Question

Exercise 2.12 C。mputing Predetermined Overhead Rates and Job Costs [LO2-1, L02-2, LO2-3] Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 155,000 $. 651,000 $4.50 Required 1. Compute the plantwide predetermined overhead rate 2. During the year, Job 400 was started and completed. The following information was available with respect to this job Direct materials Direct labor cost Machine-hours used $ 370 $ 280 38 Compute the total manufacturing cost assigned to Job 400 3. If Job 400 includes 50 units, what is the unit product cost for this job? 4. If Moody uses a markup percentage of 130% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute the plantwide predetermined overhead rate. (Round your answer to 2 decimal places.) Predetermined overhead rate per MHRequired 1Required 2Required 3Required 4 If Job 400 includes 50 units, what is the unit product cost for this job? (Round your intermediate calculations and final answer to the nearest whole dollar.) Unit product costRequired 1 Required 2 Required 3Required 4 If Moody uses a markup percentage of 130% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? (Round your intermediate calculations and final answer to the nearest whole dollar.) Selling price per unit

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) predetermined overhead rate = $8.7

Explanation:

The estimated total manufacturing overhead cost is computed as follows:

Total manufacturing overhead = total fixed MOH + Total variable.MOH

= $651000 + ($4.5 × 155000)

= $651000 + $697500

= $1348500

The plantwide predetermined overhead rate is computed as follows:

Predetermined OH rate = estimated total Manufacturing OH ÷ estimated total machine hours

= $1348500/155000

= $8.7

2) total manufacturing cost = $981

Total manufacturing cost assigned to job 400 = direct labour + direct material + manufacturing OH applied

= $370 + $280 + (38 × $8.7)

= $370 + $280 + $330.6

= $981

3) unit product cost = $20

Unit product cost = total manufacturing cost / number of units in the job

= 981/50

= 19.62 ~ $20

4) selling price per unit = $45

Total manufacturing cost $981
Markup (130% of man. cost) $1275
Selling price for job 400 (a) $2256
Number of units in job 400 (b) 50
Selling price per unit $45

I have given complete and detailed solution to your problem, in case of any query you can comment and

PLEASE DO GIVE POSITIVE RATING

Add a comment
Know the answer?
Add Answer to:
Exercise 2.12 C。mputing Predetermined Overhead Rates and Job Costs [LO2-1, L02-2, LO2-3] Moody Corporation uses a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs [LO2-1, LO2-2, LO2-3] Moody Corporation uses a...

    Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs [LO2-1, LO2-2, LO2-3] Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 154,000 656,000 $ 4.70 Required: 1. Compute the plantwide predetermined overhead rate 2. During the year, Job 400 was started and completed. The following...

  • Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs [LO2-1, LO2-2, LO2-3] Moody Corporation uses a...

    Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs [LO2-1, LO2-2, LO2-3] Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 650,000 Variable manufacturing overhead cost per machine-hour $ 4.50 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The...

  • Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs (LO2-1, LO2-2, LO2-3] Moody Corporation uses a...

    Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs (LO2-1, LO2-2, LO2-3] Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 159,000 $ 651.000 $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate 2. During the year, Job 400 was started and completed. The...

  • overhead and job costs EXERCISE 2-12 Computing Predetermined Overhead Rates and Job Costs LO 2-1, LO2-2,...

    overhead and job costs EXERCISE 2-12 Computing Predetermined Overhead Rates and Job Costs LO 2-1, LO2-2, LV2-3 Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production ...... Fixed manufacturing overhead cost....... Variable manufacturing overhead cost per machine-hour........ 100.000 $650,000 $3.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: ots Machine-hours required to support estimated production 152, eee Fixed manufacturing overhead cost $659,800 Variable manufacturing overhead cost per machine-hour $ 4.30 - eBook Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job!...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 155,000 $651,000 4.40 Required 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job Direct materials Direct labor cost...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 151,000 $ 650,000 $ 4.10 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

  • Homework - Chapter 2 6 Saved 6 Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs...

    Homework - Chapter 2 6 Saved 6 Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs [LO2-1, LO2-2, LO2-3] 14.28 points Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Skipped Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 152,000 651,000 $4.50 eBook Required 1. Compute the plantwide predetermined overhead rate 2. During...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 154,000 $ 655,000 $ 5.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT