Question

Required: 1. Using the companys plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Det
Complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 2B Required 4
Required: 1. Using the companys plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Det
Complete this question by entering your answers in the tabs below. Required 1A Required 13 Required 2A Required 28 Required 4
Complete this question by entering your answers in the tabs below. Required 1A Required 18 Required 2A Required 2B Required 4
b.What would the bid price have been If departmental predetermined overhead rates had been used to apply overhead cost? Compl

the first pic is the information for the 6 required things to find
2 Pre-Built Problems Saved He Blast it! said David Wilson, president of Teledex Company. Weve just lost the bid on the Ko
Che Department Fabricating Machining $385.000 $ 40,000 $220.000 110.000 Assembly total plant $ 99.0005 924.000 330,000 60,000
Manufacturing overhead Direct labor Department Fabricating Machining $385,000 $400,000 $ 220,000 110,000 Assembly $ 99,000 $
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturin
ter 02 Pre-Built Problems Jobs require varying amounts of work in the three departments. The Koopers job, for example, would
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturin
O2 Pre-Bullt Problems Saved Help Jobs require varying amounts of work in the three departments. The Koopers job, for example,
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1A. . Plant-wide predetermined overhead rate = $ 924,000 / $ 660,000 = 1.40 or 140 % of direct labor cost.

1B. Manufacturing overhead applied to Kooper's job = $ 15,600 x 140 % = $ 21,840

2A.

Fabricating Machining Assembly
Manufacturing Overhead $ 385,000 $ 440,000 $ 99,000
Direct Labor 220,000 110,000 330,000
Departmental Predetermined Overhead Rate 175 % 400 % 30 %

2B.

Department Direct Labor Cost on Kooper Job Departmental Predetermined Overhead Rate Overhead Assigned
Fabrication $ 6,800 175 % $ 11,900
Machining 600 400 % 2,400
Assembly 8,200 30 % 2,460
Total Overhead Assiigned $ 16,760

4.A.

Direct materials $ 8,700
Direct labor 15,600
Overhead applied 21,840
Total manufacturing costs 46,140
Bid Price on Kooper's job ( 46,140 x 150 % ) $ 69,210

4B.

Direct materials $ 8,700
Direct labor 15,600
Overhead applied 16,760
Total Manufacturing Costs 41,060
Bid Price on Kooper's job ( 41,060 x 150 % ) 61,590
Add a comment
Know the answer?
Add Answer to:
the first pic is the information for the 6 required things to find Required: 1. Using...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Department Fabricating Machining Assembly Total Plant Manufacturing overhead Direct labor 379,750 434,000 97,650 $ 911,4co s...

    Department Fabricating Machining Assembly Total Plant Manufacturing overhead Direct labor 379,750 434,000 97,650 $ 911,4co s 217,000 108,s00 325,500 651,000 Jobs require varying amounts of work in the three departments. he Koopers job,for example, would have required manu costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Fabricating 4,700 6,200 hining 300 600 Assembly $3,100 7,900 Total Plant 8,100 $14,700 Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current...

  • if you can please answer questions 1-4 including the A & B sections that woukd be...

    if you can please answer questions 1-4 including the A & B sections that woukd be great! Thank you very much! "Blast It" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • All one problem, 6 parts. THANK YOU!! "Blast it!" said David Wilson, president of Teledex Company,...

    All one problem, 6 parts. THANK YOU!! "Blast it!" said David Wilson, president of Teledex Company, "We've just lost the bid on the Koopers job by $4,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $4,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

  • "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the...

    "Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT