Bottleneck resources are the limited resources available which will not allow production of all the products due to its limited availability, so the product with highest contribution margin per bottle neck resources should be produced first.
we will find contribution margin per machine hours
X1 | X2 | X3 | ||
Sales | $168 | $268 | $536 | |
Variable costs | ($84) | ($142) | ($308) | |
Contribution margin (Sales-variable cost) | $84 | $126 | $228 | |
Machine hour per unit | 1 | 2.5 | 4 | |
Contribution margin per hour | $84($84/1) | $50.4($126/2.5) | $57($228/4) | |
Ranking | 1 | 3 | 2 |
we will first produce product X-1 than X3 and than X2
X1 | X3 | X2 | |||
Maximum demand | 385,000 | 71,000 | 184,000 | ||
Machine hour per unit | 1 | 4 | 2.5 | ||
Total machine hour required for X1 | 385,000 | ||||
Machine hour left after producing X1 | 453,000(838,000-385,000) | ||||
Total machine hour required for X3 | 284,000(71,000*4) | ||||
Machine hours left after producing X1 & X3 | 169,000(453,000-284,000) | ||||
Machine hours for X2 | 169,000 | ||||
Units produced of X2 | 67,600(169,000 hours/2.5 hours per unit) | ||||
So, units to be produced
X1=385,000
X3=71,000
X2=67,600
2)With an increase in 20 machine hours clarke can produce X2. SO maximum that can be paid is contribution margin of X2. Any amount higher than contribution margin of X2 will result into loss.
SO maximum = 20 hours*$50.4 contribution margin per hour of X2
=$1,008
3)if the maximum capacity was 453,000it will be used for producing X1 (385,000 units ) & X 3 (453,000-385,000)/4=17,000 units. As an entire demand of X3 is not fulfilled any additional available hours will be used for production of X3
SO maximum that should be paid = Contribution margin per hour of X3*20hours
=$57*20
=$1,140
4)If the demand of all the units are fulfilled there will be no bottleneck
Total machine hours = (X1 maximum units*machine hours for producing one unit of X1)+(X2 maximum units*machine hours for producing one unit of X2)+(X3 maximum units*machine hours for producing one unit of X3)
(385,000*1)+(184,000*2.5)+(71,000*4)
=1,129,000 hours
Thus, At 1,129,000 machine hours capacity availability there will be no bottleneck
Required information [The following information applies to the questions displayed below.) Clarke Corporation manufactures three products...
Required information [The following information applies to the questions displayed below.] Clarke Corporation manufactures three products (X-1, X-2, and X-3) utilizing, in one of the processes, a single machine for all products. Data on the individual products follow. X-1 X-2 X-3 Price per unit $ 128 $ 228 $ 456 Variable cost per unit $ 64 $ 132 $ 268 Machine hours per unit 1.0 2.5 4.0 Maximum units demand per period 335,000 164,000 41,000 The single machine used for...
Required information The following information applies to the questions displayed below.) Clarke Corporation manufactures three products (X-1, X-2, and X-3) utilizing, in one of the processes, a single machine for all products. Data on the individual products follow. 164 $ Price per unit Variable cost per unit Machine hours per unit Maximum units demand per period 1.0 380,000 264 141 2.5 182,000 528 304 4.0 68,000 The single machine used for all three products has a maximum capacity of 818,000...
Required Information The following information applies to the questions displayed below) Clarke Corporation manufactures three products (X-1. X-2 and X-3) utilizing in one of the processes, o single machine for all products. Data on the individual products follow. $ Price per unit Variable cost per unit Machine hours per unit Maximum units demand per period 4.0 340,000 166,888 44,660 The single machine used for all three products has a maximum capacity of 658,000 hours per period Required: a. How many...
Required information [The following information applies to the questions displayed below.] Clarke Corporation manufactures three products (X-1, X-2, and X-3) utilizing, in one of the processes, a single machine for all products. Data on the individual products follow. X-1 $ 112 $ 56 1.0 315,000 Price per unit Variable cost per unit Machine hours per unit Maximum units demand per period X-2 $ 212 $ 128 2.5 156,000 $ $ X-3 424 252 4.0 29,000 The single machine used for...
The following information applies to the questions displayed below.] Clarke Corporation manufactures three products (X-1, X-2, and X-3) utilizing, in one of the processes, a single machine for all products. Data on the individual products follow. X-1 X-2 X-3 Price per unit $ 160 $ 260 $ 520 Variable cost per unit $ 80 $ 140 $ 300 Machine hours per unit 1.0 2.5 4.0 Maximum units demand per period 375,000 180,000 65,000 The single machine used for all three...
Clarke Corporation manufactures three products (X-1, X-2, and X-3) utilizing, in one of the processes, a single machine for all products. Data on the individual products follow. X-1 X-2 X-3 Price per unit $ 148 $ 248 $ 496 Variable cost per unit $ 74 $ 137 $ 288 Machine hours per unit 1.0 2.5 4.0 Maximum units demand per period 360,000 174,000 56,000 The single machine used for all three products has a maximum capacity of 738,000 hours per...
Clarke Corporation manufactures three products (X-1, X-2, and X-3) utilizing, in one of the processes, a single machine for all products. Data on the individual products follow. X-1 X-2 X-3 Price per unit $ 160 $ 260 $ 520 Variable cost per unit $ 80 $ 140 $ 300 Machine hours per unit 1.0 2.5 4.0 Maximum units demand per period 375,000 180,000 65,000 The single machine used for all three products has a maximum capacity of 798,000 hours per...
Needing Help with b and c. Required information [The following information applies to the questions displayed below.] Clarke Corporation manufactures three products (X-1, X-2, and X-3) utilizing, in one of the processes, a single machine for all products. Data on the individual products follow. X-1 X-2 X-3 Price per unit $156 $256 $512 Variable cost per unit $78 $139 $296 Machine hours per unit 1.0 2.5 4.0 Maximum units demand per period 370,000 178,000 ...
! Required information Problem 4-75 and 4-76 (Static) (LO 4-4,5) [The following information applies to the questions displayed below) Clarke Corporation manufactures three products (X-1, X-2, and X-3) utilizing in one of the processes, a single machine for all products. Data on the individual products follow. X-1 X-2 Price per unit X-3 $ 100 $ 200 Variable cost per unit $ 400 50 $ 120 $ 240 Machine hours per unit 1.0 4.0 Maximum units demand per period 300,000 150,000...
Required: a. How many units of each product should be produced each period? b. A local engineering firm has suggested to Clarke that it might be able to increase the capacity on the machine. What is the maximum Clarke would be willing to pay for an increase of twenty (20) machine hours? c. Suppose the maximum capacity on the machine was 354,000 hours (instead of 618,000 hours). What is the maximum Clarke would be willing to pay for an increase...