1) predetermined overhead rate = $8.7
Explanation:
The estimated total manufacturing overhead cost is computed as follows:
Total manufacturing overhead = total fixed MOH + Total variable.MOH
= $651000 + ($4.5 × 155000)
= $651000 + $697500
= $1348500
The plantwide predetermined overhead rate is computed as follows:
Predetermined OH rate = estimated total Manufacturing OH ÷ estimated total machine hours
= $1348500/155000
= $8.7
2) total manufacturing cost = $981
Total manufacturing cost assigned to job 400 = direct labour + direct material + manufacturing OH applied
= $370 + $280 + (38 × $8.7)
= $370 + $280 + $330.6
= $981
3) unit product cost = $20
Unit product cost = total manufacturing cost / number of units in the job
= 981/50
= 19.62 ~ $20
4) selling price per unit = $45
Total manufacturing cost | $981 |
Markup (130% of man. cost) | $1275 |
Selling price for job 400 (a) | $2256 |
Number of units in job 400 (b) | 50 |
Selling price per unit | $45 |
I have given complete and detailed solution to your problem, in case of any query you can comment and
PLEASE DO GIVE POSITIVE RATING
Exercise 2.12 C。mputing Predetermined Overhead Rates and Job Costs [LO2-1, L02-2, LO2-3] Moody Corporation uses a...
Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs [LO2-1, LO2-2, LO2-3] Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 154,000 656,000 $ 4.70 Required: 1. Compute the plantwide predetermined overhead rate 2. During the year, Job 400 was started and completed. The following...
Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs [LO2-1, LO2-2, LO2-3] Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 650,000 Variable manufacturing overhead cost per machine-hour $ 4.50 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The...
Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs (LO2-1, LO2-2, LO2-3] Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 159,000 $ 651.000 $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate 2. During the year, Job 400 was started and completed. The...
overhead and job costs EXERCISE 2-12 Computing Predetermined Overhead Rates and Job Costs LO 2-1, LO2-2, LV2-3 Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production ...... Fixed manufacturing overhead cost....... Variable manufacturing overhead cost per machine-hour........ 100.000 $650,000 $3.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: ots Machine-hours required to support estimated production 152, eee Fixed manufacturing overhead cost $659,800 Variable manufacturing overhead cost per machine-hour $ 4.30 - eBook Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job!...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 155,000 $651,000 4.40 Required 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job Direct materials Direct labor cost...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 151,000 $ 650,000 $ 4.10 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...
Homework - Chapter 2 6 Saved 6 Exercise 2-12 Computing Predetermined Overhead Rates and Job Costs [LO2-1, LO2-2, LO2-3] 14.28 points Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Skipped Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 152,000 651,000 $4.50 eBook Required 1. Compute the plantwide predetermined overhead rate 2. During...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 154,000 $ 655,000 $ 5.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...