Land | Building | |
Land | 600000 | |
Razing Costs | 63000 | |
Less: Salvage | (9450) | |
Legal Fees | 2775 | |
Survey | 3300 | |
Plans | 102000 | |
Title Insurance | 2250 | |
Liability Insurance | 1350 | |
Construction | 4110000 | |
Interest | 255000 | |
Total cost | $658,575 | $4,471,650 |
Sweet Co. purchased land as a factory site for $600,000. The process of tearing down two...
Sarasota Co. purchased land as a factory site for $600,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $63,000 to raze the old buildings and sold salvaged lumber and brick for $9,450. Legal fees of $2,775 were paid for title investigation and drawing the purchase contract.Sarasota paid $3,300 to an engineering firm for a land survey, and $102,000 for drawing the factory plans. The land survey had...
Culver Co. purchased land as a factory site for $600,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $63,000 to raze the old buildings and sold salvaged lumber and brick for $9,450. Legal fees of $2,775 were paid for title investigation and drawing the purchase contract. Culver paid $3,300 to an engineering firm for a land survey, and $102,000 for drawing the factory plans. The land survey...
Bonita Co. purchased land as a factory site for $512,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $53,760 to raze the old buildings and sold salvaged lumber and brick for $8,064. Legal fees of $2,368 were paid for title Investigation and drawing the purchase contract. Bonita paid $2,816 to an engineering form for a land survey, and $87,040 for drawing the factory plans. The land survey...
Cheyenne Co. purchased land as a factory site for $456,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $47,880 to raze the old buildings and sold salvaged lumber and brick for $7,182. Legal fees of $2,109 were paid for title investigation and drawing the purchase contract. Cheyenne paid $2,508 to an engineering firm for a land survey, and $77,520 for drawing the factory plans. The land survey...
Coronado Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $51,240 to raze the old buildings and sold salvaged lumber and brick for $7,686. Legal fees of $2,257 were paid for title investigation and drawing the purchase contract. Coronado paid $2,684 to an engineering firm for a land survey, and $82,960 for drawing the factory plans. The land survey...
Shamrock Co. purchased land as a factory site for $432,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $45,360 to raze the old buildings and sold salvaged lumber and brick for $6,804. Legal fees of $1.998 were paid for title investigation and drawing the purchase contract. Shamrock paid $2,376 to an engineering firm for a land survey, and $73.440 for drawing the factory plans. The land survey...
Flounder Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $51,240 to raze the old buildings and sold salvaged lumber and brick for $7,686. Legal fees of $2,257 were paid for title investigation and drawing the purchase contract. Flounder paid $2,684 to an engineering firm for a land survey, and $82,960 for drawing the factory plans. The land survey...
Oriole Co. purchased land as a factory site for $408,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $42,840 to raze the old buildings and sold salvaged lumber and brick for $6,426. Legal fees of $1,887 were paid for title investigation and drawing the purchase contract. Oriole paid $2,244 to an engineering firm for a land survey, and $69,360 for drawing the factory plans. The land survey...
Larkspur Co. purchased land as a factory site for $568,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $59,640 to raze the old buildings and sold salvaged lumber and brick for $8,946. Legal fees of $2,627 were paid for title investigation and drawing the purchase contract. Larkspur paid $3,124 to an engineering firm for a land survey, and $96,560 for drawing the factory plans. The land survey...
Teal Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $51,240 to raze the old buildings and sold salvaged lumber and brick for $7,686. Legal fees of $2,257 were paid for title investigation and drawing the purchase contract. Teal paid $2,684 to an engineering firm for a land survey, and $82,960 for drawing the factory plans. The land survey...