Question

Schrager Company has two production departments Cutting and Assembly, July 1 Inventories are Raw Materials $4,400, Work in Pr

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
Account Debit Credit
1 Raw Materials Inventory $   64,600
Accounts Payable $   64,600
2 Factory Labor $   60,200
Wages Payable $   60,200
3 Manufacturing Overhead $   72,800
Cash $   41,600
Accounts Payable $   31,200
4 Work in process - cutting $   17,200
Work in process - assembly $      9,600
Raw Materials Inventory $   26,800
5 Work in process - cutting $   33,100
Work in process - assembly $   27,100
Factory Labor $   60,200
6 Work in process - cutting $   34,400
Work in process - assembly $   35,000
Manufacturing Overhead $   69,400
7 Work in process - assembly $   69,000
Work in process - cutting $   69,000
8 Finished Goods Inventory $ 136,600
Work in process - assembly $ 136,600
9 Cost of Goods Sold $ 151,700
Finished Goods Inventory $ 151,700
Accounts receivable $ 201,100
Cash $ 201,100
Add a comment
Know the answer?
Add Answer to:
Schrager Company has two production departments Cutting and Assembly, July 1 Inventories are Raw Materials $4,400,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Schrager Company has two production departments: Cutting and Assembly. July 1 inventories are Raw Materials $5,100,...

    Schrager Company has two production departments: Cutting and Assembly. July 1 inventories are Raw Materials $5,100, Work in Process—Cutting $3,600, Work in Process—Assembly $11,600, and Finished Goods $32,600. During July, the following transactions occurred. 1. Purchased $62,700 of raw materials on account. 2. Incurred $61,600 of factory labor. (Credit Wages Payable.) 3. Incurred $71,600 of manufacturing overhead; $42,000 was paid and the remainder is unpaid. 4. Requisitioned materials for Cutting $16,600 and Assembly $9,600. 5. Used factory labor for Cutting...

  • Schrager Company has two production departments: Cutting and Assembly. July 1 inventories are Raw Materials $5,200,...

    Schrager Company has two production departments: Cutting and Assembly. July 1 inventories are Raw Materials $5,200, Work in Process-Cutting $3,200, Work in Process-Assembly $10,900, and Finished Goods $32,400. During July, the following transactions occurred. 1. 2. 3. 4. 5. Purchased $62,700 of raw materials on account. Incurred $60,200 of factory labor. (Credit Wages Payable.) Incurred $71,800 of manufacturing overhead; $42,900 was paid and the remainder is unpaid. Requisitioned materials for Cutting $16,500 and Assembly $9,800. Used factory labor for Cutting...

  • Schrager Company has two production departments: Cutting and Assembly July 1 inventories are Raw Materials $4,600,...

    Schrager Company has two production departments: Cutting and Assembly July 1 inventories are Raw Materials $4,600, Wo in Process-Cutting $3,800, Work in Process-Assembly $11,500, and Finished Goods $32,000. During July, the following transactions occurred. 1. Purchased $64,200 of raw materials on account. 2. Incurred $61,000 of factory labor. (Credit Wages Payable.) 3. Incurred $71,000 of manufacturing overhead: $42,300 was paid and the remainder is unpaid. 4. Requisitioned materials for Cutting $16,700 and Assembly $9,600. 5. Used factory labor for Cutting...

  • Exercise 16-4 Schrager Company has two production departments: Cutting and Assembly. July 1 inventories are Raw...

    Exercise 16-4 Schrager Company has two production departments: Cutting and Assembly. July 1 inventories are Raw Materials $4,600, Work in Process—Cutting $3,500, Work in Process—Assembly $11,400, and Finished Goods $32,600. During July, the following transactions occurred. 1. Purchased $63,100 of raw materials on account. 2. Incurred $60,900 of factory labor. (Credit Wages Payable.) 3. Incurred $71,600 of manufacturing overhead; $41,900 was paid and the remainder is unpaid. 4. Requisitioned materials for Cutting $16,700 and Assembly $9,700. 5. Used factory labor...

