Answer is not $30 F.
Teel Printing uses two measures of activity, press runs and book set-ups, in the cost formulas in its budgets and performance
0 0
Add a comment Improve this question Transcribed image text
Answer #1
A spending variance is the difference between the actual and expected (or budgeted) amount of an expense. The spending variance for direct labor is known as the labor rate variance, and is the actual labor rate per hour minus the standard rate per hour, multiplied by the number of hours worked
Particulars Standard labour wages Actual cost of wages Spending Variance
Salaries 8850
Run expences for 201 runs 80400
Book setup expenses for 110 104500
193750 193780 -30
So the answer is $30 U
Add a comment
Know the answer?
Add Answer to:
Answer is not $30 F. Teel Printing uses two measures of activity, press runs and book...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Teel Printing uses two measures of activity, press runs and book set-ups, in the cost formulas...

    Teel Printing uses two measures of activity, press runs and book set-ups, in the cost formulas in its budgets and performance reports. The cost formula for wages and salaries is $8,850 per month plus $400 per press run plus $950 per book set-up. The company expected its activity in July to be 204 press runs and 111 book set-ups, but the actual activity was 201 press runs and 110 book set-ups. The actual cost for wages and salaries in July...

  • Teel Printing uses two measures of activity, press runs and book set-ups, in the cost formulas...

    Teel Printing uses two measures of activity, press runs and book set-ups, in the cost formulas in its budgets and performance reports. The cost formula for wages and salaries is $8,850 per month plus $400 per press run plus $950 per book set-up. The company expected its activity in July to be 204 press runs and 111 book set-ups, but the actual activity was 201 press runs and 110 book set-ups. The actual cost for wages and salaries in July...

  • eel Printing uses two measures of activity, press runs and book set-ups, in the cost formulas...

    eel Printing uses two measures of activity, press runs and book set-ups, in the cost formulas in its budgets and performance reports. The cost formula for wages and salaries is $8,850 per month plus $400 per press run plus $950 per book set-up. The company expected its activity in July to be 204 press runs and 111 book set-ups, but the actual activity was 201 press runs and 110 book set-ups. The actual cost for wages and salaries in July...

  • TB MC Qu. 9-342 Teel Printing uses two measures... Teel Printing uses two measures of activity,...

    TB MC Qu. 9-342 Teel Printing uses two measures... Teel Printing uses two measures of activity, press runs and book set-ups, in the cost formules in its budgets and performance reports. The cost formula for wages and salaries is $8,850 per month plus $400 per press run plus $950 per book set-up. The company expected its activity in July to be 204 press runs and 111 book set-ups, but the actual activity was 201 press runs and 110 book set-ups....

  • TB MC Qu. 9-342 Teel Printing uses two measures... Teel Painting uses two measures of activity...

    TB MC Qu. 9-342 Teel Printing uses two measures... Teel Painting uses two measures of activity pressure and book set-ups in the cost forms in its budgets and performance reports. The cost formula for wages and salaries is $8.850 per month plus $400 per press un plus $950 per book setup. The company expected its activity in July to be 204 press runs and 11 book set but the actual activity was 201 press runs and book setups. The actual...

  • Kudej Printing uses two measures of activity, press runs and book set-ups, in the cost formulas...

    Kudej Printing uses two measures of activity, press runs and book set-ups, in the cost formulas in its budgets and performance reports. The cost formula for wages and salaries is $8,360 per month plus $570 per press run plus $910 per book set-up. The company expected its activity in May to be 194 press runs and 74 book set-ups, but the actual activity was 195 press runs and 72 book set-ups. The actual cost for wages and salaries in May...

  • The following information relates to questions 19 through 22. Prime Printing uses two measures of activity,...

    The following information relates to questions 19 through 22. Prime Printing uses two measures of activity, press runs and book set-ups, in the cost formulas in its budgets and performance reports. The cost formula for wages and salaries is $7,220 per month plus $650 per press run plus $1,110 per book set-up. The company expected its activity in January to be 188 press runs and 117 book set-ups, but the actual activity was 191 press runs and 114 book set-ups....

  • Borunda Air uses two measures of activity, flights and passengers, in the cost formulas in its...

    Borunda Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $40,500 per month plus $2,898 per flight plus $13 per passenger. The company expected its activity in July to be 126 flights and 326 passengers, but the actual activity was 129 flights and 323 passengers. The actual cost for plane operating costs in July was $403,540. The activity variance for plane operating...

  • Herrod Catering uses two measures of activity, jobs and meals, in the cost formulas in its...

    Herrod Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $530 per month plus $102 per job plus $33 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in December to be 10 jobs and 133 meals, but the actual activity was 5 jobs and...

  • Standahl Air uses two measures of activity, flights and passengers, in the cost formulas in its...

    Standahl Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $39,590 per month plus $2,649 per flight plus $4 per passenger. The company expected its activity in August to be 82 flights and 294 passengers, but the actual activity was 85 flights and 297 passengers. The actual cost for plane operating costs in August was $255,690. The spending variance for plane operating...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT