Frederick Company uses ABC to account for its chrome wheel manufacturing process. Company managers have identified four manufacturing activities that incur manufacturing overhead costs: materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for the upcoming year and their allocation bases are as follows EEB (Click the icon to view the budgeted costs and activity bases.) Frederick Company expects to produce 1,000 chrome wheels during the year. The wheels are expected to use 2,750 parts, require 15 setups, and consume 1,700 hours of finishing time Job 420 used 150 parts, required 3 setups, and consumed 120 finishing hours Job 510 used 425 parts, required 4 setups, and consumed 310 finishing hours Read the requirements. Requirement 1. Compute the cost allocation rate for each activity. First identify the formula, then compute the rate for each activity Activity cost allocation rate Data Table Total Budgeted Manufacturing Overhead Cost Activity Materials handling Machine setup Insertion of parts Finishing Total Allocation Base $ 11,000 Number of parts 3,600 44,000 76,500 $ 135,100 Number of setups Number of parts Choose from any drop-down list and then click Check Answer 19,000ing direct labor hours parts remaining Clear All

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Activity cost allocation rate = Budgeted manufacturing overhead costs for activity / Quantity of allocation base

Computation of activity rate
Activity Estimated Overhead Cost Activity Base Usage of Activity Base Activity Rate
Materials handling $11,000.00 Nos of parts 2750 $4.00
Machine setup $3,600.00 Nos of setups 15 $240.00
Insertion of parts $44,000.00 Nos of parts 2750 $16.00
Finishing $76,500.00 Finishing direct labor hours 1700 $45.00
Total $135,100.00
Add a comment
Know the answer?
Add Answer to:
Frederick Company uses ABC to account for its chrome wheel manufacturing process. Company managers have identified...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Frederick Companyes A lo account for its chrome wheel malecturing process Company managers have identified for...

    Frederick Companyes A lo account for its chrome wheel malecturing process Company managers have identified for manufacturing activities that incur manufacturing overhead costs materials handing machine setup. Intion of parts and finding the budgeted activity costs for the upcoming year and the allocation bases are as follows Cick the icon to view the budgeted costs and activity bases) Frederick Company expects to produce 1,000 chrome wheels during the year. The wheels we expected to use 3.300 parts require 20 setups...

  • Central Pain uses ABC to account for its chrome wheel manufacturing process. Company managers have identified f...

    Central Pain uses ABC to account for its chrome wheel manufacturing process. Company managers have identified four manufacturing activities that incur manufacturing overhead costs: materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for the upcoming year and their allocation bases are as follows: m (Click the icon to view the budgeted costs and activity bases.) Central Plain expects to produce 1000 chrome wheels during the year. The wheels are expected to use 3,000 parts, require...

  • Franklin Company uses ABC to account for its chrome wheel manufacturing process. Company managers have identified...

    Franklin Company uses ABC to account for its chrome wheel manufacturing process. Company managers have identified four manufacturing activities that incur manufacturing overhead costs: materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for the upcoming year and their allocation bases are as follows: E: (Click the icon to view the budgeted costs and activity bases.) Franklin Company expects to produce 1,000 chrome wheels during the year. The wheels are expected to use 2,600 parts, require...

  • Question Help Fredenck Company usos ABC to account for its chrome wheel manufacturing rous Com m...

    Question Help Fredenck Company usos ABC to account for its chrome wheel manufacturing rous Com m unaners have identified four manufacturing activities that incur manufacturing overhead costs: materials handling, machine setup insertion of parts and finishing the budgeted activity costs for the upcoming year and the allocation bases are as follows: (Click the icon to view the budgeted costs and activity bases) Frederick Company expects to produce 1,000 chrome wheels during the year. The wheels are expected to use 2,750...

  • E4-20A (similar to) Question Help Farrington Company uses ABC to account for its chrome wheel manufacturing...

    E4-20A (similar to) Question Help Farrington Company uses ABC to account for its chrome wheel manufacturing process. Company managers have identified four manufacturing activities that incur manufacturing overhead costs: materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for the upcoming year and their allocation bases are as follows: E (Click the icon to view the budgeted costs and activity bases.) Farrington Company expects to produce 1,000 chrome wheels during the year. The wheels are expected...

  • Fletcher​, Inc. uses​ activity-based costing to account for its chrome bumper manufacturing process. Company managers have...

    Fletcher​, Inc. uses​ activity-based costing to account for its chrome bumper manufacturing process. Company managers have identified four manufacturing​ activities: materials​ handling, machine​ setup, insertion of​ parts, and finishing. The budgeted activity costs for 2018 and their allocation bases are as​follows: Activity Total Budgeted Cost Allocation Base Materials handling $3,000 Number of parts Machine setup 3,000 Number of setups Insertion of parts 52,000 Number of parts Finishing 72,000 Finishing direct labor hours Total $130,000 Fletcher expects to produce 500 chrome...

  • E4-2UA Similar to) Question Help insertion of parts, and West Horizons ABC to account for chrome...

    E4-2UA Similar to) Question Help insertion of parts, and West Horizons ABC to account for chrome whol manufacturing process Company managers have identified four manufacturing activities that incur manufacturing overhead costs: materials handing machine se finishing. The budgeted activity costs for the upcoming year and their allocation bases are as follows: Click the icon to view the budgeted costs and activity bases.) 3.100 parts require 25 setups, and consume 2.400 hours of finishing time West Hormon expects to pro 1,000...

  • Total Budgeted Manufacturing Overhead Cost Allocation Base Activity Materials handling $ Number of parts Machine setup...

    Total Budgeted Manufacturing Overhead Cost Allocation Base Activity Materials handling $ Number of parts Machine setup 13,200 5,200 49,500 86,100 Number of setups Number of parts Insertion of parts Finishing Finishing direct labor hours $ 154,000 Total Print Done * Requirements 1. Compute the cost allocation rate for each activity. 2. Compute the manufacturing overhead cost that should be assigned to Job 420. 3. Compute the manufacturing overhead cost that should be assigned to Job 510 Print Done Farragut Company...

  • i Requirements 1. Compute the cost allocation rate for each activity. 2. Compute the manufacturing overhead...

    i Requirements 1. Compute the cost allocation rate for each activity. 2. Compute the manufacturing overhead cost that should be assigned to Job 420. 3. Compute the manufacturing overhead cost that should be assigned to Job 510. Print Done Data Table Total Budgeted Manufacturing Overhead Cost Allocation Base $ Activity Materials handling .... Machine setup Insertion of parts. 8,700 4,650 49,300 75,600 Number of parts Number of setups Number of parts Finishing Finishing direct labor hours $ 138,250 Total .....

  • Compute the predetermined overhead allocation rate for each activity 2 Points Volty, Inc. uses activity-based costing...

    Compute the predetermined overhead allocation rate for each activity 2 Points Volty, Inc. uses activity-based costing to account for its chrome bumper manufacturing process. Company managers have identified four manufacturing activities: materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for 2018 and their allocation bases are as follows: Activity Materials handling Machine setup Insertion of parts Finishing Total Total Budgeted Cost $15,000 6,000 60,000 90,000 $171,000 Allocation Base Number of parts Number of setups Number...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT