Sweet Co. purchased land as a factory site for $600,000. The process of tearing down two old buildings on the site and constr

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Land Building
Land 600000
Razing Costs 63000
Less: Salvage (9450)
Legal Fees 2775
Survey 3300
Plans 102000
Title Insurance 2250
Liability Insurance 1350
Construction 4110000
Interest 255000
Total cost $658,575 $4,471,650
Add a comment
Know the answer?
Add Answer to:
Sweet Co. purchased land as a factory site for $600,000. The process of tearing down two...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sarasota Co. purchased land as a factory site for $600,000. The process of tearing down two...

    Sarasota Co. purchased land as a factory site for $600,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $63,000 to raze the old buildings and sold salvaged lumber and brick for $9,450. Legal fees of $2,775 were paid for title investigation and drawing the purchase contract.Sarasota paid $3,300 to an engineering firm for a land survey, and $102,000 for drawing the factory plans. The land survey had...

  • Culver Co. purchased land as a factory site for $600,000. The process of tearing down two...

    Culver Co. purchased land as a factory site for $600,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $63,000 to raze the old buildings and sold salvaged lumber and brick for $9,450. Legal fees of $2,775 were paid for title investigation and drawing the purchase contract. Culver paid $3,300 to an engineering firm for a land survey, and $102,000 for drawing the factory plans. The land survey...

  • Bonita Co. purchased land as a factory site for $512,000. The process of tearing down two...

    Bonita Co. purchased land as a factory site for $512,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $53,760 to raze the old buildings and sold salvaged lumber and brick for $8,064. Legal fees of $2,368 were paid for title Investigation and drawing the purchase contract. Bonita paid $2,816 to an engineering form for a land survey, and $87,040 for drawing the factory plans. The land survey...

  • Cheyenne Co. purchased land as a factory site for $456,000. The process of tearing down two...

    Cheyenne Co. purchased land as a factory site for $456,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $47,880 to raze the old buildings and sold salvaged lumber and brick for $7,182. Legal fees of $2,109 were paid for title investigation and drawing the purchase contract. Cheyenne paid $2,508 to an engineering firm for a land survey, and $77,520 for drawing the factory plans. The land survey...

  • Coronado Co. purchased land as a factory site for $488,000. The process of tearing down two...

    Coronado Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $51,240 to raze the old buildings and sold salvaged lumber and brick for $7,686. Legal fees of $2,257 were paid for title investigation and drawing the purchase contract. Coronado paid $2,684 to an engineering firm for a land survey, and $82,960 for drawing the factory plans. The land survey...

  • Shamrock Co. purchased land as a factory site for $432,000. The process of tearing down two...

    Shamrock Co. purchased land as a factory site for $432,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $45,360 to raze the old buildings and sold salvaged lumber and brick for $6,804. Legal fees of $1.998 were paid for title investigation and drawing the purchase contract. Shamrock paid $2,376 to an engineering firm for a land survey, and $73.440 for drawing the factory plans. The land survey...

  • Flounder Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site a...

    Flounder Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $51,240 to raze the old buildings and sold salvaged lumber and brick for $7,686. Legal fees of $2,257 were paid for title investigation and drawing the purchase contract. Flounder paid $2,684 to an engineering firm for a land survey, and $82,960 for drawing the factory plans. The land survey...

  • Oriole Co. purchased land as a factory site for $408,000. The process of tearing down two...

    Oriole Co. purchased land as a factory site for $408,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $42,840 to raze the old buildings and sold salvaged lumber and brick for $6,426. Legal fees of $1,887 were paid for title investigation and drawing the purchase contract. Oriole paid $2,244 to an engineering firm for a land survey, and $69,360 for drawing the factory plans. The land survey...

  • Larkspur Co. purchased land as a factory site for $568,000. The process of tearing down two...

    Larkspur Co. purchased land as a factory site for $568,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $59,640 to raze the old buildings and sold salvaged lumber and brick for $8,946. Legal fees of $2,627 were paid for title investigation and drawing the purchase contract. Larkspur paid $3,124 to an engineering firm for a land survey, and $96,560 for drawing the factory plans. The land survey...

  • Teal Co. purchased land as a factory site for $488,000. The process of tearing down two...

    Teal Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $51,240 to raze the old buildings and sold salvaged lumber and brick for $7,686. Legal fees of $2,257 were paid for title investigation and drawing the purchase contract. Teal paid $2,684 to an engineering firm for a land survey, and $82,960 for drawing the factory plans. The land survey...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT