Option 3rd is correct. i.e $34,052.
Amount($) | |
Total fixed manufacturing overhead | 33,400 |
Total variable manufacturing overhead(4000*2)+(1000*4) | 12,000 |
Total manufacturing overhead | 45,400 |
Divide by Total machine hours | 5,000 |
Predetermined manufacturing overhead rate | 9.08 |
Job M | |
Direct materials | 8,400 |
Direct labor | 8,400 |
Overhead applied(1300+600)*9.08 | 17,252 |
Total manufacturing cost | 34,052 |
Help Save Opunul Corporation has two manufacturing departments-Molding and Finishing. The company used the following data...
Opunul Corporation has two manufacturing departments-Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Molding 6,500 $14,000 Finishing 3,500 $4,200 Total 10,000 $18,200 Estimated total machine-hours (MES) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per X $ 1.00 $ 2.00 During the most recent month, the company started and completed two jobs--Job A and Job M. There were no beginning Inventories. Data concerning those two...
Opunul Corporation has two manufacturing departments--Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Molding Estimated total machine-hours (MHS) 6,500 Estimated total fixed manufacturing overhead cost $ 20,000 Estimated variable manufacturing overhead cost per $ 2.50 MH Finishing 3,500 $5,000 $ 5.00 Tota 10,000 $25,000 During the most recent month, the company started and completed two jobs --Job A and Job M. There were no beginning inventories. Data concerning...
Opunul Corporation has two manufacturing departments--Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Molding Estimated total machine-hours (MHS) 6,500 Estimated total fixed manufacturing overhead cost $ 16,000 Estimated variable manufacturing overhead cost per $ 1.00 Finishing 3,500 $ 4,100 $ 2.00 Tota. 10,000 $ 20,100 During the most recent month, the company started and completed two jobs --Job A and Job M. There were no beginning inventories. Data...
Help Save & Opunul Corporation has two manufacturing departments-Molding and Finishing The company used the following data at the beginning of the year to calculate predetemined overhead rates Estimated total machine-hours (ts) Estimated total fixed manufacturing overhead cost Estinated variable manufacturing overhead cost per Holding 6,500 Finishing 3,see $ 3,500 Total 10,000 $ 30,s00 $ 27,000 2.00 4.00 Duning the most recent month, the company started and completed two jobs Job A and Job M There were no beginning inventories...
Opunui Corporation has two manufacturing departments--Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHs) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Molding 3,250 $ 17,000 $ 3.00 Finishing 1,750 $ 6,100 $ 6.00 Total 5,000 $ 23,100 During the most recent month, the company started and completed two jobs--Job A and Job M. There were no beginning inventories. Data...
TB MC Qu. 2-113 Opunul Corporation has two manufacturing... Opunul Corporation has two manufacturing departments --Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Molding Estimated total machine-hours (MS) 6,500 Estimated total fixed manufacturing overhead cont $ 29,000 Estimated variable manufacturing overhead cost $ 2.50 per M Finishing 3,500 $6,000 $ 5.00 Total 10,000 $35,000 During the most recent month, the company started and completed two jobs-Job A and...
Opunui Corporation has two manufacturing departments --Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Estimated total machine-hours (MHs) Estimated total fixed manufacturing overhead cost Estimated variable manufacturing overhead cost per MH Molding 4,000 $ 25,000 $ 1.00 Finishing 1,000 $ 3,700 $ 2.00 Total 5,000 $ 28,700 During the most recent month, the company started and completed two jobs--Job A and Job M. There were no beginning inventories....
Opunui Corporation has two manufacturing departments--Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Molding Finishing Total Estimated total machine-hours (MHs) 3,250 1,750 5,000 Estimated total fixed manufacturing overhead cost $ 19,000 $ 4,300 $ 23,300 Estimated variable manufacturing overhead cost per MH $ 2.50 $ 5.00 During the most recent month, the company started and completed two jobs--Job A and Job M. There were no beginning inventories. Data...
Opunui Corporation has two manufacturing departments--Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Molding Estimated total machine-hours (MHS) 6,500 Estimated total fixed manufacturing overhead cost $ 24,000 Estimated variable manufacturing overhead cost $ 1.50 per MH Finishing 3,500 $ 6,800 $ 3.00 Total 10,000 $ 30,800 During the most recent month, the company started and completed two jobs--Job A and Job M. There were no beginning inventories. Data...
Opunui Corporation has two manufacturing departments--Molding and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Molding Finishing Total Estimated total machine-hours (MHs) 6,500 3,500 10,000 Estimated total fixed manufacturing overhead cost $ 23,000 $ 4,600 $ 27,600 Estimated variable manufacturing overhead cost per MH $ 2.00 $ 4.00 During the most recent month, the company started and completed two jobs--Job A and Job M. There were no beginning inventories. Data...