1a. | Materials price variance = AQP x (AR - SR) = 76000 x ($0.30 - $0.33) = $2280 F |
Materials quantity variance = SR x (AQ - SQ) = $0.33 x (43750 - 35000) = $2887.50 = $2888 U | |
AQ = 76000 - 32250 = 43750 | |
SQ = 5000 toys x 7 microns = 35000 | |
1b. | Labor rate variance = AH x (AR - SR) = 6000 x ($6.90 - $6.50) = $2400 U |
AR = $41400/6000 = $6.90 | |
Labor efficiency variance = SR x (AH - SH) = $6.50 x (6000 - 5500) = $3250 U | |
SH = 5000 toys x 1.1 hours = 5500 |
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy Direct materials: 6 microns per toy at $0.33 per micron Direct labor: 1.2 hours per toy at $6.60 per hour During July, the company produced 5,300 Maze toys. Production data for the month on the toy follow Direct materials: 72,000 microns were purchased at a cost of $0.30...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.34 per micron Direct labor: 1.4 hours per toy at $6.50 per hour During July, the company produced 5,300 Maze toys. The toy's production data for the month are as follows: Direct materials. 78,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.35 per micron Direct labor: 1.1 hours per toy at $6.50 per hour During July, the company produced 4,600 Maze toys. The toy's production data for the month are as follows: Direct materials: 72,000 microns were purchased at a cost of...
Dawson Toys, Ltd.. produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy Direct materials: 7 microns per toy at 50.33 per micron Direct labor 1.2 hours per toy at $7.20 per hour During July, the company produced 5,000 Maze toys. Production data for the month on the toy follow Direct materials: 74.000 microns were purchased at a cost of $0.20...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.34 per micron Direct labor: 1.3 hours per toy at $7.50 per hour During July, the company produced 5,200 Maze toys. Production data for the month on the toy follow: Direct materials: 74,000 microns were purchased at a cost of $0.32...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.34 per micron Direct labor: 1.1 hours per toy at $6.80 per hour During July, the company produced 4,800 Maze toys. Production data for the month on the toy follow: Direct materials: 71,000 microns were purchased at a cost of $0.33...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.34 per micron Direct labor: 1.1 hours per toy at $7.00 per hour During July, the company produced 4,800 Maze toys. Production data for the month on the toy follow: Direct materials: 73,000 microns were purchased at a cost of $0.32...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $1.50 per micron Direct labor: 1.3 hours per toy at $21 per hour During July, the company produced 3,000 Maze toys. The toy's production data for the month are as follows: Direct materials. 25,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.33 per micron Direct labor: 1.3 hours per toy at $6.50 per hour During July, the company produced 5,000 Maze toys. The toy's production data for the month are as follows: Direct materials: 79,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.30 per micron Direct labor: 1.4 hours per toy at $6.50 per hour During July, the company produced 5,400 Maze toys. The toy's production data for the month are as follows: Direct materials: 79,000 microns were purchased at a cost of...