direct labor-hours Machine-hours Assembly Fabrication Total 29 50 Required: 1. If Wilmington used a plantwide prede
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Assembly department predetermined overhead rate = Estimated manufacturing overhead cost for assembly department / Estimated direct labor hours in assembly department = 6720000 / 140000 48
Fabrication department predetermined overhead rate = Estimated manufacturing overhead cost for fabrication department / Estimated machine hours in fabrication department = 7280000 / 280000 26
Manufacturing overhead applied from Assembly to Job Bravo = Assembly department predetermined overhead rate * Direct labor hours used by Job Bravo in Assembly department = 48 * 29 1392
Manufacturing overhead applied from Fabrication to Job Bravo = Fabrication department predetermined overhead rate * Machine hours used by Job Bravo in Fabrication department = 26 * 24 624
   Total departmental manufacturing overhead applied to Job Bravo 2016
Add a comment
Know the answer?
Add Answer to:
Wilmington Company has two manufacturing departments - Assembly and Fabrication It considers all of its manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. $ Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 600,000 50,000 20,000 Fabrication $ 800,000 30,000 100,000 Total 1,400,000 80,000 120,000 Assembly Fabrication Total...

  • Wilmington Company has two manufacturing departments --Assembly and Fabrication. It considers all of its manufacturing overhead...

    Wilmington Company has two manufacturing departments --Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 3,960,000 110,eee 44,000 Fabrication Total $4,400,eee 58,360, eee 66,eee 176, eee 220, eee 264, Bee...

  • Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $3,570,000 105,000 42,000 Fabrication $3,990,000 63.000 Total $ 7,560,000 168.000 252,000 Job Bravo Direct labor-hours Machine-hours chours...

  • Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 2,210,000 85,000 34,000 Fabrication $ 2,550,000 51,000 170,000 Total $4,760,000 136,000 204,000 Job Bravo Direct labor-hours...

  • Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year-Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $5,250,000 125.000 50,000 Fabrication $5,750,000 75.000 250.000 Total $11,000,000 200,000 300.000 Assembly Fabrication Total Job Bravo Direct...

  • Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 1,920,000 80,000 32,000 Fabrication $2,240,000 48,000 160,000 Total $ 4,160,000 128,000 192,000 Assembly Fabrication Job Bravo...

  • Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year-Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 770,000 55,000 22,000 Fabrication $ 990,000 33,000 110,000 Total $ 1,760,000 88,000 132,000 Job Bravo Direct...

  • Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year-Job Bravo. Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 3,570,000 105,000 42,000 Fabrication $ 3,990,000 63,000 210.000 Total $ 7,560,000 168,000 252.000 Assembly Fabrication Total...

  • Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Assembly Fabrication Total Manufacturing overhead costs $ 1,650,000 $ 1,950,000 $ 3,600,000 Direct labor-hours 75,000 45,000 120,000 Machine-hours 30,000 150,000 180,000 Job Bravo Assembly...

  • Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs...

    Wilmington Company has two manufacturing departments-Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year-Job Bravo $ Estimated Data Manufacturing overhead costs Direct labor-hours Machine-hours Assembly $ 600,000 50,000 20.000 Fabrication $ 800,000 30,000 100.000 Total 1,400,000 80,000 120.000 Assembly Fabrication Total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT