The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of JuComplete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 What is the coRequired 1 Required 2 Required 3 Required 4 How much total direct labor cost is incurred in June? Job 602 Job 603 Job 604 TotRequired 1 Required 2 Required 3 Required 4 What predetermined overhead rate is used in June? Predetermined overhead rate < RRequired 1 Required 2 Required 3 Required 4 How much cost is transferred to finished goods inventory in June? Job Raw Materia

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1) Direct Material Job 602 Job 603 Job 604 Total
May Cost 600 0 0 600
June Cost 800 3,600 2,600 7000
Total Cost 1,400 3,600 2,600 7600
2) Direct Labour
Job 602 Job 603 Job 604 Total
May Cost 150 0 0 150
June Cost 750 1,380 2,000 4130
Total Cost 900 1,380 2,000 4280
3) Predetermined overhead rate Job 602 Job 603 Job 604
Overhead (A) 450 690 1,000
Direct Labour (B) 900 1,380 2,000
Predetermined overhead rate 50% 50% 50%
4)

Job

Direct Materials

Direct Labor

Applied Overhead

Total Cost

Cost Transferred to Finished Goods

Cost of Ending WIP

602

$     1,400.00 $     900.00 $            450.00 $             2,750.00 $                2,750.00

603

$     3,600.00 $  1,380.00 $            690.00 $             5,670.00 $                5,670.00

604

$     2,600.00 $  2,000.00 $         1,000.00 $             5,600.00 $           5,600.00

Total

$     7,600.00 $  4,280.00 $         2,140.00 $           14,020.00 $                8,420.00 $           5,600.00

Job 603 3600 1380 690 Job 604 2600 2000 1000 1 The computer workstation furniture manuf Job 602 3 Direct materials 1400 4 Dir

Add a comment
Know the answer?
Add Answer to:
The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...

    The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 $1,300 Direct materials Direct labor Job 603 $3,100 1,409 700 Job $3,200 2,100 1,050 45e Job 602 was started in production in May, and these costs were assigned to it in May, direct materials, $700; direct labor, $250; and overhead, $125, Jobs 603...

  • The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...

    The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 Job 603 Job 604 Direct materials $ 1,500 $ 3,200 $ 3,100 Direct labor 1,000 1,520 2,300 Overhead 400 608 920 Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $400; direct labor,...

  • The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...

    The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 Job 603 Job 604 Direct materials $ 1,600 $ 3,700 $ 3,100 Direct labor 700 1,380 1,600 Overhead 350 690 800 Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $500; direct labor,...

  • 2. The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As...

    2. The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June. Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Direct materials Direct labor Overhead Job 682 $1,600 700 3se Job 603 $3,200 1,380 590 Job 604 $3,200 1,600 800 eBook Job 602 was started in production in May, and these costs were assigned to it in May, direct materials, $700 direct labor, $150and...

  • The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...

    The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 Job 603 Job 604 Direct materials $ 1,700 $ 3,500 $ 2,600 Direct labor 700 1,340 2,300 Overhead 350 670 1,150 Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $400; direct labor,...

  • The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...

    The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 Job 603 Job 604 Direct materials $ 1,500 $ 3,200 $ 3,100 Direct labor 1,000 1,520 2,300 Overhead 400 608 920 Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $400; direct labor,...

  • The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...

    The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 Job 603 Job 604 Direct materials $ 1,500 $ 3,200 $ 3,100 Direct labor 1,000 1,520 2,300 Overhead 400 608 920 Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $400; direct labor,...

  • The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...

    The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solution's job cost sheets show the following total costs accumulated on three furniture jobs. Job 602 Job 603 Job 604 Direct materials $1500 $3,300 $27,000 Direct Labor $800 $1,420 $2,100 Overhead $400 $710 $1,050 Job 602 was started in production in May, and these were to it in May;Direct materials ,$600; Direct Labor $180; and overhead, $90. Jobs 603...

  • 2 The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As...

    2 The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Direct materiais Direct labor Overhead Job 602 $1,800 700 350 Job 603 $3,600 1,300 690 Job 604 $3,200 1,500 750 eBook Job 602 was started in production in May, and these costs were assigned to it in May, direct materials, $700; direct labor, $150;...

  • The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of...

    The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs.                                             Job 602                  Job 603                   Job 604 Direct materials                $1,500                    $3,500                     $3,100 Direct labor                           900                      1,380                       2,200 Overhead                             360                          552                      880       Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $800; direct labor, $150;...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT