Answer
EUP - Weighted Average Method |
Units |
% Material |
Direct Materials |
% Conversion |
Conversion |
Units TRANSFERRED |
57,000 |
100% |
57,000 |
100% |
57,000 |
Units of ENDING WIP [20000 + 45000 – 45000] |
8,000 |
100% |
8,000 |
70% |
5,600 |
Equivalent Units of Production |
65,000 = Answer |
62,600 = Answer |
COST per EUP |
Direct Material |
Conversion |
|||
Cost of Beginning WIP |
$ 80,000.00 |
$ 24,000.00 |
|||
Cost incurred during the period |
$ 166,000.00 |
$ 246,000.00 |
|||
Total Costs |
Costs |
$ 246,000.00 |
Costs |
$ 270,000.00 |
|
Equivalent units of production |
EUP |
65,000 |
EUP |
62,600 |
|
Cost per EUP = Answer |
$ 3.78 = Answer |
$ 4.31 = Answer |
Work in Process Inventory, August 1 20,000 units Direct materials: 100% complete $80,000 24,000 104,000 45,000...
Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials 80,000 24,000 104,000 54,000 58,000 ? 157,000 Conversion costs: Direct labor 112,000 Overhead applied 147,000 259,000...
The answers that I got before were:
A) for Direct materials is $237,000 and for conversion is
$283,000
B) For direct materials is 3.20 and for conversion is 4.09.
The assignment said that these were not correct. Thank you in
advance for your help!
Badgersize Company has the following information for its Forming Department for the month of August. $ 80,000 24,000 $ 104,000 54,000 58,000 Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20%...
Badgersize Company has the following information for its Forming Department for the month of August. $ 80,000 24,000 104,000 53,000 58,000 Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied Total conversion $ 136,000...
Explanations for each answer are
appreciated.
Badgersize Company has the following information for its Forming Department for the month of August Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $80,000 24,000 $ 104,000 48,000 56,000 conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs Direct labor...
Hi, would you help me with the solution of the problem below? Thanks Tanya Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete $ 80,000 Conversion: 20% complete 24,000 Balance in work in process, August 1 $ 104,000 Units started during August 50,000 Units completed and transferred in August 60,000 Work in process (70% complete), August 31 ? Costs charged to Work...
Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,900 units Direct materials: 100% complete s 80,eee 24,e00 $104,00e 55,e00 56,000 conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied $138,000 $117,e00 147,000 $264,006e...
Transferred to finished goods in August Inventory in process, August 31 Total units to be assigned costs Cost Information Costs per equivalent unit: Total costs for August in Roasting Department Total equivalent units Cost per equivalent unit (2) Costs assigned to production: Direct Inventory in process, August 1 Costs incurred in August Total costs accounted for by the Roasting Department Costs allocated to completed and partially completed units: Inventory in process, August 1 balance To complete inventory in process, August...
Badgersize Company has the following information for its Forming Department for the month of August:Work in Process Inventory, August 1: 20,000 unitsDirect materials: 100% complete $ 80,000Conversion: 20% complete 24,000Balance in work in process, August 1 $ 104,000Units started during August 50,000Units completed and transferred in August 60,000Work in process (70% complete), August 31 ?Costs charged to Work in Process in AugustDirect materials $ 150,000Conversion costs:Direct labor $ 120,000Overhead applied 132,000Total conversion $ 252,000Assume materials are added at the start...
For the "to complete inventory in process august 1"
how did you get $840?
The debits to Work in Process --Roasting Department for Morning Brew Coffee Company for August 2016, together with information concerning production, a as follows: 53479 Work in process, August 1, 700 pounds, 20% completed "Direct materials (700x $4.70) Conversion (700 x 20% x $1.35) $3200 $1479 65.780 21.942 Coffee beans added during August 14.300 pounds Conversion costs during August Work in process, August 31, 400 pounds,...
The debits to Work in Process—Roasting Department for Morning Brew Coffee Company for August, together with information concerning production, are as follows: Work in process, August 1, 400 pounds, 60% completed $2,232* *Direct materials (400 X $4.5) $1,800 Conversion (400 X 60% X $1.8) 432 $2,232 Coffee beans added during August, 13,000 pounds 57,850 Conversion costs during August 24,605 Work in process, August 31, 700 pounds, 70% completed ? Goods finished during August, 12,700 pounds ? All direct materials are...