Question

Vernon Manufacturing Co. expects to make 30,600 chairs during the 2017 accounting period. The company made 4,400 chairs in Ja

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

January

February

Price

$39.73

$46.35

--Working

January

February

Material cost

$16,800

$9,500

Labor Cost

$24,700

$12,000

A

Total Variable cost

$41,500

$21,500

B

Units produced

4400

1500

C = A/B

Variable cost per unit

$9.43

$14.33

D

Manufacturing Overhead rate ($612000/30600 units)

$20.00

$20.00

E = C+D

Total Cost per unit

$29.43

$34.33

F = E x 35%

Markup 35%

$10.30

$12.02

G = E+F

Price

$39.73

$46.35

Add a comment
Know the answer?
Add Answer to:
Vernon Manufacturing Co. expects to make 30,600 chairs during the 2017 accounting period. The company made...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Campbell Manufacturing Co. expects to make 31,700 chairs during the 2017 accounting period. The company made...

    Campbell Manufacturing Co. expects to make 31,700 chairs during the 2017 accounting period. The company made 4,200 chairs in January. Materials and labor costs for January were $16,200 and $24,100, respectively. Campbell produced 1,500 chairs in February. Material and labor costs for February were $8,600 and $12,800, respectively. The company paid the $475,500 annual rental fee on its manufacturing facility on January 1, 2017. Required Assuming that Campbell desires to sell its chairs for cost plus 40 percent of cost,...

  • Baird Manufacturing Co. expects to make 31,300 chairs during the 2017 accounting period. The company made...

    Baird Manufacturing Co. expects to make 31,300 chairs during the 2017 accounting period. The company made 3,500 chairs in January. Materials and labor costs for January were $17,500 and $25,200, respectively. Baird produced 1,300 chairs in February Material and labor costs for February were $9,300 and $13,800, respectively. The company paid the $313,000 annual rental fee on its manufacturing facility on January 1, 2017 Required Assuming that Baird desires to sell its chairs for cost plus 15 percent of cost,...

  • Perez Manufacturing Co. expects to make 30,300 chairs during the 2017 accounting period. The company made...

    Perez Manufacturing Co. expects to make 30,300 chairs during the 2017 accounting period. The company made 4,700 chairs in January. Materials and labor costs for January were $17,100 and $25,500, respectively. Perez produced 2,300 chairs in February Material and labor costs for February were $9,300 and $13,600, respectively. The company paid the $484,800 annual rental fee on its manufacturing facility on January 1, 2017 Required Assuming that Perez desires to sell its chairs for cost plus 10 percent of cost,...

  • Jordan Manufacturing Co. expects to make 31,000 chairs during the year 1 accounting period. The company...

    Jordan Manufacturing Co. expects to make 31,000 chairs during the year 1 accounting period. The company made 5,100 chairs in January. Materials and labor costs for January were $16,700 and $25,700, respectively. Jordan produced 2,400 chairs in February. Material and labor costs for February were $9,600 and $13,800, respectively. The company paid the $248,000 annual rental fee on its manufacturing facility on January 1, year 1. Required Assuming that Jordan desires to sell its chairs for cost plus 50 percent...

  • xercise 4-11A (Algo) How the allocation of fixed cost attects a pricing decision LO 4-3 Adams...

    xercise 4-11A (Algo) How the allocation of fixed cost attects a pricing decision LO 4-3 Adams Manufacturing Co. expects to make 30,900 chairs during the year 1 accounting period. The company made 3.800 chairs in January. Materials and labor costs for January were $17,900 and $24,800, respectively. Adams produced 1,900 chairs in February Material and labor costs for February were $9,500 and $12,400, respectively. The company paid the $401.700 annual rental fee on its manufacturing facility on January 1, year...

  • Vernon Services Company has 51 employees, 25 of whom are assigned to Division A and 26...

    Vernon Services Company has 51 employees, 25 of whom are assigned to Division A and 26 to Division B. Vernon incurred $307,530 of fringe benefits cost during year 2. Required Determine the amount of the fringe benefits cost to be allocated to Division A and to Division B. Division Allocated Cost A B Production workers for Walton Manufacturing Company provided 330 hours of labor in January and 660 hours in February. Walton expects to use 4,000 hours of labor during...

  • Production workers for Thornton Manufacturing Company provided 430 hours of labor in January and 660 hours...

    Production workers for Thornton Manufacturing Company provided 430 hours of labor in January and 660 hours in February. Thornton expects to use 4,000 hours of labor during the year. The rental fee for the manufacturing facility is $7,000 per month. Required Based on this information, how much of the rental cost should be allocated to the products made in January and to those made in February? (Do not round intermediate calculations.) points Month Allocated Cost (8 01:48:59 January February eBook...

  • Vernon Corporation estimated its overhead costs would be $23,600 per month except for January when it...

    Vernon Corporation estimated its overhead costs would be $23,600 per month except for January when it pays the $133,950 annual insurance premium on the manufacturing facility. Accordingly, the January overhead costs were expected to be $157,550 ($133,950 + $23,600). The company expected to use 7,200 direct labor hours per month except during July, August, and September when the company expected 9,300 hours of direct labor each month to build inventories for high demand that normally occurs during the Christmas season....

  • Production workers for Rooney Manufacturing Company provided 410 hours of labor in January and 680 hours...

    Production workers for Rooney Manufacturing Company provided 410 hours of labor in January and 680 hours in February. Rooney expects to use 4,000 hours of labor during the year. The rental fee for the manufacturing facility is $9,000 per month. Required Based on this information, how much of the rental cost should be allocated to the products made in January and to those made in February? (Do not round intermediate calculations.) 3:19 Allocated Cost Month January February

  • Vernon Manufacturing Company was started on January 1, 2018, when it acquired $84,000 cash by issuing...

    Vernon Manufacturing Company was started on January 1, 2018, when it acquired $84,000 cash by issuing common stock. Vernon immediately purchased office furniture and manufacturing equipment costing $7,700 and $25,300, respectively. The office furniture had an 8-year useful life and a zero salvage value. The manufacturing equipment had a $3,100 salvage value and an expected useful life of three years. The company paid $11,400 for salaries of administrative personnel and $15,100 for wages to production personnel. Finally, the company paid...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT