On July 23 of the current year, Dakota Mining Co. pays $4.715,000 for land estimated to contain 5,125,000 tons of recoverable ore. It installs and pays for machinery costing $410,000 on July 25. The company removes and sells 480,000 tons of ore during its first five months of operations ending on December 31 . Depreciation of the machinery is in proportion to the mine's depletion as the machinery will be abandoned after the ore is mined.
Required
Prepare entries to record (a) the purchase of the land, (b) the cost and installation of machinery. (c) the first five months' depletion assuming the land has a net salvage value of zero after the ore is mined, and (d) the first five months' depreciation on the machinery.
Anolys/s Component
(e) If the machine will be used at another site when extraction is complete, how would we depreciate this machine?
Date | Account Title and Explanation | Debit ($) | Credit ($) |
July 23 (a) |
Mineral Deposit | 4,715,000 | |
Cash | 4,715,000 | ||
(To record purchase of land for mineral ore extraction) | |||
July 25 (b) |
Machinery | 410,000 | |
Cash | 410,000 | ||
(To record the installation of machinery) | |||
Dec.31 (c) | Depletion Expenses-Mineral Deposit | 441,600 | |
Accumulated Depletion-Mineral Deposit | 441,600 | ||
(To record the depletion expenses) | |||
Dec.31 (d) | Depreciation Expenses-Machinery | 38,400 | |
Accumulated Depreciation-Machinery | 38,400 | ||
(To record the depreciation expenses) |
Working Note:-
Depletion Expenses= $4,715,000/ 5,125,000 tons
=0.92 per ton
480,000 tons*0.92 =$441,600
Depreciation Expenses= $410,000/ 5,125,000 tons
=$0.08 per ton
480,000 tons *$0.08= $38,400
e-After the completion of extraction work, if the machine is used at another site, then it is depreciated over its own useful life.
On July 23 of the current year, Dakota Mining Co. pays $4.715,000 for land estimated to contain 5,125,000 tons of recoverable ore
On July 23 of the current year, Dakota Mining Co. pays $7,390,320 for land estimated to contain 8,904,000 tons of recoverable ore. li installs machinery costing $801,360 that has a 10 -year life and no salvage value and is capable of mining the ore deposit in eight years. The machinery is paid for on July 25 , seven days before mining operations begin. The company removes and sells 458,250 tons of ore during its first five months of operations ending...
On July 23 of the current year, Dakota Mining Co. pays $6,645,600 for land estimated to contain 8.520,000 tons of recoverable ore. It installs machinery costing $681.600 that has a 10-year life and no salvage value and is capable of mining the ore deposit in eight years. The machinery is paid for on July 25, seven days before mining operations begin. The company removes and sells 437,500 tons of ore during its first five months of operations ending on December...
on July 23 of the current year, Dakota Mining Co. pays $5,961,600 for land estimated to contain 8,280,000 tons of recoverable ore. It installs and pays for machinery costing $828,000 on July 25. The company removes and sells 426,500 tons of ore during its first five months of operations ending December 31. Depreciation of the machinery is in proportion to the mine’s depletion as the machinery will be abandoned after the ore is mined.
Required information The following information applies to the questions displayed below) On July 23 of the current year, Dakota Mining Co. pays $6,966,000 for land estimated to contain 9,288,000 tons of recoverable ore. It installs and pays for machinery costing $2,322,000 on July 25. The company removes and sells 479,500 tons of ore during its first five months of operations ending on December 31. Depreciation of the machinery is in proportion to the mine's depletion as the machinery will be...
Check my work [The following information applies to the questions displayed below.] On July 23 of the current year, Dakota Mining Co. pays $4,715,000 for land estimated to contain 5,125,000 tons of recoverable ore. It installs and pays for machinery costing $410,000 on July 25 The company removes and sells 480.000 tons of ore during its first five months of operations ending on December 31. Depreciation of the machinery is in proportion to the mine's depletion as the machinery will...
Required information (The following information applies to the questions displayed below. On July 23 of the current year, Dakota Mining Co. pays $6,966,000 for land estimated to contain 9,288,000 tons of recoverable ore. It installs and pays for machinery costing $2,322,000 on July 25. The company removes and sells 479,500 tons of ore during its first five months of operations ending on December 31. Depreciation of the machinery is in proportion to the mine's depletion as the machinery will be...
Check my work 2 Required information [The following information applies to the questions displayed below.) On July 23 of the current year, Dakota Mining Co. pays $6.789,600 for land estimated to contain 8,280,000 tons of recoverable ore. It installs and pays for machinery costing $1,490,400 on July 25. The company removes and sells 424,250 tons of ore during its first five months of operations ending on December 31. Depreciation of the machinery is in proportion to the mine's depletion as...
Required Information The following information applies to the questions displayed below On July 23 of the current year, Dakota Mining Co. pays $6.383.520 for land estimated to contain 8,184,000 tons of recoverable ore. It insta s and pays for machinery costing $1063.920 on July 25. The company removes and sells 420,750 tons of ore during its first five months of operations ending on December 31 Depreciation of the machinery is in proportion to the mine's depletion as the machinery w...
On April 2, 2017, Montana Mining Co. pays $3,721,000 for an ore deposit containing 1,525,000 tons. The company installs machinery in the mine costing $213,500, with an estimated seven-year life and no salvage value. The machinery will be abandoned when the ore is completely mined. Montana begins mining on May 1, 2017, and mines and sells 166,200 tons of ore during the remaining eight months of 2017. Prepare the December 31, 2017, entries to record both the ore deposit depletion...
On April 2, 2017, Montana Mining Co, pays $3,708,390 for an ore deposit containing 1.558,000 tons. The company installs machinery in the mine costing $212,300, with an estimated seven-year life and no salvage value. The machinery will be abandoned when the ore is completely mined. Montana begins mining on May 1, 2017, and mines and sells 172,600 tons of ore during the remaining eight months of 2017 Prepare the December 31, 2017, entries to record both the ore deposit depletion...