Tannin Products
Inc. Factory Overhead Cost Variance Report : Trim Department For the month ended July 31 |
||||
Productive capacity for the month 12,000 hrs. |
||||
Actual productive capacity used for the month : 7,000 hrs. | ||||
Actual |
Budget ( at actual production ) |
Unfavorable Variances | Favorable Variances | |
Variable factory overhead costs | ||||
Indirect factory labor | $ 21,840 | $ 22,400 | $ 560 | |
Power and light | 5,160 | 5,250 | 90 | |
Indirect materials | 8,100 | 7,700 | $ 400 | |
Total variable factory overhead cost | 35,100 | 35,350 | 400 | 650 |
Fixed factory overhead costs | ||||
Supervisory salaries | 36,940 | 36,940 | 0 | 0 |
Depreciation of plant and equipment | 9,720 | 9,720 | 0 | 0 |
Insurance and Property Taxes | 18,140 | 18,140 | 0 | 0 |
Total fixed factory overhead cost | 64,800 | 64,800 | 0 | 0 |
Total factory overhead cost | 99,900 | 100,150 | 400 | 650 |
Total controllable variances | 400 | 650 | ||
Net controllable variance | 250 Favorable |
Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July...
Factory Overhead Cost Variance Report
Tannin Products Inc. prepared the following factory overhead
cost budget for the Trim Department for July of the current year,
during which it expected to use 14,000 hours for production:
Variable overhead costs:
Indirect factory labor
$47,600
Power and light
10,360
Indirect materials
15,400
Total variable overhead cost
$73,360
Fixed overhead costs:
Supervisory salaries
$56,430
Depreciation of plant and equipment
14,850
Insurance and property taxes
27,720
Total fixed overhead cost
99,000
Total factory overhead cost...
Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 24,000 hours for production: 1 Variable overhead cost: 2 Indirect factory labor $57,600.00 3 Power and light 14,400.00 4 Indirect materials 24,000.00 5 Total variable overhead cost $96,000.00 6 Fixed overhead cost: 7 Supervisory salaries $55,000.00 8 Depreciation of plant and equipment 39,200.00 9 Insurance and property taxes 152,300.00 10 Total fixed overhead cost...
Factory Overhead Cost Variance Report Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 13,000 hours for production: Variable overhead costs: Indirect factory labor $40,300 Power and light 9,750 Indirect materials 19,500 Total variable overhead cost $ 69,550 Fixed overhead costs: Supervisory salaries $56,200 Depreciation of plant and equipment 14,790 Insurance and property taxes 27,610 Total fixed overhead cost 98,600 Total factory overhead...
Factory Overhead Cost Variance Report Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 13,000 hours for production: $40,300 9,360 19,500 $ 69,160 Variable overhead cost: Indirect factory labor Power and light Indirect materials Total variable overhead cost Fixed overhead cost: Supervisory salaries Depreciation of plant and equipment Insurance and property taxes Total fixed overhead cost $58,140 15,300 28,560 102,000 $171,160 Total factory...
Factory Overhead Cost Variance Report Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 12,000 hours for production: Variable overhead costs: Indirect factory labor $28,800 Power and light 8,880 Indirect materials 13,200 Total variable overhead cost $ 50,880 Fixed overhead costs: Supervisory salaries $46,510 Depreciation of plant and equipment 12,240 Insurance and property taxes 22,850 Total fixed overhead cost 81,600 Total factory overhead...
ucts Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 10,000 hours for production: 7.300 16,000 Variable overhead cost: Indirect factory labor $28.000 Power and light Indirect materials Total variable overhead cost $ 51,300 Fored overhead cost: Supervisory salaries Depreciation of plant and equipment Insurance and property taxes Totale overhead cost 82.600 Total factory overhead cost $13.900 Tannin has available 14,000 hours of monthly productive...
Factory Overhead Cost Variance Report
Tannin Products Inc. prepared the following factory overhead
cost budget for the Trim Department for July of the current year,
during which it expected to use 20,000 hours for production:
Variable overhead costs:
Indirect factory labor
$46,000
Power and light
12,000
Indirect materials
20,000
Total variable overhead cost
$78,000
Fixed overhead costs:
Supervisory salaries
$54,500
Depreciation of plant and equipment
40,000
Insurance and property taxes
35,500
Total fixed overhead cost
130,000
Total factory overhead cost...
Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 22,000 hours for production: 1 Variable overhead cost: 2 Indirect factory labor $55,000.00 3 Power and light 11,000.00 4 Indirect materials 22,000.00 5 Total variable overhead cost $88,000.00 6 Fixed overhead cost: 7 Supervisory salaries $52,600.00 8 Depreciation of plant and equipment 39,400.00 9 Insurance and property taxes 137,500.00 10 Total fixed overhead cost...
Tiger Equipment Inc., a manufacturer of construction equipment, prepared the following factory overhead cost budget for the Welding Department for May of the current year. The company expected to operate the department at 100% of normal capacity of 8,400 hours. Variable costs: Indirect factory wages $30,240 Power and light 20,160 Indirect materials 16,800 Total variable cost $67,200 Fixed costs: Supervisory salaries $20,000 Depreciation of plant and equipment 36,200 Insurance and property taxes 15,200 Total fixed cost 71,400 Total factory overhead...
Tiger Equipment Inc., a manufacturer of construction equipment, prepared the following factory overhead cost budget for the Welding Department for May of the current year. The company expected to operate the department at 100% of normal capacity of 8,400 hours. Variable costs: Indirect factory wages Power and light Indirect materials Total variable cost $30,240 20,160 16,800 $67,200 Fixed costs: Supervisory salaries $20,000 Depreciation of plant and equipment 36,200 Insurance and property taxes 15,200 Total fixed cost 71,400 Total factory overhead...