Question

QUESTION 11 4 As the CFO of a company, you consider the following three projects: NPV 60.5K 66.6K 42.0K Project Investment 50K 60K 40K Unfortunately, the company has only S100,000 available for investment. Which projects do you choose based on weighted average profitability index (WAPI):? Proiect A alone Project A + Project B Project A + Project C Project B + Project C D.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We can calculate the profitability index of each project:

Profitability index (PI)=(Investment+NPV)/Investment:

Project NPV Inv PI
A 60.5 50 2.21
B 66.6 60 2.11
C 42 40 2.05

Hence we shall select A and B but total outlay shall exceed:

Hence if A and C selected, NPV=60.5+42=102.50

if B and C selected, NPV=66.6+42=108.6

Project B and Project C shall be selected.

Hence option D is correct

Add a comment
Know the answer?
Add Answer to:
QUESTION 11 4 As the CFO of a company, you consider the following three projects: NPV...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • If a company must choose between two mutually exclusive investment projects, the best general method to...

    If a company must choose between two mutually exclusive investment projects, the best general method to employ for decision-making purposes is: Cash-flow bailout Cash-flow break-even Net Present value (NPV) Discounted payback Accounting (book) rate of return, based on average investment over the life of each project The profitability index (PI) is calculated as: Net present value (NPV) divided by average investment New present value (NPV) divided by initial investment Average investment divided by net present value (NPV) Initial investment divided...

  • Given the following information, in which order would you choose the following projects based on the...

    Given the following information, in which order would you choose the following projects based on the profitability index? Project A (NPV of cash flows: $190,000, Investment Cost: $50,000) Project B (NPV of cash flows: $200,000, Investment Cost: $70,000) Project C (NPV of cash flows: $440,000, Investment Cost: $110,000) Project B, Project C then Project A Project C, Project B then Project A Project A, Project C then Project B Project A, Project B then Project C Project C, Project A...

  • Consider the following two mutually exclusive projects: Year CF of Project A CF of Project B...

    Consider the following two mutually exclusive projects: Year CF of Project A CF of Project B 0 -$350,000 -$50,000 1 45,000 24,000 2 65,000 22,000 3 65,000 19,500 4 440,000 14,600 Whichever project you choose, if any, you require a 15 percent return on your investment. a)If you apply the payback (PB) criterion, which investment will you choose? Why? b)If you apply the NPV criterion, which investment will you choose? Why? c)If you apply the IRR criterion, which investment will...

  • Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0...

    Consider the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$ 360,000 –$ 45,000 1 35,000 23,000 2 55,000 21,000 3 55,000 18,500 4 430,000 13,600    Whichever project you choose, if any, you require a return of 14 percent on your investment. c-1 What is the NPV for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)       c-2 If you apply the NPV...

  • Consider the following two mutually exclusive projects: Year FNM Cash Flow (A) -$256,924 27,200 58,000 58,000...

    Consider the following two mutually exclusive projects: Year FNM Cash Flow (A) -$256,924 27,200 58,000 58,000 428,000 Cash Flow (B) -$15,486 5,007 8.930 13,709 8,052 Whichever project you choose, if any, you require a 6 percent return on your investment. e. What is the NPV for Project A? f. What is the NPV for Project B ? g. What is the IRR for Project A? h. What is the IRR for Project B? i. What is the profitability index for...

  • Hi, I have a question regarding #17, (f). On the solution, it says "NPV doesn't have...

    Hi, I have a question regarding #17, (f). On the solution, it says "NPV doesn't have ranking problem." What does it mean by that? Thank you very much in advance! x Step 30 of 30 Final decision: In this case, according to NPV criterion, Project A should be selected but according to payback period, discounted payback period, IRR, and profitability index criterion, Project B should be selected. But, the final outcome should be based on NPV because compared to other...

  • Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$...

    Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$ 350,000 –$ 50,000 1 45,000 24,000 2 65,000 22,000 3 65,000 19,500 4 440,000 14,600 Whichever project you choose, if any, you require a 15% return on your investment. a-1. What is the payback period for each project? (Round the final answers to 2 decimal places.) Payback Period Project A years Project B years a-2. If you apply the payback criterion, which investment will...

  • Consider the following two mutually exclusive projects: Cash Flow Year 0 Cash Flow (B) - $...

    Consider the following two mutually exclusive projects: Cash Flow Year 0 Cash Flow (B) - $ 50,000 24,000 22,000 19,500 14, 600 - $ 350,000 45,000 65,000 65,000 440,000 AM + Whichever project you choose, if any, you require a 15% return on your investment. a-1. What is the payback period for each project? (Round the final answers to 2 decimal places.) Payback Period Project A Project B years years a-2. If you apply the payback criterion, which investment will...

  • 11 Consider the following two mutually exclusive projects: Cash Flow Cash Flow Year (A) (B) 3342,000...

    11 Consider the following two mutually exclusive projects: Cash Flow Cash Flow Year (A) (B) 3342,000 250,500 53,000 24,800 73,000 22,800 73,000 20,300 448,000 15,400 AWNO Book Hint Print Whichever project you choose, if any, you require a return of 14 percent on your investment erences a-1 What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Project A Project B انمي | N| 22 a-2 If...

  • The CFO of a major corporation is trying to decide on what project to pursue using...

    The CFO of a major corporation is trying to decide on what project to pursue using different investment criteria: Net Present Value (NPV), Payback Period, Discounted Payback Period, Internal Rate of Return (IRR), and the Profitability Index (PI). The CFO has four projects to choose between: Project W (which is a strip mine - see problem 6), Project X, Project Y, and Project Z. Additional information about each project is summarized below You can use the workspace provided to help...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT