Question

On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,850,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $4,000,000, 14% bonds $1,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 800,000 March 31 1,400,000 June 30 1,040,000 September 30 800,000 December 31 600,000 Required: Calculate the amount of interest capitalized for 2018 using the specific interest method. (Do not round the intermediate calculations. Round your percentage answers to 1 decimal place (i.e. 0.123 should be entered as 12.3%).)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Dale Expenditure weight Average January 1 $800,000 & 12 $ 800,000 March 31 $1,400,000 & 2 $ 1050,000 June 30 $1040,000 stos $Thank you

Please rate if it is helpful to you

Add a comment
Know the answer?
Add Answer to:
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $1,850,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $4,000,000, 14% bonds $1,000,000, 10% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 800,000 March 31 1,400,000 June 30 1,040,000 September 30 800,000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,500,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 9% bonds $6,eee, eee, 8% long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $1,000,000 1,600,000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,700,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $6,000,000, 14% bonds $4,000,000, 93 long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $ 620,000 1,220,000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,200,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 10% bonds $6,000,000, 8% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 900,000 March 31 1,500,000 June 30 1,160,000 September 30 900,000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,700,000 at 7% on January 1 to help finance the construction, in addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 12t bonds $3,000,000, 78 long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $ 740,000 1,340,000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The build...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,800,000 at 7% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 12% bonds $6,000,000, 7% long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $ 780,000 1,380,000...

  • On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,000,000 at 13% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: points $5.829.oe. 17% bonds $3.880.880.13% long-term note Construction expenditures incurred during 2021 were as follows: $ January 1 March 31 June 30 September 30 December 31 820,000 1,420.000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,500,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $8,000,000, 15% bonds $2,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 660,000 March 31 1,260,000 June 30 872,000 September 30 660,000...

  • On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,350,000 at 9% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $7,000,000, 14% bonds $3,000,000, 9% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 960,000 March 31 1,560,000 June 30 1,232,000 September 30 960,000...

  • On January 1, 2016, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2016, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2017. The company borrowed $1,500,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2016: Construction expenditures incurred during 2016 were as follows: Calculate the amount of interest capitalized for 2016 using the specific interest method.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT