Question

Check my Problem 7-1B Determine the acquisition cost of land and building (LO7-1) 1.66 points The Italian Pizza Company purch

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans..

Particulars Land Building
Purchase cost of Land $             85,000
Land Clearing Costs $               4,500
Sale of firewood to a worker $                 (450)
Title Investigation of Land $               3,000
Property taxes on Land $               2,500
Architect Fees (New Building) $         25,000
Buildng Construction Costs $      350,000
Total $             94,550 $      375,000
Add a comment
Know the answer?
Add Answer to:
Check my Problem 7-1B Determine the acquisition cost of land and building (LO7-1) 1.66 points The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 7-1B Determine the acquisition cost of land and building (LO7-1) The Italian Pizza Company purchased land as a f...

    Problem 7-1B Determine the acquisition cost of land and building (LO7-1) The Italian Pizza Company purchased land as a factory site for $89,000. Prior to construction of the new building, the land had to be cleared of trees and brush. Construction costs incurred during the first year are listed below: Problem 7-1B Determine the acquisition cost of land and building (LO7-1) The Italian Pizza Company purchased land as a factory site for $89,000. Prior to construction of the new building,...

  • The Italian Pizza Company purchased land as a factory site for $73,000. Prior to construction of...

    The Italian Pizza Company purchased land as a factory site for $73,000. Prior to construction of the new building, the land had to be cleared of trees and brush. Construction costs incurred during the first year are listed below: Land clearing costs Sale of firewood to a worker Architect fees (for new building) Title investigation of land Property taxes on land (for the first year) Building construction costs $ 3,300 (570) 13,000 1,800 1,300 230,000 Required: Determine the amounts that...

  • Online Assignment #1: Determine the acquisition cost of land and building P7-1A The Italian Bread Company...

    Online Assignment #1: Determine the acquisition cost of land and building P7-1A The Italian Bread Company purchased land as a factory site for $70,000. An old building on the . property was demolished, and construction began on a new building. Costs incurred during the first year are listed as follows: Demolition of old building Sale of salvaged materials Architect fees (for new building) Legal fees (for title investigation of land) Property taxes on the land (for the first year) Building...

  • Exercise 10-1 Acquisition costs; land and building [LO10-1] On March 1, 2018, Beldon Corporation purchased land...

    Exercise 10-1 Acquisition costs; land and building [LO10-1] On March 1, 2018, Beldon Corporation purchased land as a factory site for $73,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,500 Architect’s fees (for new building) 12,000 Legal fees for title investigation of land 2,000 Property taxes on land (for period beginning March...

  • Acquisition of Land and Building On February 1, 2019, Edwards Corporation purchased a parcel of land...

    Acquisition of Land and Building On February 1, 2019, Edwards Corporation purchased a parcel of land as a factory site for $120,000. It demolished an old building on the property and began construction on a new building that was completed on October 2, 2019. Costs incurred during this period are: Demolition of old building $ 10,000 Architect's fees 20,000 Legal fees for title investigation and purchase contract 5,000 Construction costs 625,000 Edwards sold salvaged materials resulting from the demolition for...

  • On March 1, 2021, Beldon Corporation purchased land as a factory site for $75,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are list

    On March 1, 2021, Beldon Corporation purchased land as a factory site for $75,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building$6,500Architect’s fees (for new building)14,000Legal fees for title investigation of land3,000Property taxes on land (for period beginning March 1, 2021)4,500Construction costs650,000Interest on construction loan7,500 Salvaged materials resulting from the demolition of the old building were...

  • On March 1, 2021, Beldon Corporation purchased land as a factory site for $63,000. An old...

    On March 1, 2021, Beldon Corporation purchased land as a factory site for $63,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building Architect's fees (for new building) Legal fees for title investigation of land Property taxes on land (for period beginning March 1, 2021) Construction costs Interest on construction loan $ 5,500 15,000 3,500...

  • Exercise 7-1A Record purchase of land (LO7-1) McCoy's Fish House purchases a tract of land and...

    Exercise 7-1A Record purchase of land (LO7-1) McCoy's Fish House purchases a tract of land and an existing building for $800,000. The company plans to remove the old building and construct a new restaurant on the site. In addition to the purchase price, McCoy pays closing costs, including title insurance of $1,000. The company also pays $10,000 in property taxes, which includes $7,000 of back taxes (unpaid taxes from previous years) paid by McCoy on behalf of the seller and...

  • s101(LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related o land, land...

    s101(LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related o land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. . Money borrowed to pay building contractor (signed a note) h Payment for construction from note proceeds $(275,000) 275,000 c. Cost of land fill and clearing d. Delinquent real estate taxes on property assumed by purchaser e. Premium on 6-month insurance policy during construction fRefund of 1-month insurance...

  • On March 1, 2021, Beldon Corporation purchased land as a factory site for $74,000. An old...

    On March 1, 2021, Beldon Corporation purchased land as a factory site for $74,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building Architect's fees (for new building) Legal fees for title investigation of land Property taxes on land (for period beginning March 1, 2021) Construction costs Interest on construction loan $ 6,000 13,000 2,500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT