1/ Using the information presented in Question 1 above, determine the Historical Cost of the building after taking into consideration the capitalization of interest.
2/ Using the information presented in Question 1 above, determine the Interest Expense that Desert would report on their Income Statement for the year ended December 31, 2019.
3/ Using the information in Question 1 above, assume instead that Desert's only other outstanding debt during 2019 was a $450,000, 9%, three-year note (i.e. all other information remains unchanged but Desert no longer has $3,000,000 of other non-specific borrowings; only $450,000 of non-specific debt). Determine the Avoidable Interest from this construction project under this scenario.
1. Calculation of Historical cost of the Building
As per Ind AS-16- Property,Plant and Equipment, the Historical cost of the asset includes the purchase cost of the asset and the other cost incurred to bring the asset for use.
Purchase price of land - $800000
Property taxes and other cost - $20000
Net demolition cost - $100000 ($70000+50000-20000)
Construction cost - $5400000
Interest cost to be capitalized - $160000 ($2000000*8%)
Historical cost - $6480000
2. Calculation of Interest expense to be report in Income statement for year ended 31-Dec-2019
Interest expense = $279000 ($3100000*9%)
1/ Using the information presented in Question 1 above, determine the Historical Cost of the building...
I need help figuring out the last 3 information. Early in 2019, Desert, Co. finalized plans to expand operations. The first stage was completed on January 19th with the purchase of a tract of land to be used as the location for their new office complex. The land and existing building were purchased for $800,000, paying cash. Title search, title insurance, back property taxes and other closing costs totaling $20,000 were paid at closing. During February, the old building was...
Early in 2019, Desert, Co. finalized plans to expand operations. The first stage was completed on January 19th with the purchase of a tract of land to be used as the location for their new office complex. The land and existing building were purchased for $800,000, paying cash. Title search, title insurance, back property taxes and other closing costs totaling $20,000 were paid at closing. During February, the old building was demolished at a cost of $70,000, and an additional...
During February, the old building was demolished at a cost of $240,000, and an additional $200,000 was paid to clear and grade the land. Construction of a new building began on March 1 and was completed on October 30. Construction expenditures were as follows: March 31 $1,600,000 June 30 2,400,000 July 31 2,400,000 September 1 1,200,000 HDR Company did not borrow specifically for the construction project, but did have the following debt outstanding throughout 2019: ...
During February, the old building was demolished at a cost of $240,000, and an additional $200,000 was paid to clear and grade the land. Construction of a new building began on March 1 and was completed on October 30. Construction expenditures were as follows: March 31 $1,600,000 June 30 2,400,000 July 31 2,400,000 September 1 1,200,000 HDR Company did not borrow specifically for the construction project, but did have the following debt outstanding throughout 2019: ...
Hello - this is all one question, thank you very much in advance! I give thumbs up for all of my questions/answers! On January 3, 2019, HDR Company acquired a tract of land just outside the city limits. The land and existing building were purchased for $4.8 million. HDR Company paid $800,000 and signed a noninterest-bearing note requiring the company to pay the remaining $4,000,000 on December 31, 2020. An interest rate of 7% properly reflects the time value of...
On January 3, 2019, HDR Company acquired a tract of land just outside the city limits. The land and existing building were purchased for $4.8 million. HDR Company paid $800,000 and signed a noninterest-bearing note requiring the company to pay the remaining $4,000,000 on December 31, 2020. An interest rate of 7% properly reflects the time value of money for this type of loan agreement. Transfer taxes, title insurance, and other costs totaling $48,000 were paid at closing. During...
Early in its fiscal year ending December 31, 2018, San Antonio Outfitters finalized plans to expand operations. The first stage was completed on March 28 with the purchase of a tract of land on the outskirts of the city. The land and existing building were purchased for $1,140,000. San Antonio paid $370,000 and signed a noninterest-bearing note requiring the company to pay the remaining $770,000 on March 28, 2020. An interest rate of 6% properly reflects the time value of...
Problem 10-12 Acquisition costs; lump-sum acquisition; noninterest-bearing note; interest capitalization [LO10-1, 10-2, 10-3, 10-7] Early in its fiscal year ending December 31, 2018, San Antonio Outfitters finalized plans to expand operations. The first stage was completed on March 28 with the purchase of a tract of land on the outskirts of the city. The land and existing building were purchased for $860,000. San Antonio paid $230,000 and signed a noninterest-bearing note requiring the company to pay the remaining $630,000 on...
Early in its fiscal year ending December 31, 2018. San Antonio Outfitters finalized plans to expand operations. The first stage was completed on March 28 with the purchase of a tract of land on the outskirts of the city. The land and existing building were purchased for $1.180,000. San Antonio paid $390,000 and signed a noninterest-bearing note requiring the company to pay the remaining $790,000 on March 28, 2020. An interest rate of 6% properly reflects the time value of...
Problem 10-12 Acquisition costs; lump-sum acquisition; noninterest-bearing note; interest capitalization [LO10-1, 10-2, 10-3, 10-7] Early in its fiscal year ending December 31, 2018, San Antonio Outfitters finalized plans to expand operations. The first stage was completed on March 28 with the purchase of a tract of land on the outskirts of the city. The land and existing building were purchased for $860,000. San Antonio paid $230,000 and signed a noninterest-bearing note requiring the company to pay the remaining $630,000 on...