Direct Direct Direct Materials Labor Cost Labor Hours Job 200 $ 500 $800 40 40 Job 201 350 200 10 Job 202 1,000 600 30 Franks

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Predetermined overhead rate = $100000/2500 = $40 per hour

Total manufacturing cost of Job 201 = Direct material + Direct labor + Overhead

= $350+200+40*10

= $950

Add a comment
Know the answer?
Add Answer to:
Direct Direct Direct Materials Labor Cost Labor Hours Job 200 $ 500 $800 40 40 Job...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1) Job 200 Job 201 Job 202 Direct Materials S 500 350 1,000 Direct Direct Labour...

    1) Job 200 Job 201 Job 202 Direct Materials S 500 350 1,000 Direct Direct Labour Cost Labour Hours $800 200 10 600 30 Franks Fabricating uses job costing and applies overhead using a normal costing system and uses direct labour cost as the allocation base. This period's estimated overhead cost is $100,000 and estimated direct labour cost of $50,000 and 2,500 direct labour hours. What is the overhead allocation rate? *a) 200% b) 50% c) 30% d) 60%

  • Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as...

    Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 54,500 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost 2 ? $1,533,500 Job Omega Direct materials Direct...

  • Nadal Company is debating the use of direct labor cost or direct labor hours as the...

    Nadal Company is debating the use of direct labor cost or direct labor hours as the cost allocation base for allocating manufacturing overhead. The following information is available for the most recent year: Actual direct labor hours Estimated direct labor hours Actual manufacturing overhead costs Estimated manufacturing overhead costs Actual direct labor cost Estimated direct labor cost 232,500 250,300 $363,500 $401,900 $465,800 $500,700 If Nadal Company uses direct labor cost as the allocation base, what would the predetermined manufacturing overhead...

  • Landen Corporation uses a job-order costing system. At the beginning of the year, the company made...

    Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 125,000 Machine-hours required to support estimated production 62,500 Fixed manufacturing overhead cost $ 350,000 Variable manufacturing overhead cost per direct labor-hour $ 3.80 Variable manufacturing overhead cost per machine-hour $ 7.60 During the year, Job 550 was started and completed. The following information is available with respect to this job: Direct materials $ 201...

  • Quick Step Company is debating the use of direct labor cost or direct labor hours as...

    Quick Step Company is debating the use of direct labor cost or direct labor hours as the cost allocation base for allocating manufacturing overhead. The following information is available for the most recent year: Estimated direct labor cost Actual direct labor cost Estimated manufacturing overhead costs Actual manufacturing overhead costs Estimated direct labor hours Actual direct labor hours $500,100 $465,100 $425,300 $350,700 250,200 232,800 If Quick Step Company uses direct labor hours as the allocation base, what would the predetermined...

  • Quick Step Company is debating the use of direct labor cost or direct labor hours as...

    Quick Step Company is debating the use of direct labor cost or direct labor hours as the cost allocation base for allocating manufacturing overhead. The following information is available for the most recent year: Estimated direct labor cost Actual direct labor cost Estimated manufacturing overhead costs Actual manufacturing overhead costs Estimated direct labor hours Actual direct labor hours $500,200 $466,000 $425,100 $350.800 250,300 232,600 If Quick Step Company uses direct labor hours as the allocation base, what would the allocated...

  • Reference el brr fo Standard costing (single plantwide rate): Job 721 Job 722 Direct materials 23,400...

    Reference el brr fo Standard costing (single plantwide rate): Job 721 Job 722 Direct materials 23,400 $ 2,500 ur Direct labor* 1,500 19,500 375 4,875 Manufacturing overhead 47,775 S 4,375 $ Total cost Direct labor calculated as follows: Total direct labor costs per job Hours per job Direct labor cost per hour X 25 19,500 780 $ Job 721 X 1,500 Job 722 60 X Manufacturing overhead calculated as follows: Manufacturing Predetermined Total direct labor OH allocated OH allocation rate...

  • Landen Corporation uses a job-order costing system. At the beginning of the year, the company made...

    Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 115,000 57,500 $322,000 $ 3.40 $ 6.80 During the year, Job 550 was started and completed. The following information is available with respect to this job: $ 252 $ 370 Direct...

  • Landen Corporation uses a job-order costing system. At the beginning of the year, the company made...

    Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour 155,000 77,500 $465,000 $ 4.80 $ 9.60 During the year, Job 550 was started and completed. The following information is available with respect to this job: $ 210 $ 349 Direct...

  • Quick Step Company is debating the use of direct labor cost or direct labor hours as...

    Quick Step Company is debating the use of direct labor cost or direct labor hours as the cost allocation base for allocating manufacturing overhead. The following information is available for the most recent year. Estimated Direct Labor Cost 480,000 Actual Direct Labor Cost 465,200 Estimated Manufacturing Overhead 422,400 Actual Manufacturing Overhead 350,000 Estimated Direct Labor Hours 25,080 Actual Direct Labor Hours 23,270 If Quick Step Company uses direct labor cost as the allocation base, what would the allocated manufacturing overhead...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT