Question

1) The Department Of Transportation of a Municipality is planning to construct an additional bridge to speed up evacuation in
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q1 Heu, we will us the concept of a present value of cart Annetty Fanula to evaluate which solution the department should choSo, in case - (ü) there is less net present value I cost, So Cantine lower bridge will be the better option to opt.

Add a comment
Know the answer?
Add Answer to:
1) The Department Of Transportation of a Municipality is planning to construct an additional bridge to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • BOY 1) The Department of Transportation of a Municipality is planning to construct an additional bridge to speed up eva...

    BOY 1) The Department of Transportation of a Municipality is planning to construct an additional bridge to speed up evacuation in case of an emergency. Two solutions are considered, both with a 50 years life span: Suspension Bridge 600 120 2.5 Cantilever Bridge 550 100 Construction Cost Land Acquisition Annual O&M Annual O&M increase Major Maintenance (at 25 yrs) Decommissioning cost 0.4 0.3 210 190 25 30 (NOTE: all costs are in Million $) The Department uses an interest rate...

  • In order to improve evacuation routes out of New Orleans in the event of another major...

    In order to improve evacuation routes out of New Orleans in the event of another major disaster such as Hurricane Katrina, the Louisiana Department of Transportation (L-DoT) is planning to construct an additional bridge across the Mississippi River. The department uses an interest rate of 8% and plans a 50-year life for either bridge. Which design has the better present worth? All costs in $M Land acquisition Annual O & M Annual increase Major Maintenance (Year 25 Salvage Cost nitial...

  • Problems 25 through 29 are based on the following information: The Transportation Authority is planning to...

    Problems 25 through 29 are based on the following information: The Transportation Authority is planning to build a new bridge. Since only part of the capacity will be required for the next 20 years, an alternative to building the full capacity now is to build the bridge on two stages. MARR is 8%. Estimated costs are as follows: Construction Rehabilitation Cost Annual Costs Every 10 years Maintenance Cost Build in two stages: Stage 1 (Building half-capacity now) $12M $1 M...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT