Incorrect Question 4 0/1 pts A wastewater treatment plant is planing on updated over the next 10 years. It costs the plant $3
0 0
Add a comment Improve this question Transcribed image text
Answer #1

EUAC = 300000 - 30000 * (A/G, 8%,10)

= 300000 - 30000 * 3.871314

= 183860.58 ~ 183861

Add a comment
Know the answer?
Add Answer to:
Incorrect Question 4 0/1 pts A wastewater treatment plant is planing on updated over the next...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A wastewater treatment plant is planing on updated over the next 10 years. There is not...

    A wastewater treatment plant is planing on updated over the next 10 years. There is not initial cost. It costs the plant $300,000 for the first year of treatment. The cost of treatment is expected to decrease $30,000 each year at an interest rate of 8% per year . Using annual cash flow analysis what is the annual cost? 416,139 Treat the $300,000 as an A value and cor $30,000 using (A/G)

  • A major city in Eastern Canada is planning to build a new wastewater treatment plant to...

    A major city in Eastern Canada is planning to build a new wastewater treatment plant to accommodate the increasing water consumption of the city, Plant construction will start in 2018 and is going to take five years at a cost of $30 million per year. After construction is completed, the cost of operation, maintenance is expected to be $2 million for the first year, and to increase by 1% per year thereafter. The salvage/scrap value of the wastewater treatment plant...

  • .A city government is considering increasing the capacity of the current wastewater treatment plant. The estimated...

    .A city government is considering increasing the capacity of the current wastewater treatment plant. The estimated financial data for the project are as follows: Description Cash flow Capital investment $1,500,000 Project life 25 years Incremental annual benefits $180,000 Incremental annual costs $75,000 Salvage value $35,000 Discount rate 6% Calculate the benefit-cost ratio for this capacity expansion project.

  • 3. A wastewater treatment plant adds $700,000 to the cost of a computer chip manufacturing facility...

    3. A wastewater treatment plant adds $700,000 to the cost of a computer chip manufacturing facility interest rate is 4%, and the end-of-life scrap value is $40,000? (6 points) due to capital expenditure for wastewater treatment? (3 points) a) What is the annualized capital cost (U) of this plant if its lifetime is 15 years, the b) If the facility manufactures 1 million chips per year, what is the added cost per chip

  • 3. A wastewater treatment plant adds $700,000 to the cost of a computer chip manufacturing facility...

    3. A wastewater treatment plant adds $700,000 to the cost of a computer chip manufacturing facility interest rate is 4%, and the end-of-life scrap value is $40,000? (6 points) due to capital expenditure for wastewater treatment? (3 points) a) What is the annualized capital cost (U) of this plant if its lifetime is 15 years, the b) If the facility manufactures 1 million chips per year, what is the added cost per chip

  • West Lafayette is spending $28 million on upgrades to the existing wastewater treatment plant with the...

    West Lafayette is spending $28 million on upgrades to the existing wastewater treatment plant with the addition of tertiary UV treatment. The expected life of this new treatment phase is expected to last 60 years, and it will have a market value of $5 million at the end of its useful lifetime. Operating and maintenance expenses for the tertiary treatment system are projected to be $2.2 million per year. If the city’s MARR is 6% per year, what is the...

  • 7. A water treatment plant has a remaining service life of 15 years. It costs $675,000...

    7. A water treatment plant has a remaining service life of 15 years. It costs $675,000 per year to operate and maintain the facility. The O&M costs are expected to stay constant for the first three years and then begin to increase by 0.5% a year for the next 12 years. What is the present worth of the facility if the nominal interest rate is 6%? (Hint: Draw the cash flow diagram for clarity)

  • 2. (40 pts) A wastewater treatment plant has an activated sludge system. The aeration tank is...

    2. (40 pts) A wastewater treatment plant has an activated sludge system. The aeration tank is 252 ft long, 25 ft wide, and 18 ft deep. An engineer will model the steady-state performance as first order (k= 8.3 d ?) as a series of 9 equal-volume CFSTRs. The flow rate is 3.1 MGD and the influent BODS is 165 mg/L. a) If the engineer's model is correct, what is the outlet BOD5 concentration (mg/L)? b) If the model is correct,...

  • NT4-1. 3 pts. A beef stick manufacturing plant proposed to discharge saline (salty) wastewater to a...

    NT4-1. 3 pts. A beef stick manufacturing plant proposed to discharge saline (salty) wastewater to a river. Upon reviewing the proposal, the governing regulatory agency set a 200 mg/L salt maximum level in the river downstream of the discharge point. In response the manufacturing plant proposed adding desalination equipment between the manufacturing plant and the river to remove enough salt from the wastewater to meet the regulatory requirement, 15% of the wastewater flow becomes brine (concentrated salt), a byproduct from...

  • Incorrect Incorrect Question 4 0/5 pts 0/ Shell is experiencing rapid growth. Earnings and dividends are...

    Incorrect Incorrect Question 4 0/5 pts 0/ Shell is experiencing rapid growth. Earnings and dividends are expected to grow at a rate of 15% during the next 2 years, at 13% the following year, and at a constant rate of 6% during Year 4 and thereafter. Its last dividend was $1.15, and its required rate of return is 12%. b) Find the PV of the firm's stock price at the end of Year 3. 30.36

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT