1. Direct labor budget
1st quarter | 2nd quarter | 3rd quarter | 4th quarter | Year | |
Units to be produced | 12,000 | 10,000 | 13,000 | 14,000 | 49,000 |
Direct labor hours per unit | 0.2 | 0.2 | 0.2 | 0.2 | 0.2 |
Direct labor rate per hour | $12 | $12 | $12 | $12 | $12 |
Estimated direct labor cost | $28,800 | $24,000 | $31,200 | $33,600 | $117,600 |
2. Manufacturing overhead budget
1st quarter | 2nd quarter | 3rd quarter | 4th quarter | Year | |
Units to be produced | 12,000 | 10,000 | 13,000 | 14,000 | 49,000 |
Direct labor hours per unit | 0.2 | 0.2 | 0.2 | 0.2 | 0.2 |
Variable manufacturing overhead rate per direct labor hour | $1.75 | $1.75 | $1.75 | $1.75 | $1.75 |
Variable manufacturing overhead | $4,200 | $3,500 | $4,550 | $4,900 | $17,150 |
Fixed manufacturing overhead | $86,000 | $86,000 | $86,000 | $86,000 | $344,000 |
Total manufacturing overhead | $90,200 | $89,500 | $90,550 | $90,900 | $361,150 |
Non cash fixed manufacturing overhead | $23,000 | $23,000 | $23,000 | $23,000 | $92,000 |
Cash disbursements for manufacturing overhead | $67,200 | $66,500 | $67,550 | $67,900 | $269,150 |
1 Normal 1 No Spac... Heading 1 Heading 2 Title Styles Paragraph The Production Department of...
Chapter 8 Application 14 The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year. 4th Quarter 1st Quarter 12,000 2nd Quarter 10, 3rd Quarter 13,000 Units to be produced Each unit requires 0.2 direct labor-hours and direct laborers are paid $12.00 per hour. In addition, the variable manufacturing overhead rate is $175 per direct labor-hour. The fixed manufacturing overhead is $86,000 per quarter. The only noncash element...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: Units to be produced 1st Quarter 2nd Quarter 3rd Quarter 10,500 9,500 11,500 4th Quarter 12,500 Each unit requires 0.30 direct labor-hours and direct laborers are paid $12.50 per hour. In addition, the variable manufacturing overhead rate is $1.80 per direct labor-hour. The fixed manufacturing overhead is $85,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year Units to be produced 10,000 9,000 11,000 12,000 Each unit requires 0.20 direct labor-hours and direct laborers are paid $12.00 per hout In addition, the variable manufacturing overhead rate is $1.50 per direct labor-hour. The fixed manufacturing overhead is $80,000 per quarter. The only noncash element of manufacturing overhead is depreciation, which is $20,000 per quarter. Required...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,500 10,500 12,500 13,500 Each unit requires 0.25 direct labor-hours and direct laborers are paid $14.00 per hour. In addition, the variable manufacturing overhead rate is $1.60 per direct labor-hour. The fixed manufacturing overhead is $95,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 10,100 9,100 11,100 12,100 Each unit requires 0.25 direct labor-hours and direct laborers are paid $13.00 per hour. In addition, the variable manufacturing overhead rate is $1.80 per direct labor-hour. The fixed manufacturing overhead is $81,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 11,400 10,400 12,400 13,400 Each unit requires 0.30 direct labor-hours and direct laborers are paid $12.50 per hour. In addition, the variable manufacturing overhead rate is $1.50 per direct labor-hour. The fixed manufacturing overhead is $94,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 10,800 2nd Quarter 9,800 3rd Quarter 11,800 4th Quarter 12,800 Units to be produced Each unit requires 0.25 direct labor-hours and direct laborers are paid $13.00 per hour. In addition, the variable manufacturing overhead rate is $1.90 per direct labor-hour. The fixed manufacturing overhead is $88,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 10,200 9,200 11,200 12,200 Each unit requires 0.25 direct labor-hours and direct laborers are paid $11.00 per hour. In addition, the variable manufacturing overhead rate is $1.60 per direct labor-hour. The fixed manufacturing overhead is $82,000 per quarter. The only noncash element of manufacturing overhead...
The Production Department of Hruska Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 11,000 2nd Quarter 10,000 3rd Quarter 12,000 4th Quarter 13,000 Units to be produced Each unit requires 0.30 direct labor-hours and direct laborers are paid $12.50 per hour. In addition, the variable manufacturing overhead rate is $2.05 per direct labor-hour. The fixed manufacturing overhead is $90,000 per quarter. The only noncash element of manufacturing overhead...
2. DL and MOH budget: The Production Department of Top of The World Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 10,700 9,700 11,700 12,700 Each unit requires 0.25 direct labor-hours and direct laborers are paid $14.00 per hour. In addition, the variable manufacturing overhead rate is $2.00 per direct labor-hour. The fixed manufacturing overhead is $67,000 per...