Answer: $11,892
.
As Job #7-L is not completed at the end of June, it is considered as Ending work-in-process inventory.
.
Calculation of Work-in-process inventory balance: | |
Job #7-L | |
Beginning WIP | $3,720 |
Add: Costs added during June | |
Direct materials used | $2,870 |
Direct labor | $2,410 |
Overhead applied [Direct labor cost x 120% = $2,410 x 120%] | $2,892 |
Work-in process inventory balance | $11,892 |
Question 4 Moor Company uses a job-order costing system and applies overhead costs to jobs at...
Question 4 Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A $3,250 Job #3-6 $2,690 Job #7-L $3,720 beginning work in process ..... COSTS ADDED DURING JUNE: direct materials ...... direct labor $4,680 3,530 $3,950 4,180 $2,870...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started th e month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1 - A $3,250 Job #3-G $2,690 Job #7-L $3,720 beginning work in process COSTS ADDED DURING JUNE: $3,950 4,180 $4,680 3,530 $2,870 2,410 direct materials direct labor...
Question 5 Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job Job #1-A $3,250 Job #3-G $2,690 beginning work in process .. $3,720 COSTS ADDED DURING JUNE: direct materials ... direct labor ........ $4,680 3,530 $3,950 $2,870 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: beginning work in process Job #1-A $3,250 Job #3-G $2,690 Job #7-L $3,720 COSTS ADDED DURING JUNE: direct materials direct labor ..... $4,680 3,530 $3,950 4,180 $2,870 2,410 During June,...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Comp any started the month of June with three jobs in process. The cost of beg inning work in process plus the costs added during June are shown below: Job #1 - A Job #3-G Job #7-L beginning work in process $3,720 $2,690 $3,250 COSTS ADDED DURING JUNE: $3,950 $4,680 direct materials $2,870 direct labor 2,410 3,530...
Question 5 4.5 pts Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A $3,250 Job #3-G $2,690 Job #7 -L $3,720 beginning work in process ..... COSTS ADDED DURING JUNE: direct materials direct labor $4,680 3,530 $3,950...