A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 White Lion Cages Date Requeste*(a) Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost of completed Job

Direct material 4850
Direct labor 1200
Manufacturing overhead 1500
Total Cost 7550
Unit cost 3.02

1) Source document

Direct material = Material requisition form

Direct labor = Time ticket

Manufacturing overhead = Predetermine overhead rate

2) Predetermine overhead rate = 625/500 = 125% of direct labor

3) Total cost of the completed Job = 7550

Unit cost of completed Job = $3.02

Add a comment
Know the answer?
Add Answer to:
A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost...

    A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 2,500 7/2 7/31 Manufacturing Overhead Date 7/10 700 900 12 15 400 400 500 500 22 24 1,625 1,525 27 31 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (a) Answer the following questions. (1) What are the source documents...

  • Ajob cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet...

    Ajob cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 2,500 7/2 7/31 Manufacturing Overhead 800 900 Date 7/10 12 15 22 24 27 31 500 400 625 500 1,675 1,550 700 875 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct...

  • Question 1 of 3 A job cost sheet of Sandoval Company is given below. JOB NO....

    Question 1 of 3 A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 2,500 7/2 7/31 Manufacturing Overhead Date 7/15 700 900 12 500 400 300 375 15 22 24 27 31 1,675 1,575 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are...

  • A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 2,500...

    A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 2,500 469 Quantity White Lion CagesDate Requested ITEM 7/2 FOR Todd Company Date Completed 7/31 Direct Materials Direct Labor Manufacturing Overhead Date 700 900 600 750 400 500 1,650 1,525 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs...

  • CES Exercise 2-6 (Video) (Part Level Submission) A job cost sheet of Sandoval Company is given...

    CES Exercise 2-6 (Video) (Part Level Submission) A job cost sheet of Sandoval Company is given below. vel 2.000 JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 7/2 7/31 Manufacturing Overhead on) Date 7/10 700 900 500 300 600 360 udy. 1,640 1,600 700 840 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (a) Answer the following questions. (1) What...

  • Exercise 2-6 (Part Level Submission) A job cost sheet of Sandoval Company is given below. Job...

    Exercise 2-6 (Part Level Submission) A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 440 550 22 380 475 24 1,600 27 1,500 31 540 675 Cost of completed job:          Direct materials          Direct labor           Manufacturing overhead        Total cost        Unit cost (1)...

  • Ajob cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR 2.500 7/2 7/31...

    Ajob cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR 2.500 7/2 7/31 Manufacturing Overhead Date 7/10 Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 700 900 600 300 1,625 1,525 700 12 750 15 22 24 375 27 31 875 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct...

  • A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR 2.440 7/2...

    A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR 2.440 7/2 7/31 Manufacturing Overhead Date 7/10 Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 748 919 494 339 1,680 1,510 608 417 660 812 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing...

  • Current Attempt in Progress A job cost sheet of Sandoval Company is given below. JOB NO....

    Current Attempt in Progress A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company. Date Completed Direct Direct Materials Labor 2,390 7/2 7/31 Manufacturing Overhead Date 7/10 745 901 411 345 514 431 1,670 1,580 825 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct materials, direct...

  • A job cost sheet of Ivanhoe Company is given below. JOB NO. 469 Job Cost Sheet...

    A job cost sheet of Ivanhoe Company is given below. JOB NO. 469 Job Cost Sheet Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor FOR 2.500 7/2 7/31 Manufacturing Overhead Date 7/10 700 900 400 1,675 1,575 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Your answer is partially correct. Try again. Answer the following questions. (1) What are the source documents for direct materials, direct labor, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT