Question

Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.30 pounds. Materials cost $ 2 per pound but Stefani always takes the 4.00 % cash discount all of its suppliers offer. Freight costs average $ 0.45 per pound. Direct labor. Each unit requires 1.30 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly pay rate of Stefanis employees is12.50.Payroll taxes and fringe benefits are an additional $ 2.40 per hour Manufacturing overhead. Overhead is applied at a rate of $ 7.20 per direct labor hour Compute Stefanis total standard cost per unit. (Round intermediate calculations and final answer to 2 decimal places, e.g. 1.25.) Total standard cost per unit s

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Total standard cost per unit includes direct material cost, direct labor cost and manufacturing overhead. Normal waste and spoilage is also part of standard cost of the product.

Standard cost per unit Direct materials: Pounds/hour Price/rateCost Direct Material cost: Material Normal waste & spoilage Freight cost (3.10 0.30 pounds) 3.10 1.92 5.95 0.301.92 0.58 3.40 0.45 1.53 Direct labor cost: Direct labor Setup, cleanup & downtime Payroll taxes & fring benefits (1.30+0.20 hours) 1.30 $12.50$ 16.25 0.20 12.50 2.50 1.50 S 2.403.60 Manufacturing overhead (1.30 0.20 hours) Total standard cost per unit 1.50 7.20$ 10.80 41.21 Rate-$ 2 * 96% (100%-4% discount)

Add a comment
Know the answer?
Add Answer to:
Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 11-3 (Video) Stefani Company has gathered the following information about its product. Direct materials: Each...

    Exercise 11-3 (Video) Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.90 pounds. Materials cost $2 per pound, but Stefani always takes the 4.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 1.30 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit....

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.90 pounds. Materials cost $2 per pound, but Stefani always takes the 4.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 1.30 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.10 pounds. Materials cost $1 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.30 per pound. Direct labor. Each unit requires 1.60 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.10 pounds. Materials cost $1 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.30 per pound. Direct labor. Each unit requires 1.60 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contai...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.10 pounds. Materials cost $1 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.30 per pound. Direct labor. Each unit requires 1.60 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.90 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 1.10 pounds. Materials cost $2 per pound, but Stefani always takes the 1.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 2.60 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

  • Exercise 23-3 Stefani Company has gathered the following information about its product. Direct materials: Each unit...

    Exercise 23-3 Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.70 pounds. Materials cost $5 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 2.40 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.20 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.80 pounds. Materials cost $1 per pound, but Stefani always takes the 1.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 1.00 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.40 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.60 pounds. Materials cost $2 per pound, but Stefani always takes the 2.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 1.00 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 4.20 pounds of materials. The average waste under normal conditions is 0.80 pounds Materials cost $ pound but Stefani always takes the 2.00 % cash discount all of its suppliers $0.45 per pound. Direct labor. Each unit requires 1.60 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly pay rate of Stefani's employees is $12.30. Payroll taxes...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT