Question

February 1, 2018, Salisbury Company purchased land for the future factory loca at a cost of $117,000. The dilapidated buildin

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost of land = Cost + Demolition cost + legal fees

= $117000 + $2400 + $1750

= $121150

Add a comment
Know the answer?
Add Answer to:
February 1, 2018, Salisbury Company purchased land for the future factory loca at a cost of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. February 1, 2018, Salisbury Company purchased land for the future factory location at a cost...

    1. February 1, 2018, Salisbury Company purchased land for the future factory location at a cost of $102,000.  The dilapidated building that was on the property was demolished so that construction could begin on the new factory building. The new factory was completed on November 1, 2018. Costs incurred during this period were: Item Amount Demolition dilapidated building $2,000 Architect Fees $11,250 Legal Fees - for title search $1,400 Interest During Active Construction Period $5,025 Real estate transfer tax $1,050 Construction...

  • On February 1, 2013, Edwards Corporation purchased a parcel of land as a factory site for...

    On February 1, 2013, Edwards Corporation purchased a parcel of land as a factory site for $250,000. It demolished an old building on the property and began construction on a new building that was completed on October 2, 2013. Edwards has no debt. Costs incurred during this period were: Demolition of old building $6,000 Sale of salvaged materials from the demolition 1,000 Architects’ fees 12,000 Legal fees for land purchase 2,000 Construction costs 600,000 Required: At what amount should Edwards...

  • On February 1, 2020, Sheridan Company purchased a parcel of land as a factory site for...

    On February 1, 2020, Sheridan Company purchased a parcel of land as a factory site for $324000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 19300 Architect's fees 35700 Legal fees for title investigation and purchase contract 4100 Construction costs 1387000 (Salvaged materials resulting from demolition were sold for $10300.) Sheridan should record...

  • Exercise 10-1 Acquisition costs; land and building [LO10-1] On March 1, 2018, Beldon Corporation purchased land...

    Exercise 10-1 Acquisition costs; land and building [LO10-1] On March 1, 2018, Beldon Corporation purchased land as a factory site for $73,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,500 Architect’s fees (for new building) 12,000 Legal fees for title investigation of land 2,000 Property taxes on land (for period beginning March...

  • 1. Bowie Company made a lump sum purchase of land, building, and equipment. The following were...

    1. Bowie Company made a lump sum purchase of land, building, and equipment. The following were the appraised values of each element: PP&E Element Amount Land $10,000 Building 25,000 Equipment 45,000 Bowie paid $70,000 cash for the lump sum purchase. What value should be allocated to the building? (Enter only whole dollar values.) 2. Cambridge Company purchased a truck on January 1, 2018. Cambridge paid $22,000 for the truck. The truck is expected to have a $2,500 residual value and...

  • 1. Bowie Company made a lump sum purchase of land, building, and equipment. The following were the appraised values of e...

    1. Bowie Company made a lump sum purchase of land, building, and equipment. The following were the appraised values of each element: PP&E Element Amount Land $10,000 Building 25,000 Equipment 45,000 Bowie paid $70,000 cash for the lump sum purchase. What value should be allocated to the building? (Enter only whole dollar values.) 2. Cambridge Company purchased a truck on January 1, 2018. Cambridge paid $22,000 for the truck. The truck is expected to have a $2,500 residual value and...

  • On March 1, 2021, Beldon Corporation purchased land as a factory site for $71,000. An old...

    On March 1, 2021, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2021) 4,100 Construction costs 610,000 Interest on...

  • On March 1, 2021, Beldon Corporation purchased land as a factory site for $76,000. An old...

    On March 1, 2021, Beldon Corporation purchased land as a factory site for $76,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building $ 7,000 Architect’s fees (for new building) 15,000 Legal fees for title investigation of land 3,500 Property taxes on land (for period beginning March 1, 2021) 4,600 Construction costs 660,000 Interest on...

  • Online Assignment #1: Determine the acquisition cost of land and building P7-1A The Italian Bread Company...

    Online Assignment #1: Determine the acquisition cost of land and building P7-1A The Italian Bread Company purchased land as a factory site for $70,000. An old building on the . property was demolished, and construction began on a new building. Costs incurred during the first year are listed as follows: Demolition of old building Sale of salvaged materials Architect fees (for new building) Legal fees (for title investigation of land) Property taxes on the land (for the first year) Building...

  • On March 1, 2021, Beldon Corporation purchased land as a factory site for $63,000. An old...

    On March 1, 2021, Beldon Corporation purchased land as a factory site for $63,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building Architect's fees (for new building) Legal fees for title investigation of land Property taxes on land (for period beginning March 1, 2021) Construction costs Interest on construction loan $ 5,500 15,000 3,500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT