Assume the following information pertaining to Cub Company:
Prime costs | $ | 196,000 | |
Conversion costs | 223,000 | ||
Direct materials used | 85,700 | ||
Beginning work in process | 98,900 | ||
Ending work in process | 81,400 | ||
Cost of goods manufactured is calculated to be:
291200
351200
317200
300200
326200
Option (e) is correct
Cost of goods manufactured = Direct materials cost + Conversion cost + Beginning work in process - Ending work in process
Cost of goods manufactured = $85700 + $223000 + $98900 - $81400
Cost of goods manufactured = $326200
Assume the following information pertaining to Cub Company: Prime costs $ 196,000 Conversion costs 223,000 Direct...
Assume the following information pertaining to Cub Company: Prime costs $ 202,000 Conversion costs 235,000 Direct materials used 89,900 Beginning work in process 104,300 Ending work in process 83,800 Factory overhead is calculated to be:
Assume the following information pertaining to Cub Company: Prime costs $ 201,500 Conversion costs 234,000 Direct materials used 89,550 Beginning work in process 103,850 Ending work in process 83,600 Direct labor used is calculated to be: 323,550 32500 111950 88550 112950
23) Assume the following information pertaining to Cub Company: Prime costs charged to jobs during 2018 $195,000 Conversion costs charged to jobs during 2018 225,000 Direct materials charged to jobs during 2018 | 85,000 |Jan 1, 2018: work in process 100,000 Dec. 31, 2018: work in process 80,000 What is Cub's 2018 cost of goods manufactured? A) $330,000. B) $440,000. C) $290,000. D) $300,000. E) $355,000.
Assume the following information pertaining to Cub Company: Ending work in process $89,800 Beginning work in proces $106,400 Direct materials use d 노인 $88,800 Conversion costs $239,300 Prime costs $211,200 s0 $50,000 $100,000 $150,000 $200,000 $250,000 $300,000 Total manufacturing cost is calculated to be: $344,700 $88,800 $122,400 $328,100 $116,900
Assume the following information pertaining to Moonbeam Company: Finished goods inventory Work in process inventory Direct materials Beginning $158,500 104,000 140,750 Ending $149,650 127,750 157,550 Costs incurred during the period are as follows: Total manufacturing costs Factory overhead Direct materials used $934,000 218,000 172,150 Cost of goods sold is calculated to be: Multiple Choice O $910.250. $926,100 $932,100 ooo $906,100. O $919,100.
Assume the following information pertaining to Moonbeam Company: Finished goods inventory Work in process inventory Direct materials Beginning $152,500 100,000 135,750 Ending $144,250 122,750 151, 750 Costs incurred during the period are as follows: Total manufacturing costs Factory overhead Direct materials used $926,000 214,000 168,750 Materials purchases are calculated to be: < Prev 15 of 31 ! Next e to search
1. Which of the following costs are conversion costs? a. direct materials cost and factory overhead cost b. direct labor cost and factory overhead cost c. factory overhead cost d. direct materials cost and direct labor cost 2. Given the following data: Work in process, beginning $14,000 Work in process, ending 20,000 Direct labor costs 4,000 Cost of goods manufactured 8,000 Factory overhead 8,000 Direct materials used is a. $2,000 b. $4,000 c. $14,000 d. $8,000 3. Prime...
Information about Morton Company for the month ending December 31, 2018, is as follows: Sales $650,000 Cost of goods sold 452,000 Net operating income 35,000 Beginning inventories: Direct materials 50,000 Work in process 42,000 Finished goods 70,000 Ending direct materials is 20 percent smaller than beginning direct materials. Ending work in process is 10 percent more than the beginning work in process. Ending finished goods increased by $11,000 during the year. Prime costs and conversion costs are 70 percent and...
Prepare the schedule of cost of goods manufactured for Barton Company using the following information. Direct materials Direct labor Factory overhead costs Work in process, beginning Work in process, ending $ 242,500 73,000 28,000 160,000 144, 250 Barton Company Schedule of Cost of Goods Manufactured Total manufacturing costs Total cost of work in process Cost of goods manufactured $ Use the following information to compute the cost of direct materials used for the current year. Assume the raw materials inventory...
Cost Definitions Wyandotte Company provided the following information for the last calendar year: Beginning inventory: Direct materials $30,000 Work in process 50,000 Ending inventory: Direct materials $16,400 Work in process 23,600 > During the year, direct materials purchases amounted to $254,800, direct labor cost was $166,800, and overhead cost was $300,000. There were 40,000 units produced. Required: 1. Calculate the total cost of direct materials used in production 2. Calculate the cost of goods manufactured Calculate the unit manufacturing cost....