Question

Work in Process Inventory, August 1 20,000 units Direct materials: 100% complete $80,000 24,000 104,000 45,000 Conversion: 20% complete Balance in work in process, August 1 $ Units started during August Units completed and transferred in August work in process (70% complete), August 31 Costs charged to Work in Process in 57,000 7 August 166,000 Direct materials Conversion costs Direct labor Overhead applied 104,000 142,000 246,000 Total conversion Assume materials are added at the start of processing Instructions a. Calculate the equivalent units for the Forming Department for the month of August. rect Conversion Materials Equivalent units b. Find the cost per equivalent unit of input resource. (Round your answers to 2 decimal places.) rect Conversion Materials Cost per equivalent unit

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • All working forms part of the answer
  • Requirement ‘a’

EUP - Weighted Average Method

Units

% Material

Direct Materials

% Conversion

Conversion

Units TRANSFERRED

57,000

100%

57,000

100%

57,000

Units of ENDING WIP [20000 + 45000 – 45000]

8,000

100%

8,000

70%

5,600

Equivalent Units of Production

65,000 = Answer

62,600 = Answer

  • Requirement ‘b’

COST per EUP

Direct Material

Conversion

Cost of Beginning WIP

$          80,000.00

$                                  24,000.00

Cost incurred during the period

$        166,000.00

$                                246,000.00

Total Costs

Costs

$        246,000.00

Costs

$                                270,000.00

Equivalent units of production

EUP

65,000

EUP

62,600

Cost per EUP = Answer

$              3.78 = Answer

$                                      4.31 = Answer

  • NOTE: The above answers are based on Weighted Average Method.
    If answers are required by FIFO Method, please let me know through comments.
Add a comment
Know the answer?
Add Answer to:
Work in Process Inventory, August 1 20,000 units Direct materials: 100% complete $80,000 24,000 104,000 45,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Badgersize Company has the following information for its Forming Department for the month of August. Work in Process In...

    Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials 80,000 24,000 104,000 54,000 58,000 ? 157,000 Conversion costs: Direct labor 112,000 Overhead applied 147,000 259,000...

  • The answers that I got before were: A) for Direct materials is $237,000 and for conversion...

    The answers that I got before were: A) for Direct materials is $237,000 and for conversion is $283,000 B) For direct materials is 3.20 and for conversion is 4.09. The assignment said that these were not correct. Thank you in advance for your help! Badgersize Company has the following information for its Forming Department for the month of August. $ 80,000 24,000 $ 104,000 54,000 58,000 Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20%...

  • Badgersize Company has the following information for its Forming Department for the month of August. $...

    Badgersize Company has the following information for its Forming Department for the month of August. $ 80,000 24,000 104,000 53,000 58,000 Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied Total conversion $ 136,000...

  • Explanations for each answer are appreciated. Badgersize Company has the following information for its Forming Department...

    Explanations for each answer are appreciated. Badgersize Company has the following information for its Forming Department for the month of August Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $80,000 24,000 $ 104,000 48,000 56,000 conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs Direct labor...

  • Hi, would you help me with the solution of the problem below? Thanks Tanya Badgersize Company...

    Hi, would you help me with the solution of the problem below? Thanks Tanya Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $ 80,000 Conversion: 20% complete 24,000 Balance in work in process, August 1 $ 104,000 Units started during August 50,000 Units completed and transferred in August 60,000 Work in process (70% complete), August 31 ? Costs charged to Work...

  • Badgersize Company has the following information for its Forming Department for the month of August. Work...

    Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,900 units Direct materials: 100% complete s 80,eee 24,e00 $104,00e 55,e00 56,000 conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied $138,000 $117,e00 147,000 $264,006e...

  • Transferred to finished goods in August Inventory in process, August 31 Total units to be assigned...

    Transferred to finished goods in August Inventory in process, August 31 Total units to be assigned costs Cost Information Costs per equivalent unit: Total costs for August in Roasting Department Total equivalent units Cost per equivalent unit (2) Costs assigned to production: Direct Inventory in process, August 1 Costs incurred in August Total costs accounted for by the Roasting Department Costs allocated to completed and partially completed units: Inventory in process, August 1 balance To complete inventory in process, August...

  • Badgersize company

    Badgersize Company has the following information for its Forming Department for the month of August:Work in Process Inventory, August 1: 20,000 unitsDirect materials: 100% complete $ 80,000Conversion: 20% complete 24,000Balance in work in process, August 1 $ 104,000Units started during August 50,000Units completed and transferred in August 60,000Work in process (70% complete), August 31 ?Costs charged to Work in Process in AugustDirect materials $ 150,000Conversion costs:Direct labor $ 120,000Overhead applied 132,000Total conversion $ 252,000Assume materials are added at the start...

  • For the "to complete inventory in process august 1" how did you get $840? The debits...

    For the "to complete inventory in process august 1" how did you get $840? The debits to Work in Process --Roasting Department for Morning Brew Coffee Company for August 2016, together with information concerning production, a as follows: 53479 Work in process, August 1, 700 pounds, 20% completed "Direct materials (700x $4.70) Conversion (700 x 20% x $1.35) $3200 $1479 65.780 21.942 Coffee beans added during August 14.300 pounds Conversion costs during August Work in process, August 31, 400 pounds,...

  • The debits to Work in Process—Roasting Department for Morning Brew Coffee Company for August, together with...

    The debits to Work in Process—Roasting Department for Morning Brew Coffee Company for August, together with information concerning production, are as follows: Work in process, August 1, 400 pounds, 60% completed $2,232* *Direct materials (400 X $4.5) $1,800 Conversion (400 X 60% X $1.8) 432 $2,232 Coffee beans added during August, 13,000 pounds 57,850 Conversion costs during August 24,605 Work in process, August 31, 700 pounds, 70% completed ? Goods finished during August, 12,700 pounds ? All direct materials are...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT