Question

Miramar Industries manufactures two products: A and B. The manufacturing operation involves three overhead activities—production setup,...

Miramar Industries manufactures two products: A and B. The manufacturing operation involves three overhead activities—production setup, materials handling, and general factory activities. Miramar uses activity-based costing to allocate overhead to products. An activity analysis of the overhead revealed the following estimated costs and activity bases for these activities: Activity Cost Activity Base Production setup $250,000 Number of setups Material handling 150,000 Number of parts General overhead 80,000 Number of direct labor hours Each product's total activity in each of the three areas are as follows: Product A Product B Number of setups 100 300 Number of parts 40,000 20,000 Number of direct labor hours 8,000 12,000 What is the activity rate for materials handling?

a.$2.50 per part

b.$7.50 per part

c.$3.75 per part

d.$1.50 per part

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer : a. $2.50 per part

Calculated as

                                     Product A     Product B    Total

Number of parts                         40,000          20,000 = 60000

Material handling cost per setup =   $150000

Material handling cost rate = Total material handling cost/Number of parts

= $150000/60000 = $2.50 per part

Thanks a lot

Kindly hit thumbs up if satisfied

For any query mention in comment section please

Add a comment
Know the answer?
Add Answer to:
Miramar Industries manufactures two products: A and B. The manufacturing operation involves three overhead activities—production setup,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 43. Miramar Industries manufactures two products: A and B. The manufacturing operation involves three overhead activities—production...

    43. Miramar Industries manufactures two products: A and B. The manufacturing operation involves three overhead activities—production setup, material handling, and general factory activities. Miramar uses activity-based costing to allocate overhead to products. An activity analysis of the overhead revealed the following estimated costs and activity bases for these activities: Activity Cost Activity Base Production setup $250,000 Number of setups Material handling 150,000 Number of parts General overhead 80,000 Number of direct labor hours Each product's total activity in each of...

  • Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places) Number of units produced Direct labor cost (@ $26 per DLH) Direct materials cost Product A 13,000 units 0.18 DLH per unit $ 2.40 per unit Product B 1,200 units 0.26 DLH per unit $ 2.70 per unit Activity Machine setup Materials handling Quality control...

  • Activity-Based Product Costing Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta,...

    Activity-Based Product Costing Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows: Activity Activity Cost Pool Production $259,200 Setup 55,000 Materials handling 9,750 Inspection 60,000 Product engineering 123,200 Total $507,150 The activity bases identified for each activity are as...

  • Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places) Number of units produced Direct labor cost (@ $24 per DLH) Direct materials cost Product A 11,500 units 0.20 DLH per unit $ 2.40 per unit Product B 1,500 units 0.27 DLH per unit $ 2.70 per unit Activity Machine setup Materials handling Quality control...

  • Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places.) Number of units produced Direct labor cost (@ $29 per DLH) Direct materials cost Product A 12,000 units 0.14 DLH per unit $ 1.80 per unit Product B 1,900 units 0.21 DLH per unit $ 2.30 per unit Activity Machine setup Materials handling Quality control...

  • Consider the following data for two products of Gitano Manufacturing (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places.) Number of units produced Direct labor cost 825 per DLH) Direct materials CONE Product 11.500 units 0.11 DLH per unit $ 1.90 per unit Product B 1.800 units 0.27 DLH per unit $ 2.30 per unit Activity Machine setup Materials handling Quality control inspections Overhead...

  • Consider the following data for two products of Gitano Manufacturing (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit answers to 2 decimal places.) Sumber of units produced Direct bor boat (625 per DLR) Direct materials cast 11,500 units 0.11 U per unit 1.800 units 0.27 D per unit 6 2.30 unit 6 9.625 Activity Machine setup Materials handling Quality control inspections 14,010 6148,835 Required: Answer is complete but...

  • Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your Intermediate calculations and "OH rate and cost per unlt" answers to 2 decimal places.) Product A Number of units produced 12,500 units Direct labor cost (@ $24 per DLH) 0.20 DLH per unit Direct materials cost $ 1.50 per unit Product B 1,400 units 0.23 DLH per unit $ 2.30 per unit Mat ne serctivit Machine setup Materials handling...

  • Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with...

    Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places.) Number of units produced Direct labor cost (@ $29 per DLH) Direct materials cost Product A 13,000 units 0.18 DLH per unit $ 1.60 per unit Product B 1,100 units 0.28 DLH per unit $ 2.30 per unit Activity Machine setup Materials handling Quality control...

  • HOW DO I CALCULATE? Consider the following data for two products of Gitano Manufacturing. (Loss amounts...

    HOW DO I CALCULATE? Consider the following data for two products of Gitano Manufacturing. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and "OH rate and cost per unit" answers to 2 decimal places.) Number of units produced Direct labor cost (@ $28 per DLH) Direct materials cost Product A 11,000 units 0.12 DLH per unit $ 1.60 per unit Product B 1,100 units 0.28 DLH per unit $ 2.90 per unit Activity Machine setup...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT