So, the project should be
Accepted
PI = 3.52
Compute the Pl static for your firm's new project if the appropriate cost of capital is...
Compute the PI static for your firm's new project if the appropriate cost of capital is 9 percent. (Do not round ntermediate calculations and round your final answer to 2 decimal laces.) Your firm's project Time 0 1 2 3 4 5 6 Cash Flow -680 80 560 760 760 360 760 Should the project be accepted or rejected? Multiple Choice O Rejected O Accepted
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 -$2,900 1 $910 2 $900 3 $800 4 $580 5 $380 Cash flow IRR % Should the project be accepted or rejected? O rejected O accepted
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: Cash flow 0 $1,300 1 $470 2 $570 3 $580 4 $360 5 $160 IRR IRR C % Should the project be accepted or rejected? O accepted O rejected
Compute the Pl statistic for Project Z if the appropriate cost of capital is 8 percent (Do not round intermediate celculations and round your final answer to 2 decimal places.) Project z Time: Cash flow:-$1,600 $470 $600 $770 $420 $220 0 Pl Should the project be accepted or rejected? O accepted O rejected
Compute the MIRR static for Project I if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project I Time: Cash flow: $11,000 $5,330 $4,180 $1,520 $2,000 MIRR % Should the project be accepted or rejected? accepted rejected
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: -$1,000 $350 $480 $520 $300 $100 Cash flow: IRR : :% Should the project be accepted or rejected? O accepted O rejected
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,800 $670 $720 $680 $460 $260 IRR % Should the project be accepted or rejected? Rejected Accepted
Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: Cash flow:-$10,100 $3,850 $4,680 $2,020 $2,650 IRR % Should the project be accepted or rejected? rejected O accepted Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E...
Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,100 $390 $510 $540 $320 $120 IRR= _____% Should the project be accepted or rejected?
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign Do not round intermediate calculations and round your final answer to 2 decimal places.) Protect Time: Cash flow: $1,900 $530 $660 $700 $780 $280 NPV Should the project be accepted or rejected? accepted rejected