Question

Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers:...

Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers: Overhead Costs Pool Cost Driver Overhead Cost Budgeted Level for Cost Driver Budgeted Quality control # of inspections $ 79,200 800 Machine time Machine hours 264,320 826 Materials handling # of Batches 14,850 135 Miscellaneous overhead cost Direct labor hours 67,000 7,300 Diamond Cleats Co. has an order for cleats that has the following production requirements: Number of inspections 630 Number of machine hours 390 Number of batches 6 Direct labor hours 1,560 Using activity-based costing, applied machine overhead for the baseball cleat order is: Multiple Choice

$47,200.

$54,700.

$39,900.

$58,550.

$124,800.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct answer-----------$124,800

Working

Calculation of Activity rates
Activity Cost Pool Activity driver Overhead Cost (A) Expected Activity (B) Activity rate (A/B)
Machine time Number of machine hour $ 264,320 826 $          320.00 Per machine hour

.

Cost assigned to Baseball
Activity name Activity Rates Activity ABC Cost
(A) (B) (A x B)
Machine time $        320.00                      390.00 $ 124800.00
Add a comment
Know the answer?
Add Answer to:
Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers:...

    Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers: Overhead Costs Pool Cost Driver Overhead Cost Budgeted Level for Cost Driver Budgeted Quality control # of inspections $ 87,100 1,300 Machine time Machine hours 255,120 1,063 Materials handling # of Batches 1,650 55 Miscellaneous overhead cost Direct labor hours 64,000 6,700 Diamond Cleats Co. has an order for cleats that has the following production requirements: Number of inspections 390 Number of machine hours...

  • Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers:...

    Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers: Overhead Costs Pool Cost Driver Overhead Cost Budgeted Level for Cost Driver Budgeted Quality control # of inspections $ 87,100 1,300 Machine time Machine hours 255,120 1,063 Materials handling # of Batches 1,650 55 Miscellaneous overhead cost Direct labor hours 64,000 6,700 Diamond Cleats Co. has an order for cleats that has the following production requirements: Number of inspections 390 Number of machine hours...

  • Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers:...

    Diamond Cleats Co. manufactures cleats for baseball shoes. It has outlined the following overhead cost drivers: Overhead Costs Pool Cost Driver Overhead Cost Budgeted Level for Cost Driver Budgeted Quality control # of inspections $ 51,100 700 Machine time Machine hours 153,765 603 Materials handling # of Batches 3,150 70 Miscellaneous overhead cost Direct labor hours 63,000 6,400 Diamond Cleats Co. has an order for cleats that has the following production requirements: Number of inspections 435 Number of machine hours...

  • Sheen Co. manufacturers laser printers. It has outlined the following overhead cost drivers: Overhead Costs Pool...

    Sheen Co. manufacturers laser printers. It has outlined the following overhead cost drivers: Overhead Costs Pool Cost Driver Overhead Cost Budgeted Level for Cost Driver Quality control Number of inspections $ 66,000 1,100 Machine operation Machine hours 141,000 1,500 Materials handling Number of batches 1,500 30 Miscellaneous overhead cost Direct labor hours 51,000 5,100 Sheen Co. has an order for 1,000 laser printers that has the following production requirements: Number of inspections 195 Machine hours 190 Number of batches 5...

  • Sheen Co. manufacturers laser printers. It has outlined the following overhead cost drivers: Overhead Costs Pool...

    Sheen Co. manufacturers laser printers. It has outlined the following overhead cost drivers: Overhead Costs Pool Cost Driver Overhead Cost Budgeted Level for Cost Driver Quality control Number of inspections $ 73,000 1,000 Machine operation Machine hours 149,000 1,000 Materials handling Number of batches 1,800 40 Miscellaneous overhead cost Direct labor hours 56,000 5,600 Sheen Co. has an order for 1,000 laser printers that has the following production requirements: Number of inspections 255 Machine hours 220 Number of batches 6...

  • Soved Help Save Sheen Co. manufacturers laser printers. It has outlined the following overhead cost drivers:...

    Soved Help Save Sheen Co. manufacturers laser printers. It has outlined the following overhead cost drivers: Overhead Costs Pool Quality control Machine operation Materials handling Miscellaneous overhead cost Cost Driver Number of inspections Machine hours Number of batches Direct labor hours Overhead Cost $ 80,000 180,000 1,200 63,000 Budgeted Level for Cost Driver 1,600 1,500 30 6,300 Sheen Co. has an order for 1,000 laser printers that has the following production requirements: Number of inspections Machine hours Number of batches...

  • 51.47 is the 5th option Sheen Co. manufacturers laser printers. It has outlined the following overhead...

    51.47 is the 5th option Sheen Co. manufacturers laser printers. It has outlined the following overhead cost drivers: Overhead Costs Pool Quality control Machine operation Materials handling Miscellaneous overhead cost Cost Driver Number of inspections Machine hours Number of batches Direct labor hours Overhead Cost $ 90,000 156,000 1,200 64,000 Budgeted Level for Cost Driver 1,500 1,500 40 4,000 Sheen Co. has an order for 1,000 laser printers that has the following production requirements: 200 Number of inspections Machine hours...

  • Wings Co. budgeted $555,600 manufacturing direct wages, 2,315 direct labor hours, and had the following manufacturing...

    Wings Co. budgeted $555,600 manufacturing direct wages, 2,315 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Budgeted Overhead Cost Budgeted Level for Cost Driver Overhead Cost Driver Materials handling $ 160,000 3,200 pounds Weight of materials Machine setup 13,260 390 setups Number of setups Machine repair 1,380 30,000 machine hours Machine hours Inspections 10,560 160 inspections Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor 20 hours Direct materials 130...

  • Wings Co. budgeted $556,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing...

    Wings Co. budgeted $556,000 manufacturing direct wages, 2,500 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Materials handling Machine setup Machine repair Inspections Budgeted Overhead Cost $198,000 14,888 1,800 10,200 Budgeted Level for Cost Driver 3,300 pounds 400 setups 30,000 machine hours 17e inspections Overhead Cost Driver Weight of materials Number of setups Machine hours Number of inspections Requirements for Job #971 which manufactured 4 units of product: Direct labor Direct materials Machine setup Machine hours...

  • A company has identified the following overhead costs and cost drivers for the coming year: (CIA...

    A company has identified the following overhead costs and cost drivers for the coming year: (CIA adapted) Overhead Item Machine setup Inspection Material handling Engineering Cost Driver Budgeted Cost Number of setups $ 20,000 Number of inspections 130,000 Number of material moves 80,000 Engineering hours 50,000 Budgeted Activity Level 200 6,500 8,000 1,000 Budgeted direct labor cost was $100,000 and budgeted direct material cost was $280,000. The following Information was collected on three jobs that were completed during the year:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT