System Announcements CALCULATOR PRINTER VERSION BACK NEXT RCES Exercise 5-11 Joshua Hill, Coronado & Hill Fabricators produc

0 0
Add a comment Improve this question Transcribed image text
Answer #1
January February March Quarter
Budgeted unit sales 5000 9750 8750 23500
Budgeted Ending inventory 488 438 363 363
Total units required 5488 10188 9113 23863
Beginning inventory 1400 488 438 1400
Budgeted production 4088 9700 8675 22463
Workings:
Budgeted Ending inventory:
January 488 =9750*5%
February 438 =8750*5%
March 363 =7250*5%
Add a comment
Know the answer?
Add Answer to:
System Announcements CALCULATOR PRINTER VERSION BACK NEXT RCES Exercise 5-11 Joshua Hill, Coronado & Hill Fabricators'...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Joshua Hill, Waterway & Hill Fabricators' production manager, has just completed the company's production budget for...

    Joshua Hill, Waterway & Hill Fabricators' production manager, has just completed the company's production budget for the first quarter. January February March Quarter Budgeted Production 18,086 32,955 29,223 80,264 Each brick requires 15 minutes to produce, and Joshua expects to pay workers $17 per direct labor hour in the coming year. Prepare Waterway & Hill's direct labor budget for the first quarter. (Round per unit answers to 2 decimal places, eg. 0.35 & all other answers to O decimal places,...

  • Joshua Hill, Marigold & Hill Fabricators' production manager, has just received the company's sales budget for...

    Joshua Hill, Marigold & Hill Fabricators' production manager, has just received the company's sales budget for the first quarter: PHOTO ONE Manufacturing overhead budget for the first quarter follows: PHOTO ONE He also received the direct materials purchases budget and direct labor budget which were as follows: PHOTO TWO Joshua plans to have 2,072 finished bricks at a cost of $18,130 in inventory at the beginning of the year. The company applies manufacturing overhead based on direct labor hours, and...

  • Joshua Hill, Bonita & Hill Fabricators' production manager, has just received the company's sales budget for...

    Joshua Hill, Bonita & Hill Fabricators' production manager, has just received the company's sales budget for the first quarter: February March 10.1409,100 Quarter 24.440 Budgeted unit sales Budgeted ending inventory January 5.200 2,028 7.228 1.456 1,820 1,508 1,508 Total units required 11.960 2,028 10.608 1,820 25.948 1456 Beginning inventory Budgeted production 5,772 9 .932 8,788 24,492 Its manufacturing overhead budget for the first quarter is as follows: January February March Quarter DLH worked 1,443 2,483 2,197 6,123 VOH per DLH...

  • Joshua Hill, Waterway & Hill Fabricators' production manager, has just completed the company's production budget for...

    Joshua Hill, Waterway & Hill Fabricators' production manager, has just completed the company's production budget for the first quarter. January February March Quarter 21,978 37,818 33,46293,258 Each brick requires 15 minutes to produce, and Joshua expects to pay workers $20 per direct labor hour in the coming year. Prepare Waterway & Hill's direct labor budget for the first quarter. (Round per unit answers to 2 decimal places, e.g. 0.35 & all other answers to 0 decimal places, eg. 5,275. Convert...

  • CALCULATOR PRINTER VERSION BACK NEXT > Exercise 5-12 Concord manufactures competition stunt kites. In November, Jerry...

    CALCULATOR PRINTER VERSION BACK NEXT > Exercise 5-12 Concord manufactures competition stunt kites. In November, Jerry Box prepared the following production budget for the first quarter of the coming year. Desired ending inventory is based on the following month's budgeted sales, Budgeted unit Sales Budgeted ending inventory Total units required Beginning inventory Budgeted production January February March Quarter 23,500 37,800 31,800 93,100 7,560 6,360 2,640 2,640 31,060 44,160 34,440 95,740 4,700 7.560 6,360 4,700 26.360 36,600 28,080 91,040 Following higher...

  • 5-8 Preparing a sales budget (LO 3) Bates & Hill Fabricators produces commemo- rative bricks that...

    5-8 Preparing a sales budget (LO 3) Bates & Hill Fabricators produces commemo- rative bricks that organizations use for fundraising projects. Aaron Bates, the company's vice president of marketing, has prepared the following sales forecast for the first six months of the coming year. The company plans to sell the bricks for $15 each. June January February March April May 20,000 39,000 35,000 29,000 23,000 20,000 Required Prepare Bates & Hill's sales budget for the first quarter of the coming...

  • Joshua Hill, Bramble & Hill Fabricators' production manager, has just completed the company's production budget for...

    Joshua Hill, Bramble & Hill Fabricators' production manager, has just completed the company's production budget for the first quarter. January February March Quarter Budgeted Production 20,938   36,710   32,506 90,154 Each brick requires 15 minutes to produce, and Joshua expects to pay workers $19 per direct labor hour in the coming year. Prepare Bramble & Hill's direct labor budget for the first quarter. (Round per unit answers to 2 decimal places, e.g. 0.35 & all other answers to 0 decimal places,...

  • Joshua plans to have 3,248 finished bricks at a cost of $28,420 in inventory at the...

    Joshua plans to have 3,248 finished bricks at a cost of $28,420 in inventory at the beginning of the year. The company applies manufacturing overhead based on direct labor hours, and the current predetermined rates are $12 per direct labor hour for fixed manufacturing overhead and $0.70 per direct labor hour for variable manufacturing overhead. Prepare Sheridan & Hill’s ending inventory and cost of goods sold budget for the first quarter. Assuming that the company has no beginning and ending...

  • please help HVV - Davis, Managerial Accounting, 3e Helal System Announcements PRINTER VERSION BACK Exercise 5-7...

    please help HVV - Davis, Managerial Accounting, 3e Helal System Announcements PRINTER VERSION BACK Exercise 5-7 Coronado and Company makes and sells high-quality glare ters for computer monitors, John Stanford, controller is responsible for preparing Coronado's master budget. He has received the following sales forecast for the coming year from the sales manager January 38,100 S98 February 23,900 598 March 24,200 Forecasted unit sales Sales price per unit April 26,700 Prepare Coronado's sales budget for the first quarter February March...

  • CALCULATOR PRINTER VERSION BACK NEXT Exercise 5-13 Concord Auto has developed the following production plan for...

    CALCULATOR PRINTER VERSION BACK NEXT Exercise 5-13 Concord Auto has developed the following production plan for its new auto part, January 11,430 February March 8,880 9,300 April 13,700 Budgeted production (units) Each unit contains 3 pounds of raw material. The desired raw materials ending inventory is 125% of the next month's production needs, plus an additional 598 pounds. January's beginning inventory requirements equal 125% of the current month's production needs, plus an additional 598 pounds Prepare the direct materials purchases...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT