Eppich Corporation has provided the following data for the most recent month:
Raw materials, beginning balance | $ | 22,000 | |||||
Work in process, beginning balance | $ | 33,400 | |||||
Finished Goods, beginning balance | $ | 51,400 | |||||
Transactions:
(1) | Raw materials purchases | $ | 78,800 |
(2) | Raw materials used in production (all direct materials) | $ | 78,200 |
(3) | Direct labor | $ | 53,400 |
(4) | Manufacturing overhead costs incurred | $ | 94,000 |
(5) | Manufacturing overhead applied | $ | 73,400 |
(6) | Cost of units completed and transferred from Work in Process to Finished Goods |
$ | 190,000 |
(7) | Any overapplied or underapplied manufacturing overhead is closed to Cost of Goods Sold |
? | |
(8) | Finished goods are sold | $ | 222,600 |
Required:
Complete the following T-accounts by recording the beginning balances and each of the transactions listed above.
Eppich Corporation has provided the following data for the most recent month:
Raw materials, beginning balance | $ | 22,000 | |||||
Work in process, beginning balance | $ | 33,400 | |||||
Finished Goods, beginning balance | $ | 51,400 | |||||
Transactions:
(1) | Raw materials purchases | $ | 78,800 |
(2) | Raw materials used in production (all direct materials) | $ | 78,200 |
(3) | Direct labor | $ | 53,400 |
(4) | Manufacturing overhead costs incurred | $ | 94,000 |
(5) | Manufacturing overhead applied | $ | 73,400 |
(6) | Cost of units completed and transferred from Work in Process to Finished Goods |
$ | 190,000 |
(7) | Any overapplied or underapplied manufacturing overhead is closed to Cost of Goods Sold |
? | |
(8) | Finished goods are sold | $ | 222,600 |
Required:
Complete the following T-accounts by recording the beginning balances and each of the transactions listed above.
Raw materials | |||||
Beg bal | 22000 | work in process | 78200 | ||
Purchase | 78800 | end bal | 22600 | ||
100800 | 100800 | ||||
Work in process | |||||
beg bal | 33400 | finished goods | 190000 | ||
direct labor | 53400 | ||||
raw material | 78200 | ||||
manufacturing OH | 73400 | end bal | 48400 | ||
238400 | 238400 | ||||
Finished goods | |||||
beg bal | 51400 | cost of goods sold | 222600 | ||
work in process | 190000 | end bal | 18800 | ||
241400 | 241400 | ||||
Manufacturing overhead | |||||
cost ledger control acc | 94000 | work in process | 73400 | ||
(manufacturing oh incurred) | cost of goods sold | 20600 | |||
94000 | 94000 | ||||
Cost of goods sold | |||||
Finished goods | 222600 | costing profit/loss | 243200 | ||
manufacturing overhead | 20600 | ||||
243200 | 243200 |
Please give a thumbs up if it is helpful & let me know if any doubt
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $22,000 $33,400 $51,400 Transactions: (1) Raw materials purchases (2) Raw materials used in production (all direct materials) (3) Direct labor (4) Manufacturing overhead costs incurred (5 Manufacturing overhead applied (6) Cost of units completed and transferred from Work in Process to Finished Goods (7) Any overapplied or underapplied manufacturing overhead is closed to cost of...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $25,000 $34,600 $52,600 Transactions: 1:41:43 $ 78, 200 $ 78,800 $ 54,600 $ 97,000 $ 74,600 (1) Raw materials purchases (2) Raw materials used in production (all direct materials) (3) Direct labor (4) Manufacturing overhead costs incurred (5) Manufacturing overhead applied (6) Cost of units completed and transferred from Work in Process to Finished Goods...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance $ 19,000 Work in process, beginning balance $ 32,200 Finished Goods, beginning balance $ 50,200 Transactions: (1) Raw materials purchases $ 79,400 (2) Raw materials used in production (all direct materials) $ 77,600 (3) Direct labor $ 52,200 (4) Manufacturing overhead costs incurred $ 91,000 (5) Manufacturing overhead applied $ 72,200 (6) Cost of units completed and transferred from Work in Process to Finished...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $16,500 $31,200 $49,200 Transactions: (1) Raw materials purchases (2) Raw materials used in production (all direct materials) (3) Direct labor (4) Manufacturing overhead costs incurred (5) Manufacturing overhead applied (6) Cost of units completed and transferred from Work in Process to Finished Goods (7) Any overapplied or underapplied manufacturing overhead is closed to cost of...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $25,500 $34,800 $52,800 Transactions: (1) Raw materials purchases (2) Raw materials used in production (all direct materials) (3) Direct labor (4) Manufacturing overhead costs incurred (5) Manufacturing overhead applied (6) Cost of units completed and transferred from Work in Process to Finished Goods (7) Any overapplied or underapplied manufacturing overhead is closed to cost of...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $ 23, eee $33,800 $51,800 Transactions: (1) Raw materials purchases (2) Raw materials used in production (all direct materials) (3) Direct labor (4) Manufacturing overhead costs incurred (5) Manufacturing overhead applied (6) Cost of units completed and transferred from Work in Process to Finished Goods () Any overapplied or underapplied manufacturing overhead is closed to...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $ 23,009 $ 33,809 $ 51,800 Transactions: U R S R (1) Raw materials purchases (2) Raw materials used in production (all direct materials) (3) Direct labor (4) Manufacturing overhead costs incurred re (5) Manufacturing overhead applied (6) Cost of units completed and transferred fron Work in Process to Finished Goods (7) Any overapplied or...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $23,000 $33,800 $51,800 Transactions: (1) Raw materials purchases (2) Raw materials used in production (all direct materials) (3) Direct labor (4) Manufacturing overhead costs incurred (5) Manufacturing overhead applied (6) Cost of units completed and transferred from work in Process to Finished Goods (7) Any overapplied or underapplied manufacturing overhead is closed to cost of...
Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $18,500 $32,000 $50,000 Transactions: (1) Raw materials purchases $ 79,500 Raw materials used in production (all direct $ 77,500 17 materials) (3) Direct labor $ 52,000 (4) Manufacturing overhead costs incurred $ 98,500 (5) Manufacturing overhead applied $ 72,000 (6) Cost of units completed and transferred from Work in $190, Process to Finished Goods (7)...
please help! Eppich Corporation has provided the following data for the most recent month: Raw materials, beginning balance Work in process, beginning balance Finished Goods, beginning balance $23,500 $34,000 $52,000 Transactions: (1) Raw materials purchases (2) Raw materials used in production (all direct materials) (3) Direct labor (4) Manufacturing overhead costs incurred (5) Manufacturing overhead applied (6) Cost of units completed and transferred from Work in Process to Finished Goods (7) Any overapplied or underapplied manufacturing overhead is closed to...