  • please help with the following. oport Schrager Company has two production departments: Cutting and Assembly. July...

    please help with the following. oport Schrager Company has two production departments: Cutting and Assembly. July 1 inventories are Raw Materials $5.200, Work in Process-Cutting $3.900, Work in Process-Assembly $10,800, and Finished Goods $32,600. During July, the following transactions occurred. 1. Purchased $63.100 of raw materials on account. 2. Incurred $60,200 of factory labor. (Credit Wages Payable) 3. Incurred $72.000 of manufacturing overhead: $42.900 was paid and the remainder isung 4. Requisitioned materials for Cutting $17.200 and Assembly $9.500. 5....

  • Oriole Company has two production departments: Cutting and Assembly, July 1 Inventories are Raw Materials $5,200,...

    Oriole Company has two production departments: Cutting and Assembly, July 1 Inventories are Raw Materials $5,200, Work in Process-Cutting $3,200, Work in Process- Assembly $10,900, and Finished Goods $32,400. During July, the following transactions occurred. 1. Purchased $62,700 of raw materials on account 2. Incprred $60,200 of factory labor. (Credit Wages Payable.) 3. Incurred $71,800 of manufacturing overhead; $42,900 was paid and the remainder is unpaid. 4. Requisitioned materials for Cutting $16,500 and Assembly $9,800 5. Used factory labor for...

  • Exercise 3-4 (Video) Schrager Company has two production departments: Cutting and Assembly. July 1 Inventories are...

    Exercise 3-4 (Video) Schrager Company has two production departments: Cutting and Assembly. July 1 Inventories are Raw Materials $5,100, Work in Process-Cutting $3,200, Work in Process-Assembly $11,200, and Finished Goods $32,000. During July, the following transactions occurred. 1. Purchased 563,700 of raw materials on account. 2. Incurred 560,500 of factory labor. (Credt Wages Payable.) 3. Incurred $71,700 of manufacturing overhead: 541,400 was paid and the remainder is unpaid. 4. Requisitioned materials for Cutting $16,000 and Assembly $9,900. 5. Used factory...

  • Crane Company has two production departments: Cutting and Assembly, July 1 invertories are Raw Materials $4,300....

    Crane Company has two production departments: Cutting and Assembly, July 1 invertories are Raw Materials $4,300. Work in Process-Cutting $3,000, Work in Process-Assembly $10.700, and Finished Goods $32,000. During July, the following transactions occurred. 1. 2. 3 5. 6. 7 Purchased $62,600 of raw materials on account. Incurred $60,100 of factory labor. (Credit Wages Payable.) Incurred $71,000 of manufacturing overhead: $41,000 was paid and the remainder is unpaid. Requisitioned materials for Cutting $15,800 and Assembly $9.000. Used factory labor for...

  • Exercise 16-04 Schrager Company has two production departments Cutting and Assembly. Juy 1 inventories are Raw...

    Exercise 16-04 Schrager Company has two production departments Cutting and Assembly. Juy 1 inventories are Raw Materials 55,100, Work in Process-Outting $3.200, Work in Process Assembly $11,200, and finished Goods $32.800. During ly the following transactions occurred. 1. Purchased $63,700 of raw materials on account. 2. incurred $60,500 of factory labor. (Credit Wages Payable) 3. Incurred $71,700 of manufacturing overhead; 141,400 was paid and the remainder is unpaid. 4. Requisitioned materials for Cutting $16,800 and Assembly $9,900. 5. Used factory...

  • Schwager Company has two production departments Cutting and Assembly, July 1 Inventories are Raw Materials $5,200,...

    Schwager Company has two production departments Cutting and Assembly, July 1 Inventories are Raw Materials $5,200, Work In Process-Cutting $3,700, Work in Process Assembly $10,000, and finished Goods $2.500. During July, the following transactions occurred 1. Purchased $63,700 of raw materials on account 2. incurred 561,900 of factory labor. (Credit Wages Payable) 3. Incurred $71,500 of manufacturing overhead: $41,600 was paid and the remainder is unpaid 4. Requisitioned materials for Cutting 517,800 and Assembly 59,300 5. Used factory labor for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT