1. Material Price Variance = (Standard price- Actual Price)* Actual quantity used
= (4-4.40) * 17500*1.85
= - 12950
2. Material Quantity variance= (Standard quantity used - Actual quantity used) * Standard rate
= (1.85*17500 - 1.90*17500) * 4
=(32375 - 33250 ) *4
= - 3500
3. Labor rate variance = (Standard Rate - Actual Rate) * Actual hours
= (16 - 15.40) * 1.15*17500
= 12075
4. Labor efficiency variance= (Standard hours to be used- Actual hours used) * Standard Rate
= (1.10*17500 - 1.15*17500) *16
= (19250 - 20125)*16 = -14000
Help please. Problem 9-20 Basic Variance Analysis; the Impact of Variances on Unit Costs (LO9-4, LO9-5,...
Problem 9-20 Basic Variance Analysis; the Impact of Variances on Unit Costs [LO9-4, LO9-5, LO9-6] Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit Direct materials: Standard: 1.90 feet at $3.40 per foot $ 6.46 Actual: 1.85 feet at $3.80 per foot $ 7.03 Direct labor: Standard: 0.95 hours at $20.00 per hour 19.00 Actual: 1.00...
Problem 9-20 Basic Variance Analysis; the Impact of Variances on Unit Costs Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit Direct materials: Standard: 1.80 feet at $2.80 per foot $ 5.04 Actual: 1.75 feet at $3.00 per foot $ 5.25 Direct labor: Standard: 0.90 hours at $17.00 per hour 15.30 Actual: 0.95 hours at $16.40...
Problem 10-13 (Algo) Basic Variance Analysis; the Impact of Variances on Unit Costs [LO10-1, LO10-2, LO10-3] Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit $ 3.24 $ 3.85 17.10 Direct materials: Standard: 1.80 feet at $1.80 per foot Actual: 1.75 feet at $2.20 per foot Direct labor: Standard: 0.90 hours at $19.00 per hour Actual:...
Problem 10-13 (Algo) Basic Variance Analysis: the Impact of Variances on Unit Costs [LO10-1, LO10-2, LO10-3] Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May Standard Cost per Unit Actual Cost per Unit S 3.24 $ 3.85 17.10 Direct materials: Standard: 1.80 feet at $1.80 per foot Actual: 1.75 feet at $2.20 per foot Direct labor: Standard: 0.90 hours at $19.00 per hour Actual:...
Problem 10-13 (Algo) Basic Variance Analysis; the Impact of Variances on Unit Costs (LO10-1, LO10-2. LO10-3) points Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit $ 2.52 References $ 3.15 15.30 Direet materias: Standard: 1.80 feet at $1.40 per foot Actual 1.75 feet at $1.80 per foot Direct labor Standard: 0.90 hours at $17.00 per...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit $ 7.60 $ 8.14 17.60 17.71 Direct materials: Standard: 1.90 feet at $4.00 per foot Actual: 1.85 feet at $4.40 per foot Direct labor: Standard: 1.10 hours at $16.00 per hour Actual: 1.15 hours at $15.40 per hour Variable overhead: Standard: 1.10 hours at $9.00 per hour...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit Direct materials: Standard: 1.90 feet at $4.00 per foot $ 7.60 Actual: 1.85 feet at $4.40 per foot $ 8.14 Direct labor: Standard: 1.10 hours at $16.00 per hour 17.60 Actual: 1.15 hours at $15.40 per hour 17.71 Variable overhead: Standard: 1.10 hours at $9.00 per hour...
need help with this question. correct answers please feel free to take your time. please help thanks:) Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May Standard Cost per Actual Cost per Unit Unit Direct materials: standard: 1.90 feet at $4.80 per foot Actual: 1.85 feet at $5.20 per foot 9.12 $9.62 Direct labor: standard: 1.45 hours at $20.00 per hour Actual: 1.50 hours...
0 Saved Help Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per $ 4.20 12.60 Direct materials: Standard: 1.80 feet at $2.20 per foot Actual 1.75 feet at $2.40 per foot Direct labor! Standard: 0.90 hours at $14.00 per hour Actualı 0.95 hours at $13.40 per hour Variable overhead: Standard: 0.90 hours at $5.00 per hour Actualt...
Standard Cost per Unit Actual Cost per Unit $ 3.96 $ 4.20 12.60 Direct materials: Standard: 1.80 feet at $2.20 per foot Actual: 1.75 feet at $2.40 per foot Direct labor: Standard: 0.90 hours at $14.00 per hour Actual: 0.95 hours at $13.40 per hour Variable overhead: Standard: 0.90 hours at $5.00 per hour Actual: 0.95 hours at $4.60 per hour Total cost per unit Excess of actual cost over standard cost per unit 12.73 4.50 4.37 $ 21.30 $21.06...