Question

Required information [The following information applies to the questions displayed below.) Clarke Corporation manufactures th

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Bottleneck resources are the limited resources available which will not allow production of all the products due to its limited availability, so the product with highest contribution margin per bottle neck resources should be produced first.

we will find contribution margin per machine hours

X1 X2 X3
Sales $168 $268 $536
Variable costs ($84) ($142) ($308)
Contribution margin (Sales-variable cost) $84 $126 $228
Machine hour per unit 1 2.5 4
Contribution margin per hour $84($84/1) $50.4($126/2.5) $57($228/4)
Ranking 1 3 2

we will first produce product X-1 than X3 and than X2

X1 X3 X2
Maximum demand 385,000 71,000 184,000
Machine hour per unit 1 4 2.5
Total machine hour required for X1 385,000
Machine hour left after producing X1 453,000(838,000-385,000)
Total machine hour required for X3 284,000(71,000*4)
Machine hours left after producing X1 & X3 169,000(453,000-284,000)
Machine hours for X2 169,000
Units produced of X2 67,600(169,000 hours/2.5 hours per unit)

So, units to be produced

X1=385,000

X3=71,000

X2=67,600

2)With an increase in 20 machine hours clarke can produce X2. SO maximum that can be paid is contribution margin of X2. Any amount higher than contribution margin of X2 will result into loss.

SO maximum = 20 hours*$50.4 contribution margin per hour of X2

=$1,008

3)if the maximum capacity was 453,000it will be used for producing X1 (385,000 units ) & X 3 (453,000-385,000)/4=17,000 units. As an entire demand of X3 is not fulfilled any additional available hours will be used for production of X3

SO maximum that should be paid = Contribution margin per hour of X3*20hours

=$57*20

=$1,140

4)If the demand of all the units are fulfilled there will be no bottleneck

Total machine hours = (X1 maximum units*machine hours for producing one unit of X1)+(X2 maximum units*machine hours for producing one unit of X2)+(X3 maximum units*machine hours for producing one unit of X3)

(385,000*1)+(184,000*2.5)+(71,000*4)

=1,129,000 hours

Thus, At 1,129,000 machine hours capacity availability there will be no bottleneck

Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.) Clarke Corporation manufactures three products...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT