Q1
Prime Corporation
Cost of Goods Manufactured Schedule for the Month $ $
Direct Materials used:
Beginning raw materials inventory 11500
Add: Cost of raw materials purchased 31000
Total raw materials available 42500
Less: Ending raw materials inventory 18800
Total raw materials used 23700
Direct Labour 58500
Manufacturing overhead applied to work in process 87800
Total Manufacturing Costs 170000
Add beginning work in process inventory 55900
225900
Less ending work in process inventory 65600
Cost of Goods Manufactured 160300
Q2
Prime Corporation
Cost of Goods Sold Schedule for the Month $
Beginning Finished Goods inventory 34600
Add: Cost of Goods Manufactured 160300
Cost of Goods available for sale 194900
Less :Ending Finished Goods inventory 43800
Cost of Goods Sold before adjustment 151100
Add: Underapplied overheads 4040
Adjusted Cost of Goods Sold 155140
Add a comment
Know the answer?
Add Answer to:
Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $ 31,000 $ 4,770 $58. see $ 87,800 $ 4.040 Inventories Raw materials Work in process Finished goods Beginning $ 11,500 $ 55,900 $ 34,600 Ending $ 18, 8ee $ 65,689 $ 43,800 Required: 1. Prepare a schedule of cost of goods manufactured for the month 2....

  • Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials used in production Direct labor Manufacturing overhead applied to work in process Underapplied overhead $31,000 $ 4,900 $58,400 $87,300 $ 4,140 Inventories Beginning Ending Raw materials $11,700 $18,800 Work in $54,600 $65,600 process Finished $34,100 $43,800 goods Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of cost of goods sold for the month....

  • Primare Corporation has provided the following data concerning last month’s manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month’s manufacturing operations. Purchases of raw materials $ 31,000 Indirect materials included in manufacturing overhead $ 4,770 Direct labor $ 59,900 Manufacturing overhead applied to work in process $ 87,500 Underapplied overhead $ 4,090 Inventories Beginning Ending Raw materials $ 10,400 $ 18,800 Work in process $ 55,400 $ 67,200 Finished goods $ 34,900 $ 42,500 Required: 1. Prepare a schedule of cost of goods manufactured for the month. Prepare a...

  • Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $31,000 $ 4,710 $59,400 $88,800 $ 4,010 Inventories Raw materials Work in process Finished goods Beginning Ending $ 11,500 $ 19,700 $ 54,700 $ 66,600 $ 34,300 $ 42,400 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of...

  • Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials used in production Direct labor Manufacturing overhead applied to work in process Underapplied overhead $31,000 $ 4,770 $58,400 $87,000 $ 4,080 Inventories Raw materials Work in process Finished goods Beginning $ 10,600 $ 54,700 $ 33,200 Ending $ 18,800 $ 65,300 $ 43,300 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of cost...

  • Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $32,000 $ 4,850 $59,900 $88,700 $ 4,030 Inventories Raw materials Work in process Finished goods Beginning $ 11,900 $ 55,400 $ 34,600 Ending $ 19,400 $ 65,500 $ 44,000 Required: 1. Prepare a schedule of cost of goods manufactured for the month 2. Prepare a schedule of...

  • Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $31,000 $ 4,620 $58, 200 $87,200 $ 4,070 Inventories Raw materials Work in process Finished goods Beginning $ 10,000 $ 54,500 $ 34,800 Ending $ 18,700 $ 67,800 $ 42,600 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule...

  • Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials used in production Direct labor Manufacturing overhead applied to work in process Underapplied overhead $30,000 $ 4,990 $58,600 $87,900 $ 4,040 Ending Inventories Raw materials Work in process Finished goods Beginning $ 11,500 $ 55,700 $ 33,100 $ 19,800 $ 69,800 $ 42,700 Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of cost...

  • Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations. Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $ 31,000 $ 4,640 $ 58,200 $ 88,400 $ 4,020 Inventories Beginning Ending Raw materials $11,700 $19,100 Work in $55,800 $68,700 process Finished $34,000 $43,200 goods Required: 1. Prepare a schedule of cost of goods manufactured for the month. 2. Prepare a schedule of cost of goods...

  • Primare Corporation has provided the following data concerning last month's manufacturing operations Purchases of raw materials...

    Primare Corporation has provided the following data concerning last month's manufacturing operations Purchases of raw materials Indirect materials included in manufacturing overhead Direct labor Manufacturing overhead applied to work in process Underapplied overhead $32,000 $ 4,970 $59,700 $88,100 $ 4,070 Inventories Beginning Ending Raw materials $11,500 $18,500 Work irn process Finished goods $34,100 $43,100 $55,500 $67,100 Required: 1. Prepare a schedule of cost of goods manufactured for the month 2. Prepare a schedule of cost of goods sold for the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT