20) The answer is A $10

Overhead rate for quality control = Total overheads / Number of inspections = $9000 / 9000 = $10

21) The correct answer is B

Direct labor costs are directly assigned to the workers on unit basis as wages are paid to them on per unit basis or on number of hours basis.

Add a comment
Know the answer?
Add Answer to:
24. For a company using arti...- 20. The following estimated overhead cost information is available for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 10) The following overhead cost information is available for Compton Corporation for 2018: Activity Purchasing Receiving...

    10) The following overhead cost information is available for Compton Corporation for 2018: Activity Purchasing Receiving Machine setups Quality control Allocation Base Number of purchase orders Number of shipments received Number of setups Number of inspections Overhead Cost $ 80,000 60,000 150,000 48,000 During the year, 4,000 purchase orders were issued; 30,000 shipments were received; 3,000 machine setups were performed; and 3,000 inspections were conducted. a) What is the overhead rate for the purchasing activity? b) What is the overhead...

  • The following estimated overhead cost information is available for NOP Corporation: Activity                           Alloc

    The following estimated overhead cost information is available for NOP Corporation: Activity                           Allocation Base                   OH Cost Purchasing                    # of Purchase Orders         $600,000 Receiving                      # of Shipments                    $50,000 Machine Set-Ups          # of Setups                          $240,000 Quality Control             # of Inspections                   $160,000 During the year, 60,000 purchase orders were issued; 25,000 shipments were received; 2000 setups; and 10,000 inspections. Direct labor hours were 20,000. A. What is the cost allocation for each of the four activities using ABC costing? B. What is the Predetermined overhead rate using the traditional method (direct...

  • 8) Sikorski Manufacturing assigns overhead based on machine hours. The Milling Dept. logs 1,400 machine hours...

    8) Sikorski Manufacturing assigns overhead based on machine hours. The Milling Dept. logs 1,400 machine hours and the Cutting Dept. shows 3,000 machine hours for the period. If the overhead rate is $5 per machine hour, how much overhead will be assigned? a. $1,400. b. $3,000. c. $4,400. d. $22,000. 9) What is the biggest disadvantage of ABC? a. It does not provide costing information needed for GAAP purposes. b. It causes management to make frivolous decisions. c. It often...

  • Machine setups -         $130 per setup                         Soldering -     

    Machine setups -         $130 per setup                         Soldering -                  $2.25 per joint Quality control -         $40 per inspection                   Shipments -                 $220 per shipment Purchase orders -        $75 per order                           Machine related -        $8 per machine hour Product X-20 Product Y-30 Expected Activity Amount of OH Expected Activity Amount of OH Machine setups xx setups $130,000 600 setups Quality control xx inspect 160,000 5,000 inspections Purchase orders xx orders 63,000 360 orders Soldering xx...

  • Problem 2 The controller for the XZY Company has established the following overhead pools and cost...

    Problem 2 The controller for the XZY Company has established the following overhead pools and cost drivers: Overhead Cost Pool Budgeted Overhead Cost Cost Driver Machine setups $100,000 Number of setups Material Handling $50,000 Units of Raw Material Quality control inspections $37,500 Number of Inspections Other overhead costs $100,000 Machine Hours Overhead Cost Pool Budgeted Level for Cost Driver Pool Overhead Rate Machine setups 100 setups $1,000 per setup Material Handling 50,000 units $1 per unit Quality control inspections 1,000...

  • c. assigns activity cost pools to products and services, then allocates overhead back to the activity...

    c. assigns activity cost pools to products and services, then allocates overhead back to the activity cost pools. d. allocates overhead directly to products and services based on activity levels e. none of these answers are correct. 21. Which of the following has the weakest linkage between activity and cost driver? Activity Machine setup Machine maintenance Lighting on shop floor Quality control Manual cloth making Cost Driver Number of setups Book value of machines Number of kilowatt-bours Square feet of...

  • Calculate the total amount paid by the local construction company for the 5,000 windows. The estimated...

    Calculate the total amount paid by the local construction company for the 5,000 windows. The estimated manufacturing overhead costs for Watts Window Company for 2010 are listed below: Work space $3,000,000 Quality control inspections ..... 1,000,000 Electric power 400,000 Materials handling 1,200,000 Machine setups 700,000 Watts Company assigns overhead costs to products using an activity based costing system. The following information pertains to the activity based cost drivers and overhead costs: Type of cost Activity based cost driver Work space...

  • Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

    Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $   95000 500 orders Machine Setup Setups 274500 450 setups Machining Machine hours 1437500 125000 MH Assembly Parts 1150000 1000000 parts Inspection Inspections 275000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $0.10 per part. $6464 per...

  • Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

    Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $   135000 500 orders Machine Setup Setups 310500 450 setups Machining Machine hours 1550000 125000 MH Assembly Parts 1230000 1000000 parts Inspection Inspections 315000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $7081 per order. $0.14 per...

  • Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at...

    Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $   110000 500 orders Machine Setup Setups 288000 450 setups Machining Machine hours 1475000 125000 MH Assembly Parts 1180000 1000000 parts Inspection Inspections 290000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $220 per order. $6686 per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT