Required information
[The following information applies to the questions
displayed below.]
Antuan Company set the following standard costs for one unit of its
product.
Direct materials (4.0 Ibs. @ $6.00 per Ib.) | $ | 24.00 |
Direct labor (2.0 hrs. @ $13.00 per hr.) | 26.00 | |
Overhead (2.0 hrs. @ $18.50 per hr.) | 37.00 | |
Total standard cost | $ | 87.00 |
The predetermined overhead rate ($18.50 per direct labor hour) is
based on an expected volume of 75% of the factory’s capacity of
20,000 units per month. Following are the company’s budgeted
overhead costs per month at the 75% capacity level.
Overhead Budget (75% Capacity) | |||||
Variable overhead costs | |||||
Indirect materials | $ | 15,000 | |||
Indirect labor | 75,000 | ||||
Power |
15,000 |
||||
Repairs and maintenance | 30,000 | ||||
Total variable overhead costs | $ | 135,000 | |||
Fixed overhead costs | |||||
Depreciation—Building | 24,000 | ||||
Depreciation—Machinery | 72,000 | ||||
Taxes and insurance | 17,000 | ||||
Supervision | 307,000 | ||||
Total fixed overhead costs | 420,000 | ||||
Total overhead costs | $ | 555,000 | |||
The company incurred the following actual costs when it operated at
75% of capacity in October.
Direct materials (60,500 Ibs. @ $6.10 per lb.) | $ | 369,050 | |||
Direct labor (19,000 hrs. @ $13.30 per hr.) | 252,700 | ||||
Overhead costs | |||||
Indirect materials | $ | 41,400 | |||
Indirect labor | 176,250 | ||||
Power | 17,250 | ||||
Repairs and maintenance | 34,500 | ||||
Depreciation—Building | 24,000 | ||||
Depreciation—Machinery | 97,200 | ||||
Taxes and insurance | 15,300 | ||||
Supervision | 307,000 | 712,900 | |||
Total costs | $ | 1,334,650 | |||
rev: 03_28_2018_QC_CS-122864
4. Compute the direct labor cost variance,
including its rate and efficiency variances.
AH = Actual Hours
SH = Standard Hours
AR = Actual Rate
SR = Standard Rate
Required information [The following information applies to the questions displayed below.] Antuan Company set the following...
Required information [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (3.0 Ibs. @ $6.00 per Ib.) $ 18.00 Direct labor (2.0 hrs. @ $10.00 per hr.) 20.00 Overhead (2.0 hrs. @ $18.50 per hr.) 37.00 Total standard cost $ 75.00 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units...
Required information [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) Direct labor (1.8 hrs. @ $11.00 per hr.) Overhead (1.8 hrs. @ $18.50 per hr.) Total standard cost $20.00 19.80 33.30 $ 73.10 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per...
Required information [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) Direct labor (1.9 hrs. @ $13.00 per hr.) Overhead (1.9 hrs. @ $18.50 per hr.) Total standard cost $24.00 24.70 35.15 $83.85 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month....
Required information [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (2.0 hrs. @ $13.00 per hr.) 26.00 Overhead (2.0 hrs. @ $18.50 per hr.) 37.00 Total standard cost $ 87.00 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units...
[The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (2.0 hrs. @ $13.00 per hr.) 26.00 Overhead (2.0 hrs. @ $18.50 per hr.) 37.00 Total standard cost $ 87.00 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month....
Required information (The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (3.0 Ibs. @ $5.00 per Ib.) Direct labor (2.0 hrs. @ $10.00 per hr.) Overhead (2.0 hrs. @ $18.50 per hr.) Total standard cost $15.00 20.00 37.00 $72.00 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month....
Required information [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $4.00 per Ib.) $ 16.00 Direct labor (1.9 hrs. @ $11.00 per hr.) 20.90 Overhead (1.9 hrs. @ $18.50 per hr.) 35.15 Total standard cost $ 72.05 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units...
Required information [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) Direct labor (1.9 hrs. @ $13.00 per hr.) Overhead (1.9 hrs. @ $18.50 per hr.) Total standard cost $24.00 24.70 35.15 $83.85 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month....
Required information [The following information applies to the questions displayed below.) Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $4.ee per Ib.) Direct labor (1.8 hrs. @ $12.00 per hr.) Overhead (1.8 hrs. @ $18.50 per hr.) Total standard cost $16.00 21.60 33.38 $79.90 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month....
Required information [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (2.0 hrs. @ $13.00 per hr.) 26.00 Overhead (2.0 hrs. @ $18.50 per hr.) 37.00 Total standard cost $ 87.00 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units...