If it is helpful, please rate the answer and if any doubt arises let me know
2021 | 2022 | ||||
Interest Capitalized | $ 1,79,352 | $ 3,35,131 | |||
Interest Expense | $ 12,44,648 | $ 10,88,869 | |||
Total cost of building | $ 86,89,483 | ||||
Workings: | |||||
Weighted Average rate of all debt:- | |||||
$ 30,00,000 | X | 10% | = | $ 3,00,000 | |
$ 59,00,000 | X | 7% | = | $ 4,13,000 | |
$ 79,00,000 | X | 9% | = | $ 7,11,000 | |
$ 1,68,00,000 | $ 14,24,000 | ||||
Weighted Average rate of all debt = | 8.48% | ||||
($1424000/ $16800000) | |||||
Expenditure for 2021 | |||||
Jan 1,2021 | $ 10,40,000 | X | 12/12 | = | $ 10,40,000 |
March 1, 2021 | $ 8,10,000 | X | 10/12 | = | $ 6,75,000 |
June 30, 2021 | $ 4,50,000 | X | 6/12 | = | $ 2,25,000 |
October 1, 2021 | $ 7,00,000 | X | 3/12 | = | $ 1,75,000 |
$ 30,00,000 | $ 21,15,000 | ||||
Interest Capitalized in 2021 | |||||
$ 21,15,000 | X | 8.48% | = | $ 1,79,352 | |
Expenditure for 2022 | |||||
Jan 1, 2022 ($3000000 + $179352) | $ 31,79,352 | X | 9/9 | = | $ 31,79,352 |
Jan 31, 2022 | $ 11,25,000 | X | 8/9 | = | $ 10,00,000 |
April 30, 2022 | $ 14,40,000 | X | 5/9 | = | $ 8,00,000 |
August 31. 2022 | $ 26,10,000 | X | 1/9 | = | $ 2,90,000 |
$ 83,54,352 | $ 52,69,352 | ||||
Interest Capitalized in 2022 | |||||
$ 52,69,352 | X | 8.48% | X 9/12 | = | $ 3,35,131 |
Cost of Building | |||||
Expenditure for 2021 | = | $ 30,00,000 | |||
Interest Capitalized in 2021 | = | $ 1,79,352 | |||
Expenditure for 2022 | = | $ 51,75,000 | |||
Interest Capitalized in 2022 | = | $ 3,35,131 | |||
Total cost of building | = | $ 86,89,483 | |||
Interest Expense for 2021: | |||||
Total Interest Incurred | = | $ 14,24,000 | |||
Less : Interest Capitalized | = | $ 1,79,352 | |||
2021 Expense | = | $ 12,44,648 | |||
Interest Expense for 2022: | |||||
Total Interest Incurred | = | $ 14,24,000 | |||
Less : Interest Capitalized | = | $ 3,35,131 | |||
2022 Expense | = | $ 10,88,869 |
Check my work On January 1, 2021, the company obtained a $3 million loan with a...
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,040,000 March 1, 2021 810,000 June 30, 2021 450,000 October 1, 2021 700,000 January 31, 2022 1,125,000 April 30, 2022 1,440,000 August 31, 2022 2,610,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows:January 1, 2021$1,040,000March 1, 2021810,000June 30, 2021450,000October 1, 2021700,000January 31, 20221,125,000April 30, 20221,440,000August 31, 20222,610,000On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3 million loan is not specifically tied to construction of the building. The loan was outstanding all...
On January 1, 2021, the company obtained a $3 million loan with a 11% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, $1,200,000 2021 March 1, 2021 660,000 June 30, 2021 520,000 October 1, 620,000 2021 January 31, 360,000 2022 April 30, 2022 675,000 August 31, 1,080,000 2022 On January 1, 2021, the company obtained a $3 million construction loan with a 11% interest rate. Assume the $3 million...
On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,300,000 720,000 340,000 640,000 450.000 765,000 1,260,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest rate. Assume the $3 million...
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,200,000 March 1, 2021 690,000 June 30, 2021 450,000 October 1, 2021 660,000 January 31, 2022 945,000 April 30, 2022 1,260,000 August 31, 2022 2,250,000 On January 1, 2021, the company obtained a $3 million construction loan with a 12% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 $1,200,000 690,000 450,000 660,000 945,000 1,260,000 2,250,000 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 On January 1, 2021, the company obtained a $3 million construction loan with a 12% interest rate. Assume the $3 million...
Attach the calculation process thank you On January 1, 2021, the company obtained a $3 million loan with a 10% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,300,000 750,000 300,000 650,000 495,000 810,000 1,350,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10%...
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,050,000 630,000 710,000 610,000 315,000 630,000 990,000 On January 1, 2021, the company obtained a $3 million construction loan with a 12% interest rate. Assume the $3 million...
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,200,000 March 1, 2021 690,000 June 30, 2021 450,000 October 1, 2021 660,000 January 31, 2022 945,000 April 30, 2022 1,260,000 August 31, 2022 2,250,000 On January 1, 2021, the company obtained a $3 million construction loan with a 12% interest rate. Assume the $3...
On January 1, 2021, the company obtained a $3 million loan with a 12% interest rate. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,170,000 March 1, 2021 990,000 June 30, 2021 110,000 October 1, 2021 730,000 January 31, 2022 855,000 April 30, 2022 1,170,000 August 31, 2022 2,070,000 On January 1, 2021, the company obtained a $3 million construction loan with a 12% interest rate. Assume the $3...